1 / 57

ATLAS

ATLAS. Calorimetria Elettromagnetica. G.C. Costa. INFN Milano. calorimetria elettromagnetica L AR. Consuntivo attivita’ 2004 Programma 2005. ECA. Barrel. ECC. Detector barrel diviso in due ruote: ruota A e ruota C. Lar: stato e richieste.

olive
Download Presentation

ATLAS

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ATLAS Calorimetria Elettromagnetica G.C. Costa INFN Milano Commissione I "LAr: stato e richieste"

  2. calorimetria elettromagnetica L AR • Consuntivo attivita’ 2004 • Programma 2005 Commissione I "LAr: stato e richieste"

  3. ECA Barrel ECC Detector barrel diviso in due ruote: ruota A e ruota C Lar: stato e richieste • Stato della Calorimetria a Liquid Argon di ATLAS • Attività del gruppo di Milano: • Software HV • Ricostruzione del segnale • Test-beam • Misure col TDR • Integrazione servizi Endcap • Calibrazioni e analisi canale H • Identificazione di leptoni t • Studio ETmiss Attività di commissioning Barrel: em calorimeter + presampler Endcap: em calorimeter + presampler + adronico + forward Commissione I "LAr: stato e richieste"

  4. Stato del rivelatore • In B 180: • Sul calorimetro elettromagnetico barrel il 27 agosto sono stati completati tutti i tests elettrici a freddo. Iniziata subito dopo la fase di warm up attualmente calorimetro sotto tensione 50 V. • Misure sistematiche LC, TPA, dei canali di lettura e R e TDR sulle linee di calibrazione • Test con un crate equipaggiato con FEB • Test HV di tutto il calorimetro e presampler tra 0 e 2000 V alcuni settori del calorimetro e del presampler hanno mostrato problemi ad alta tensione. Commissione I "LAr: stato e richieste"

  5. Calorimetro barrel Commissione I "LAr: stato e richieste"

  6. Barrel Transport Commissione I "LAr: stato e richieste"

  7. Barrel Transport TRANSPORT SPECIFICATION * This condition on the time imposed to distinguish a sinusoidal excitation (engine) from the shock caused by a road imperfection Commissione I "LAr: stato e richieste"

  8. Transport to the pit: 26 October 2004, proposed date by TC Commissione I "LAr: stato e richieste"

  9. Endcap C • Stato ECC: • Tutti i detector nel criostato • Saldatura covers quasi completato, preparazione per cool-down in corso. Inizio cool-down 27/9 • Programma di test elettrici simile a quello del barrel Commissione I "LAr: stato e richieste"

  10. Criostato end-cap Welding of cold cover Criostato ECC Commissione I "LAr: stato e richieste"

  11. Cool down dell’End Cap Inizio della fase di cooldown per ECC a fine settembre Studiate due possibili metodi: a) raffredamento utilzzando un flusso di He tempo stimato 20g, He piu’ efficiente ma maggiore rischio (vento di 10m/s che potrebbe gettare tutta l’eventuale polvere in avanti sul calo EM). b) raffreddamento utilizzando lo scambiatore con N2 piu’ lento stimato 60 g, considerato un processo meno a rischio scelta la soluzione b) se risulta poco efficiente si potrebbe passare alla a) Commissione I "LAr: stato e richieste"

  12. Endcap A • Stato ECA (integrazione): • EMECPS: nel criostato, cablato e testato • EMEC: nel criostato, cablato e testato • HEC wheels: HEC1 nel criostato in survey, HEC2 pronta per l’inserimento • FCAL: inserzione a novembre Commissione I "LAr: stato e richieste"

  13. SCHEDULE ECA(1) Commissione I "LAr: stato e richieste"

  14. Schedule pit • Barrel lowered ~ end October • 2004 finish the Barrel Tile • 2005: February-March : our infrastructure (incl. FE Crates) • 2005 April-August: Barrel on Truck, well accessible to us for FE installation • LV PS, All boards in FE,… • One FEIC, 5 people over 2 FEC (n, n+1) in one week • ECC ready for the pit end may 2005 • Transport and lowering ECC afterwards • Services installation on ECC ( ~ottobre 2005) • ECA in the pit end 2005 • Installation ECA services: beginning 2006 Commissione I "LAr: stato e richieste"

