Injection Test in Point 2. Hardware Commissioning. Beam 1 Internal. 07 Jul. 14 Jul. 21 Jul. 28 Jul. 04 Aug. Week 28. Week 29. Week 30. Week 31. Week 32. Sector 12 cool down, cryo tuning and ML2 boil offs. Sector 12 XL2 DFBX left of 2 consolidation & boil off.
E N D
Injection Test in Point 2 Hardware Commissioning Beam 1 Internal 07 Jul 14 Jul 21 Jul 28 Jul 04 Aug Week 28 Week 29 Week 30 Week 31 Week 32 Sector 12 cool down, cryotuning and ML2boil offs Sector 12 XL2 DFBX left of 2 consolidation & boil off Sector 12 XL2, ML2 ElQA, QPS IST and powering tests • Sector 12 partlycommissioned to 450 GeV • Injection system at Point 2 • Matching section left of Point 2 Q4, D2,DFBM, Q5, DFBM + associated correctors • Inner triplet left of Point 2 Q1, Q2, Q3, D1, DFBX + associatedcorrectors • Sector23 commissioned Roberto Saban