1 / 34

The Edward St. John Student Center

The Edward St. John Student Center. Zachary Haupt Faculty Advisor: Dr. William Bahnfleth 11 April 2011. Presentation Outline. Project Background Existing Mechanical Summary Design Objectives Alternative Descriptions Ground Source Heat Pumps Enthalpy Wheel Solarban 70XL Glass

oleg-beck
Download Presentation

The Edward St. John Student Center

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Edward St. John Student Center Zachary Haupt Faculty Advisor: Dr. William Bahnfleth 11 April 2011

  2. Presentation Outline • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations

  3. Presentation Outline Project Information: Delivery Method - Design-Bid-Build Operational Date - September 2012 Occupancy - K-12 Boarding School Size - 68,000 SF Cost - $16,000,000 • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations Primary Project Team: Owner - McDonogh School Architect - Bowie Gridley Architects Civil Engineer - Matis Warfield MEP Engineer - James Posey Associates, Inc Structural Engineer - Linton Engineers, LLC

  4. Presentation Outline • Mechanical System: • 8 indoor AHUs • 7 VAV units • 5 single zone VAV units • 2 multizone VAV units • 1 single zone CAV unit • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations • Central Plant: • Located on campus • 3 Boilers • 2 Chillers Student Center

  5. Building Layout • Lower Level • AHU – 3 Serves Lecture Hall • AHU – 4 Serves Dance Studio • AHU – 5 Serves LS Dining • AHU – 1 Serves Lower & Quad Levels AHU – 3 AHU – 4 AHU – 1 AHU – 5

  6. Building Layout • Quad Level • AHU 6 & 7 Serve US Dining • AHU – 2 Serves Senior Dining • AHU – 1 Serves Lower & Quad Levels AHU – 1 AHU – 6 & 7 AHU – 2

  7. Building Layout • Upper Level • AHU – 8 Serves Entire Floor AHU – 8

  8. Presentation Outline • Improve System Performance • Energy Consumption • Emissions • Total System Costs • Minimize Payback Periods • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations

  9. Presentation Outline Solarban 70XL Ground Source Heat Pumps Enthalpy Wheel Solarban 70XL Ground Source Heat Pumps Enthalpy Wheel • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations The Bad The Bad The Bad The Good The Good The Good • Increased Construction Costs • Increased Construction Time • Impact of Loop on Ecosystem • Increased Construction Costs • Increased Size and Weight to AHU • Increased Capital Costs • Slight Decrease to Daylighting • Higher System Efficiencies • Lower Greenhouse Gas Emissions • Low Maintenance • Low Air Pressure Drop • Higher System Efficiencies • Decentralized System • Lower Greenhouse Gas Emissions • Provides Lower Heat Gain • No Added Maintenance • Large Array of Shading Choices

  10. Presentation Outline Implementing a GSHP • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations • Site Geology Study • Calculations • Pipe Sizing • Pump & System Layout • Results

  11. Located in Baltimore County Implementing a GSHP • Precambrian Soil Type • 15% Water and Sandstone • Soil Resistivity ≈ 0.6 BTU/hr· ft· °F • Site Geology Study • Calculations • Pipe Sizing • Pump & System Layout • Results

  12. McClure Company Spreadsheet & ASHRAE Implementing a GSHP ASHRAE Loop Sizing • Vertical Loop Analysis • Used to Determine # of Bores + Depths • Cross Checked With ASHRAE • Site Geology Study • Calculations • Pipe Sizing • Pump & System Layout • Results

  13. Bores Per Pump Implementing a GSHP Selected Pump Model • 750 Total GPM – 125 Total Bores • 6 GPM Per Bore • Site Geology Study • Calculations • Pipe Sizing • Pump & System Layout • Results Cost Of Pipe

  14. Layout of System Implementing a GSHP • 5 Pumps • Each Pump Serves 12 Bores • 5 Pumps • Each Pump Serves 13 Bores • Site Geology Study • Calculations • Pipe Sizing • Pump & System Layout • Results

  15. Energy Savings Annual Energy Consumption (Existing vs. GSHP) Implementing a GSHP • 5.7 % Annual Heating Savings • 12.4 % Annual Cooling Savings • 9.9 % Total Annual Energy Savings • Site Geology Study • Calculations • Pipe Sizing • Pump & System Layout • Results

  16. Presentation Outline Selecting a Wheel • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations • Determine supply air total flow (CFM) • Use SEMCO wheel chart • Keep face velocity ≈ 800 (FPM) • Calculate unit effectiveness • Results

  17. AHU - 8 Selecting a Wheel • Serves art classrooms • Scheduled at 15,000 CFM • Determine supply air total flow (CFM) • Use SEMCO wheel chart • Keep face velocity ≈ 800 (FPM) • Calculate unit effectiveness • Results