  15. Attivita’ HV L .Carminati, M. Mazzanti, F. Tartarelli • Milano è responsabile del software di controllo dell’HV di tutta la calorimetria LAr di ATLAS: • endcap, barrel; em, hadronico e forward; LAr purity monitors • Circa 4900 canali con tensioni da 600 a 2500 V • Moduli ditta Iseg (Germania) • Acquistati da Wuppertal + KTH + CERN • CANbus, OPC server • OPC client: scritto dallo user finale (Milano) usando PVSSII • PVSSII (sistema commerciale SCADA della ETM (Austria)) fa: Controllo, monitoring, trending, alarm handling • Milano ha realizzato e gestisce i programmi HV per 3 set-up: • B180 (cold test del barrel), H8 (CBT), H6 (CBT-Endcap) • B180 Cold test ECC,…ECA Commissione I "LAr: stato e richieste"

  16. Barrel Calo: 50V LAr gas, after long term 2000V cold test and Lar emptying short in LAr, remain after emptying Short in LAr, gone after emptying 50V LAr gas Red line: Isolated electrode Green rectangle: Zone cured after Lab cold test Un settore HV: DhxDf=0.2x0.2 2 linee HV (32 elettrodi) 0.2% totale Commissione I "LAr: stato e richieste"

  17. PRESAMPLER STATUS 50 V in LAr gas after cold test at 2000V Burned. Now holds 2000V. Initially appeared at warm Commissione I "LAr: stato e richieste"

  18. S/B S/B loss (%) low mass tails (%) Commissione I "LAr: stato e richieste"

  19. La “signal reconstruction”: Richiede conoscenza della funzione di trasferimento della linea di calibrazione Linea non ideale, va modellizzata Scopo delle misure TDR: individuazione di caratteristiche o anomalie di cui tener conto nella ricostruzione dei segnali Ultimo controllo prima del pit, verifica installazione linee Misure TDR effettuate: sul Test beam (a caldo ed a freddo) linee di calibrazione di alcuni FT del Barrel (a caldo) TUTTE le linee di calibrazione BARREL a freddo Misure di riflettometria nel dominio del tempo (TDR) Commissione I "LAr: stato e richieste"

  20. With MUX Without MUX MUX Misure TDR • Automatizzazione sistema: • Multiplexer • Labview per controllo MUX e TDR • Ricerca online di linee fuori tolleranza • Performance: • 1 FT (128 canali) ogni circa 30 min • 64 FT (wheel A+C) da misurare • Distorsione della forma del segnale introdotta dal MUX: • In corso di studio: si riesce a ricostruire la lunghezza della linea senza MUX da quella con MUX con una precisione del 0.3 ns Commissione I "LAr: stato e richieste"

  21. Tutte le linee sono all`interno dell`intervallo di tolleranza delle impedenze dei cavi Axon. black TDR profile (TB ft=1,short line) green Z0=50 (Hspice simulation) red Z=Z0  2 (Hspice simulation) 3 ns Risulati Barrel(preliminari) Sett.A Sett.B Estrazione lunghezze cavi Axon: • 2 “famiglie” nel Settore A • 7 “famiglie” nel Settore B Spread delle lunghezze  in una singola famiglia 31.5 ns (30cm). Probabilmente questa differenza e` data dalla differenza in impedenza dei cavi. Ft 0 Ft 1 Commissione I "LAr: stato e richieste"

  22. Risulati Barrel(preliminari) Ottima correlazione tra le lunghezze estratte dai profili misurati col MUX e quelle senza MUX. Possiamo predire dalle misure col MUX la lunghezza “vera” delle linee, cioe` quella senza MUX. Commissione I "LAr: stato e richieste"

