An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. IT PROJECTS(UNDER CAO/FOIS) PROGRESS AND CONCERNS AUGUST 2006

  2. STRUCTURE OF PRESENTATION • OVERVIEW • AREAS REQUIRING BOARD’S INTERVENTION • PROJECT SPECIFIC DETAILS

  3. OUR TASK - THIS YEAR

  4. GROWTH OF IT PROJECTS ON IR • IR’s capital budget for IT is Rs. 273 crore in 2006-07 • It is projected to increase to about Rs. 900 crore to Rs. 1200 crore by 2010 – 2011 • To make this scale of operation possible, requirement of space and other facilities for CRIS and FOIS organization needs to be significantly increased

  5. OUTLAY FOR PROJECTS UNDER CAO/FOIS

  6. IMPORTANT PROJECTS • COA (Control Charting) • FOIS (Freight Operations Information System) • CMS (Crew Management System) • ICMS (Integrated Coach Management System)

  7. MAJOR ISSUES NEEDING BOARD’s INTERVENTION

  8. STATUS – CONTROL CHARTING (COA) • Pilot project under trial at Madurai and Trivandrum divisions of SR • DOMs/SrDOMs visiting TVC/MDU and their reports being sent to CRIS continuously for necessary changes/enhancements • Tender for customization of software for IR under finalization in CRIS. • Tender for hardware and roll out to 23 divisions also under finalization in CRIS (Phase I) • Strategy for roll out – In three phases • Phase I – SR, SCR, SWR, CR, ECOR, SECR • Phase II – WR, WCR, NCR, NR, NWR • Phase III – SER, ER, ECR, NER. NFR (all detail at http://it.indianrail.gov.in)

  9. CONTROL CHARTING (COA) – TYPICAL CHART Chart and Advance Plotting FOIS COIS NTES CMS

  10. ISSUES – CONTROL CHARTING (COA) • Integration with dataloggers (1437 already installed & number growing) • Integration with FOIS, COIS, CMS and other public interface systems like NTES, Call centers etc • Record keeping of Control chart information – policy for archival

  11. IMPACT ON TARGET – CONTROL CHARTING (COA) • Board’s target for IR (76 locations/ 284 boards) – Mar 2007 • Latest review with CRIS indicates that software and hardware may become available by Dec 2006 • Roll out @ 7 locations per month

  12. DECISION/ASSITANCE-COA • Telecom and C&IS directorates to resolve the issue of supply of data by datalogger vendors to enable development of interface of COA with networked dataloggers • Safety and C&IS directorates to help freeze archival policy

  13. ISSUES-FOIS • V-SAT INSTALLATION AT 214 TMS SITES • EQUIPMENTS AVAILABILITY • RAILWAY’S INVOLVEMENT • CHANGED TRAFFIC PATTERN

  14. FOIS TMS Module • 524* locations on IR (all details at http://it.indianrail.gov.in) • 214 locations on VSAT • 324 locations online covering 376 sites • 126 locations printing RR online covering 176 sites • Around 1100 PCs and 400 printers supplied so far • 668 PCs and 612 printers under supply (within 45 days) *(3 locations of SR – 1 as P2, 1 closed, 1 HOM port location didn’t commission at all.)

  15. VSAT – BASIC FACTS • ON 21/12/04 BOARD (ML/MT/FC) APPROVED SETTING UP OF RAILWAY HUB & PURCHASE OF VSATs BY IRPMU WITH FOLLOWING FEATURES: • MASTER EARTH STATION IN KU BAND WITH AUTOTRACKING • 200 VSAT TERMINALS WITH DATA & VOICE CAPABILITY • SETTING UP OF NMS NETWORK • PAYMENT TO DOT FOR COMMERCIAL/CAPTIVE VSAT SERVICES WITH CUG CAPABILITY • HIRING OF QUARTER TRANSPONDER • AMC WITH OEM FOR MAINTENANCE SUPPORT FOR HUB & TERMINAL • CAO/FOIS TO MONITOR PROJECT & IRPMU TO NOMINATE ONE DY. CSTE EXCLUSIVELY • HIRE VSAT WITHIN 3 MONTHS & SETTING UP OF A HUB WITHOUT AFFECTING FOIS TERMINAL

  16. TMS VSAT locations • 214 TMS locations have to be commissioned on VSATs by IRPMU • Railway Board’s target was June 2006. IRPMU’s revised target is Sept 2006 • 74 VSATs covered upto 17.8.06

  17. IMPACT ON TARGET-FOIS • V-SAT DEPENDENT TMS SITES(214) WILL TAKE LONGER TO STABLISE • RESPONSE TIME ISSUES (1500 vs700 msecs) • CHANGE IN HUB FROM VENDOR’S TO OUR OWN (Realignment of each dish)