  18. AHU - 8 Selecting a Wheel • Find desired CFM • Read directly right until model intersection (closest to 800 FPM) • Mark model # down • Read directly down to find associated pressure loss • Determine supply air total flow (CFM) • Use SEMCO wheel chart • Keep face velocity ≈ 800 (FPM) • Calculate unit effectiveness • Results

  19. AHU - 8 Selecting a Wheel • Use calculations to determine unit effectiveness • ≈ 80% Good • Determine supply air total flow (CFM) • Use SEMCO wheel chart • Keep face velocity ≈ 800 (FPM) • Calculate unit effectiveness • Results

  20. Energy Savings Selecting a Wheel Annual Energy Consumption (Existing vs. Wheel) • 17.0 % Annual Heating Savings • 3.4 % Annual Cooling Savings • 8.4 % Total Annual Energy Savings • Determine supply air total flow (CFM) • Use SEMCO wheel chart • Keep face velocity ≈ 800 (FPM) • Calculate unit effectiveness • Results

  21. Presentation Outline Structural Check • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Structural Breadth • Solarban 70XL Glass • System Comparison • Final Recommendations • Calculate lb/ft2for each AHU • Calculate new lb/ft2 for AHU 8 • Check slab strength • Adjust accordingly • Check beam strength • Adjust accordingly

  22. Calculations Structural Check • Locate AHU Schedule • Mark Weight, Width, & Length of each AHU Located in Room • Calculate lb/ft2 of Each AHU • Calculate lb/ft2for each AHU • Calculate new lb/ft2 for AHU 8 • Check slab strength • Adjust accordingly • Check beam strength • Adjust accordingly

  23. Calculations Structural Check • AHU 6 Dropped • Wheel Adds • 2’ in Length • 1,300 lbs • Calculate lb/ft2for each AHU • Calculate new lb/ft2 for AHU 8 • Check slab strength • Adjust accordingly • Check beam strength • Adjust accordingly

  24. Calculations Structural Check • Rebar Spaced Every 14” O.C. • Slab Fails Under New Load • Space Rebar Every 12” O.C. • Recheck Slab • Calculate lb/ft2for each AHU • Calculate new lb/ft2 for AHU 8 • Check slab strength • Adjust accordingly • Check beam strength • Adjust accordingly

  25. Calculations Structural Check • Slab Does Not Fail • Adjust Rebar Spacing • Analyze Beam • Calculate lb/ft2for each AHU • Calculate new lb/ft2 for AHU 8 • Check slab strength • Adjust accordingly • Check beam strength • Adjust accordingly

  26. Calculations Structural Check • Beam Analyzed in spBeam • Sized Beam Cross Checked With Scheduled Beam • Scheduled Beam Well Oversized • Beam Holds New Load • Calculate lb/ft2for each AHU • Calculate new lb/ft2 for AHU 8 • Check slab strength • Adjust accordingly • Check beam strength • Adjust accordingly • Adjust accordingly

  27. Presentation Outline Installing Solarban 70XL Glass • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations • Calculate Total Amount of Glazing • Calculate Cost of Glazing • Analyze Glazing Properties • Results

  28. Total Glazing • Review Architectural Drawings Installing Solarban 70XL Glass • Calculate Total Amount of Glazing • Calculate Cost of Glazing • Analyze Glazing Properties • Results

  29. Cost • Multiply Glass SF By $/SF • Analyze 3 Types of Glass Installing Solarban 70XL Glass • Calculate Total Amount of Glazing • Calculate Cost of Glazing • Analyze Glazing Properties • Results

  30. Performance • Installed Values Obtained From Drawings • Upgraded Values Obtained From PPG Industries Installing Solarban 70XL Glass • Calculate Total Amount of Glazing • Calculate Cost of Glazing • Analyze Glazing Properties • Results

  31. Energy Savings Installing Solarban 70XL Glass • 6.6 % Annual Heating Savings • 16.7 % Annual Cooling Savings • 13 % Total Annual Energy Savings • Calculate Total Amount of Glazing • Calculate Cost of Glazing • Analyze Glazing Properties • Results

  32. Presentation Outline • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations 3 Year Payback Period 2.5 Year Payback Period 12 Year Payback Period 12.5 Year Payback Period 2.5 Year Payback Period

  33. Presentation Outline Final Recommendations • Project Background • Existing Mechanical Summary • Design Objectives • Alternative Descriptions • Ground Source Heat Pumps • Enthalpy Wheel • Solarban 70XL Glass • System Comparison • Final Recommendations • Maximize Distance Between Cost & Payback Period • Analyze Owner’s Intentions • Make Suggestion

  34. Special Thanks To: Questions Or Comments • Justin Bem • Dr. Bahnfleth • Penn State AE Mechanical Faculty • Family & Friends

More Related