  23. Linee anomale Z~ 50 -----------------calibrazione----------------------- Modulo FT Harness Canale Condizione M05 10 calB 48 “aperto instabile” al livello della MB ad alta frequenza M05 9 calA 62 aperto al livello della MB  Gia` noto P03 4 calB 24-25 “aperto instabile” al livello della MB ad alta frequenza P05 9 calA 38 strano comportamento P14 26 calB 21 strano comportamento, non terminato a 50ohm Commissione I "LAr: stato e richieste"

  24. Test beam combinato • Dati raccolti: • Elettroni, pioni e muoni in energie tra 9 e 350 GeV. • Diversi punti in h, uno scan esteso a 250 Gev (tutte le celle), 180, 150, 100, 50, 20, 10 GeV • con diversi materiali davanti al criostato (Al plates: 0; 0.3; 0.6; 0.9 X0). • Da fare: • Scansione fine per “ presampler study” • Studi di HV • VLE run (1 GeV-9 GeV) • Runs con campo magnetico , “Bremsstrahlungs recovery” • 25ns run • Presa dati con fotoni in Novembre • Completare Delay runs (signal reconstruction, OF) • Combined Calorimetry • ~ 2200 runs, ~ 0.6 TB • Full combined • ~ 1200 runs, ~ 0.4 TB [Event size ~ 50 kB/event including headers] Commissione I "LAr: stato e richieste"

  25. TB schedule Commissione I "LAr: stato e richieste"

  26. Data Taking Activities (B. Di Girolamo) • Run periods as in the official schedule: • First combination • July 5th: Tilecal and LAr calorimeters • August 9th: TRT, LAr, Tilecal, MDT, RPC, LVL1MUCTPI, EF • August 12th: Pixel added • August 27th: Restarted as combined calorimetry • Sept 7th: Restarted with Pixel, TRT, LAr, Tilecal, MDT, RPC, LVL1MUCTPI, EF • Starting from September 7th the system has been running quite smoothly. Occasional problems promptly solved. • Main focus now is to switch to a frozen configuration from September 15th to October 19th to take the core of the data needed to satisfy the physics program. • Waiting for the integration of • SCT: should be integrated soon • LVL1Calo: should be integrated soon • TGC, CSC: end September • CTP: end September Commissione I "LAr: stato e richieste"

  27. Clustering with TB data • “all3D” TopoCluster with EMB run 1004015 (250 GeV e) • Cubic interpolation reconstruction + DB for ped/ramp (“Half_Simple”) • NoiseSigma = 200 MeV, Seed s/N = 4, Neighbour s/N = 3, no corrections CLUSTER CELL SUM s = 4.8 GeV s = 8.0 GeV • Cluster improvement  40% relative (4.8 GeV / 244 GeV = 2.0%  8.0/243 = 3.3%) • Should be more pronounced with improved signal reconstruction • Available for online monitoring soon Commissione I "LAr: stato e richieste"

  28. Integrazione servizi EndCap • E’ stato effettuato uno studio dei servizi di barrel e endcap con modelli CAD a 3D per capire come posizionarli e installarli • Usati per far costruire al CERN due mockup (Barrel e EndCap) • criteri suddivisione servizi sono stati accettati dalla TC • Milano si è occupato principalmente dell’Endcap • Maturata expertise sull’Endcap • La Coll. LAr ha richiesto a Milano di assumere la responsibilita’ dell’installazione dei servizi End-cap Commissione I "LAr: stato e richieste"

  29. FASI DELL’INSTALLAZIONE ◊ 13 CRATES DI ELETTRONICA 4 DIFFERENTI TIPOLOGIE DI SERVIZI ( FCAL, EMEC, (HEC&EMEC-special),Crates-feet.reg.)) ◊ Operazioni in posizione Truck (garage) : cavi PS , coperture PS, installazione manifolds cavi LV, cavi di trigger, installazione delle box di monitoraggio ◊ Completamento dell’installazione con EC in posizione finale installazione parziale fibre TTC,cavi di trigger, installazione optical-boxes test delle “water lines”. (occorre un team di tre persone) Commissione I "LAr: stato e richieste"