  18. Problems relating to the VSAT Network • Response time excessive – timed out if data packet size exceeds 1000 bytes • Voice communication yet to be provided • Video conferencing facility between CRIS, Railway Board and zonal railway HQs required

  19. GENERAL ISSUES- V-SAT • HECL CONTRACT - 235 (± 25%) • Requirement as of now - 477 • HUB CAPACITY-500 (CAN GO UPTO 1000) • TRANSPONDER HIRING ISSUE

  20. DECISION/ASSITANCE-FOIS • Board’s directive for AT/generator supply from station to TMS site • Nomination of 2 Rates Inspectors by each zone to CAO/FOIS for verification of referential database and testing of software changes due to rates circulars

  21. STATUS-CMS • Detailed estimate of Rs 38.16 crores sanction by Railway Board. • 302 lobbies to be covered, out of which 259 are integrated lobbies (presently around 60%). (all details at http://it.indianrail.gov.in) • Target for completion March 2007

  22. STATUS-CMS • Application under development and testing for • Freight module • Coaching, shunting and pilot module • Suburban module • Site Preparation • Lump sum amount sanctioned @ Rs 1,31,728 for major and Rs 82,890 for minor lobbies • Target for readiness Aug 2006 • Terminal Equipment • Under vetting • Target of Phase I supply - Dec 2006 • Datacom Equipment • Under vetting. Will be procured through CRIS • Training • Core group and core implementers will be trained at CRIS • Core group identified on all 16 zonal railways • Training labs being set up at 5 locations

  23. ISSUES - CMS • Difference in interpretation of Board’s circulars by zonal railways in calculation of running allowance • Integration of lobbies

  24. IMPACT ON TARGET-CMS • Board’s target – 302 sites by Mar 2007 • Latest review with CRIS indicates software and hardware will be available only by Dec 2006. • Going by the FOIS and other roll out experience, commissioning of 30 sites per month would be a reasonable target

  25. DECISION/ASSITANCE-CMS Nomination of Committee of ED s of Electrical, Mechanical, Personnel & Finance for practice to be adopted for computation of running allowance and other issues / business reengineering Details of sample issues

  26. STATUS-ICMS Enhanced scope • Punctuality Module • Module is being tested on NDLS & MAS • Coaching Stock Management Module • Being implemented in three phases • Software ready and under field trials at Nizamuddin & Chennai • Ready for roll out • Timetabling Module • Time table simulation module’s system requirements under discussion

  27. STATUS-ICMS • Enhanced scope (contd) • Coaching Stock Maintenance Module • Scope of Mechanical module has been enhanced from capturing of coaching depot maintenance related activities to automation of C&W department • It covers 154 depots & 975 coaching locations. • It covers 331 depots & 973 electrical locations. • Scope of Electrical Maintenance module defines only 8 technical modules developed by NR under MIS projects. It also does not give assessment of hardware & user specifications.

  28. ICMS – Coaching Stock Management Module • Phase I – 114 terminals at 41 locations Target for implementation 31st Aug 2006 • Phase II - 78 terminals at 34 locations Target for implementation 31st Oct 2006 • Phase III - 128 terminals at 58 locations Target for implementation 31st Dec 2006 (all details at http://it.indianrail.gov.in) • Training • 186 staff from 136 locations trained so far • Training labs being set up to take care of additional training needs • Equipment • Thin clients and printers supplied to all locations • Datacom equipment- 57 LAN extenders supplied. Rest under supply • 14 locations commissioned – NR-1, WR-9, SECR-3 & SR-1 • 107 locations have been provided connectivity. • Target likely to be met

  29. ISSUES-ICMS • Freezing the scope of Mechanical & Electrical Maintenance Modules – Railway Board • Supply of datacom equipment by CRIS & commissioning of 59 VSAT locations

  30. IMPACT ON TARGET-ICMS • Three months delay due to supply of UPS and datacom equipment

  31. DECISION/ASSITANCE-ICMS • C&IS directorate to facilitate freezing of scope for Mechanical & Electrical Maintenance Modules in view of dropping of work from MIS • C&IS directorate to sanction & release funds for time tabling module.

  32. GENERAL ISSUES -INFRASTRUTURE • INVESTMENT • SPACE-BLDG • MANPOWER • DISASTER TOLERANCE – VSAT HUB ISSUE

  33. GENERAL ISSUES -TRAINING • CURRICULAM IN TRAINING INSTITUTES-TRAFFIC,MECHANICAL,ELECTRICAL-MPP DTE’S ROLE • ADDITIONALTRAINING CENTERS –5 (DLI,SC,BB,HWH,TPJ)

  34. Increase in strength of FOIS and space requirement

  35. SPACE - CRIS location

  36. SPACE – Area with Railways

  37. Required facilities for expansion Secure areas in red Restricted areas in orange Open access in green

  38. THANK YOU