An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Detroit Intermodal Freight Terminal (DIFT) Study TBWG April 23, 2013

  2. Detroit Intermodal FreightTerminal Study • Capacity of terminals and coordination of rail lines is inadequate • Addresses needs of intermodal transportation in southeast Michigan

  3. Purpose To support the economic competitiveness of southeast Michigan and the state by improving freight transportation opportunities and efficiencies for business and industry.

  4. NEED • Additional intermodal terminal capacity • Better coordination between rail terminals • Better interface between public road system (primarily interstate freeways) and rail facilities • Efficiency of business and industry • Better connectivity between railroads

  5. Projected 2025 Intermodal Demand

  6. Study Chronology • 1993-94: Early Assessment of Need and Vision • 2001: Feasibility Study • 2002: Environmental Impact Statement (EIS) Started • 2003: EIS Alternatives Expanded Based on Public Input • 2004: EIS Prepared in Preliminary Form for MDOT/Review • 2005: DEIS Presented to Public • 2009: FEIS Presented to Public • 2010: Record of Decision

  7. Public Comments700 pages of Transcripts and Comments1300 Individual Comments • The “No Action” alternative is not acceptable • Minimize the “footprint” of the Livernois Junction Yard expansion • Get trucks out of the neighborhoods.

  8. Selected Alternative Proposes intermodal operations of CSX, Norfolk Southern and Canadian Pacific be consolidated at the site of the Livernois-Junction Yard in southwest Detroit

  9. Selected Alternative responds to public comments by: • Reducing the “footprint” of Livernois-Junction Yard • Promoting collaborative efforts between MDOT, the Community and the Railroads to improve Livernois-Junction Yard • Providing direct truck access to Livernois-Junction Yard via major roadways

  10. Intermodal Terminal Locations

  11. Livernois-Junction Yard

  12. DEIS - Alternative 3 Selected Alternative

  13. 22 fewer businesses to be acquired 96 fewer acres to be acquired

  14. Acreage and Property to be Acquired • 169 Acres • 28 single family Homes • 4 multiple family homes • 29 Businesses or institutions

  15. Split of intermodal truck traffic between Wyoming ( 63%) and Livernois (37%).

  16. Key Features • Grade Separation at Central Avenue • Barrier Walls Designed to also Reduce Noise and Visual Impacts • Paving of Livernois-Junction Yard • Local Road Improvements Including Sidewalks, Streetscaping and Lighting • Landscaped Buffer

  17. Benefits • Permanent net jobs gained • In terminal area: +2,300+ • Statewide: 4,500+ • Construction jobs (FTEs): 620 in peak year • Fewer long haul trucks on I-94 and I-75 • Reduces congestion • Reduces emissions • Improves safety

  18. Benefits(continued) • More efficient, integrated transportation system promotes business • Government revenue gain $1.1 billion (2008 $’s) • Elimination of Waterman/Dix Gate at Livernois Junction Yard • Elimination of 2 at-grade railroad crossings • Terminal Gates at Livernois Avenue and Wyoming Avenue only

  19. Project Costs - A Public Private Partnership • Improvements (% are Gov vs RR) • Terminals - $248 million 50% / 50% • External Rail Improvement - $99 million 50% / 50% • Roads - $92 million 100% / 0% • Land Acquisition/Relocation - $100 million 100%/ 0%** • Estimate Total Capital Cost $539 million **Land will be leased back to the railroads at fair market value

  20. On-Going Activities • DIFT Five Year Plan • DIFT Project Agreement • Delray Interlocking • West Detroit Connection Project • Economic Development Plan • Milwaukee/Beaubien Interlocking

  21. DIFT 5-Year Program List of the first projects Broken down by individual railroad “Rolling 5-Year” program of projects Agreed upon by MDOT and the individual railroad

  22. DIFT Projects

  23. DIFT Projects

  24. Questions/Comments DIFT Website Search: Michigan.gov/mdot/studies