  30. Servizi EC 13 crates Commissione I "LAr: stato e richieste"

  31. Particolari servizi EC Commissione I "LAr: stato e richieste"

  32. Schedule installazione servizi ECC • Servizi Endcap: • Optical links • ELMB (Power Supplies and crate monitor and control) • Water manifolds • Power cables • Low Voltage Power Supplies • … Commissione I "LAr: stato e richieste"

  33. Calibrazioni e analisi H→gg • Calcolo dei coefficienti di calibrazione del calorimetro in energia basato sulla ottimizzazione della risoluzione • Calibrazione utilizzata da tutte le produzioni DC1 (‘03/’04) • Cominciato lavoro per calibrare le produzioni DC2 (Geant 4): • Sviluppo codice per accedere agli hit nei materiali passivi • Upstream/downstream del calorimetro • Energia persa negli assorbitori del calorimetro (→sampling fraction) • Usiamo il canale H come benchmark per questi studi: • Inizio studio H prodotto via VBF con full simulation • Studio effetto tagli g-id Commissione I "LAr: stato e richieste"

  34. Identificazione t e ricostruzione ETmiss • Studii su grossi campioni DC1: • 350k eventi A/H→tt: 270k t adronici (generati Milano/CNAF) • 350k QCD evs: 1.1M candidati t • 120k tt events (Milano/CNAF) • Elect. noise (pile-up non ancora) • Algoritmi di t-ID: • Migliori risultati ottenuti con una likelihood basata su 7 variabili (incluso un taglio di sd/d della traccia più energetica) • Risultati un fattore 3 meglio del TDR • Calibrazione ETmiss: • Pesi alla H1: dipendono da ET e h • Nuovi pesi con più bin e pesi tunati su Etmiss • In corso una calibrazione che dipende dalla densita’ di energia nelle celle (e h) Nuova analisi con likelihood (88.5<PT<133.5) Analisi standard (88.5<PT<133.5) s(pxmiss,pymiss)=kSET Commissione I "LAr: stato e richieste"

  35. Attivita’ 2005 • Attivita’ HV: • Sviluppi SW e analisi dati raccolti • Estate ‘05: cold test dell’end-cap (ECA) al B180 • Installazione HV in USA15 e misure sul barrel nell’IP (M: da agosto ‘05) • Integrazione col resto del DCS di ATLAS (finora sistema stand-alone) • Integrazione con l’offline (formato dati, Conditions database) • Servizi End-cap: M: ~ fine Ottobre ‘05: inizio preparazione e integrazione dei servizi nel pit su ECC • Ricostruzione del segnale: • Analisi dati CBT e implementazione dell’algoritmo nel software online del Lar • Software: • Analisi dati del CBT (calibrazione di g e pioni) • Nuove simulazioni (DC2) basate su Geant4 e studio di performance • Studio di fondi fisici e pile-up Commissione I "LAr: stato e richieste"

  36. Aggiornamento milestones 2004 • Nuova Vecchia milestone • 30-10-04 30-06-04 SW ricostruzione Segnale pronto per CBT • 31-08-04 31-07-04 TDR su Barrel freddo • 30-10-04 31-08-04 Barrel nel pit • 28 -02-05 31-12-04 Studio uniformita’ Calo al CBT Commissione I "LAr: stato e richieste"

  37. Ricercatori : D. Banfi (Dottorando, 100%) L. Carminati (Ass. Uni., 100%) D. Cavalli (Dir. Ric., 80%) G. Costa (Dir. Ric., 100%) M. Delmastro (Ass. Uni., 100%) M. Fanti (Ric. Uni., 100%) L. Mandelli (PO, 100%) M. Mazzanti (1° Ric., 100%) L. Perini (PA, 100%) F. Tartarelli (Ric., 100%) Tecnologi: M. Citterio (1° Tec.,50%) S. Coelli (art. 23.,15%) Totale 10,45 PE Laureandi: A. Carioni, M. Consonni Tecnici: G.Braga (100%), B.Monticelli (100%), F.Alberti (50%) 4 mu tecnici Servizio Elettronica Composizione del gruppo Coordinatrice WG Jet, t e PTmiss Perf. LAr EM steering (membro) LAr representatives group (membro) Responsabile ATLAS Italia LAr representatives group (chairman) LAr steering group (membro) Lar electronic coordinator Commissione I "LAr: stato e richieste"

  38. Altre slides Commissione I "LAr: stato e richieste"

  39. Commissione I "LAr: stato e richieste"

  40. MOF Commissione I "LAr: stato e richieste"

  41. La voce C& I riguarda la copertura dei costi di commissioning relativi principalmente ai calorimetri EC C ed EC A nel 2005 C&I Commissione I "LAr: stato e richieste"

  42. La voce CC e ' relativa a : extra costi CORE, items CORE non coperti, costi di infrastrutture (Building 180)CC Commissione I "LAr: stato e richieste"

  43. Previsioni spese 06-07 Commissione I "LAr: stato e richieste"

  44. Materiale da acquistare per Servizi EC • Attrezzature varie , piegatura tubi 3.7 K € • Bulloneria, raccorderia, etc… 1.6 ” • Pompa per test impianti .2 ” • Dima “regolabile” per diff. config. 1.0 ” ________ Totale 6.5 K€ Commissione I "LAr: stato e richieste"

  45. Commissione I "LAr: stato e richieste"

  46. EC cool down procedure • HEC and FCAL, DT=40K • EMEC boundaries: Mechanical constraints limit the DT • Radial gradient less than 20K at start, going down to 6K! at liquid temperatures. • Front/back less than 10K • Interlock conditions on cryostat itself not yet fully defined. • Due to severe DT conditions, left with 2 options:

  47. Moduli (Crates) HV Iseg PC (Windows) PC (Windows) xx PVSS OPC Client OPC Server FW CANbus ethernet Strumenti software • Firmware nei moduli e crates; scritto da Iseg • OPC è una standardizzazione del concetto di driver: • OPC server: legge e interpreta i messaggi CAN in INPUT e OUTPUT; pubblica i dati in un formato standard; scritto da Iseg • OPC client: accede (lettura/scrittura) ai dati del server; scritto dall’utilizzatore finale (Milano) usando PVSS • PVSS è un sistema SCADA (Supervisory Control And Data Acquisition) commerciale della ETM (Austria) • CANbus, OPC e PVSS sono standards raccomandati dal CERN per il DCS a LHC Commissione I "LAr: stato e richieste"

  48. HV granularity • Calorimetro barrel (configurazione nominale): • 448 regioni di DhxDf=0.2x0.2 ognuna con 32 elettrodi e 64 semigaps (0.2% dell’accettanza) • Ogni regione e’ alimentata da 2 linee indipendenti: ogni linea alimenta 32 semigaps Commissione I "LAr: stato e richieste"

  49. Data Taking Activities • Data taken for specific studies: • High eta (0.7-1.2) scans with energies between 20 and 250 GeV (pions and electrons) • Studies with material in front of LAr calorimeter, fixed eta and energies between 9 and 250 GeV • Low eta (0.2-0.65) scans, with steps of 0.1 and 0.0025. Energies from 20 to 350 GeV • Muon stand alone studies • Sagitta resolution in the momentum range 120-350 GeV • LVL1 trigger studies • Many others. • Data taken (all runs, including those for test and debugging): • Muon system • ~ 1350 runs, ~ 0.1 TB • Combined Calorimetry • ~ 2200 runs, ~ 0.6 TB • Full combined • ~ 1200 runs, ~ 0.4 TB [Event size ~ 50 kB/event including headers] Commissione I "LAr: stato e richieste"

  50. Test BeamCalorimetro EM Larg Cubic interpolation + Ramp and Pedestal from Database: e 250 GeV/c Current situation: We don’t have yet Optimal Filtering Coefficients nor detailed Cell-to-Cell timing. Commissione I "LAr: stato e richieste"

More Related