Financial Risk Analysis and Cost Reductions Alternatives for Dredging Projects. Karim El Kheiashy PhD MBA PMP PE Technical Manager; Bechtel Oil, Gas & Chemicals. Maurice "Zickie" Allgrove C.Eng . Director; Ports and Marine Terminals, Worley Parsons. Introduction Cost Breakdown

Download Presentation

Financial Risk Analysis and Cost Reductions Alternatives for Dredging Projects

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Financial Risk Analysis and Cost Reductions Alternatives for Dredging Projects Karim El Kheiashy PhD MBA PMP PE Technical Manager; Bechtel Oil, Gas & Chemicals. Maurice "Zickie" Allgrove C.Eng. Director; Ports and Marine Terminals, Worley Parsons

  2. Introduction • Cost Breakdown • Risk Analysis • Contingency Determination • Cost Reduction Alternatives Outline

  3. Land cost • Energy Exploration • Maritime Infrastructure • Industry Capacity • Funding Limitations The cost to replace the present system of locks is estimated at more than $125 billion. - ASCE Introduction

  4. Cost Breakdown

  5. Bare Costs • Bare costs are defined as cost in a project that have no markups included. This excludes productivity, overtime, • any tax adjustments, any direct cost markups, contractor markups, special markups or owner cost markup. • Direct Costs • Direct cost equal bare cost plus all direct cost adjustments (Direct Labor, Direct Equipment and Direct Sub Bid) which includes overtime and productivity, but does not included contractor payroll taxes and insurance (PTI). • Contract Cost • The Contract Cost includes the Cost to Prime plus the performing contractor’s markups, subcontractor markups, sub-subcontractor markups, etc. Contractor markups are already included in the Cost to Prime. PTI and any allowances, such as small tools, are applied to the contractor’s own work and then any indirect markups, such as job office overhead (JOOH), home office overhead (HOOH), profit, bond, excise tax, etc., are applied to the total. Special markups are included in the cost; however, they are only included as an additional cost that is not subject to further compounding by markups at higher levels. • Project Cost • The Project Cost includes the cost to owner plus any owner markups, such as escalation, contingencies, SIOH (owner’s supervision, inspection and overhead) and/or other costs as defined. • Cost to Prime • The Cost to Prime includes the direct cost plus all contractor markups that apply, up to the item/folder that is being viewed. That is, the cost to prime is the cost to the performing contractor, not including his own PTI and indirect markups. The cost to prime does include any sub or sub-subcontractor's PTI and indirect costs, but not the performing contractor’s PTI and indirect markups. For example, the cost to prime includes the direct cost of the prime contractor’s own work, the direct cost of their subcontractor’s work and the subcontractor’s PTI and indirect markups on their work. PTI and any allowances, such as small tools, are applied to the subcontractor's own work and then any indirect markups, such as JOOH, HOOH, profit, bond, excise tax, etc., are applied as defined by the estimator. Any subcontractor, sub-subcontractor, etc., special markups are also included in the cost to prime; however, they are only included as an additional cost that is not subject to further compounding by markups at higher levels.  • Mark-ups • Markups may include direct cost markups, contractor markups, special markups and owner markups. Direct cost markups can include adjustments to the direct cost for productivity, overtime, taxes and/or other adjustments as defined by the estimator. Contractor markups can include PTI; allowances, such as small tools; indirect costs, such as JOOH and HOOH; profit; bonds; and/or other costs as defined by the estimator. Contractor markups are defined for each contractor, subcontractor, sub-subcontractor, etc. A special markup can also be defined by the estimator and applied by the contractor, subcontractor, etc. Owner cost markups can include escalation, contingencies, SIOH (owner's supervision, inspection and overhead) and/or other costs as defined by the estimator. Cost Breakdown

  6. Risk factors • Size of the job; • Portion of the work to be done by subcontractors; • Nature of work; • Where the work is to be performed and period of performance; • Relative difficulty of work, the reasonableness of negotiated costs; • Amount of labor included in the costs; • Environmental issues Risk Analysis

  7. A contingency value to account for project risks and unknowns. • Contingency in estimates is not additional profit or fee; it represents an actual construction cost. • Monte-Carlo Simulation for risk quantification / possible cost outcomes. • Contingencies, as defined in the Cost Narrative of the USACE Cost Engineering Report, provide “allowances to cover unknowns, uncertainties and/or unanticipated conditions that are not possible to adequately evaluate from the data on hand at the time the cost estimate is prepared but must be represented by a sufficient cost to cover the identified risks” Contingency

  8. Bare cost • Direct cost • Contract cost • Project cost • Contingency • Operation & Maintenance Costs

  9. Bare cost • Direct cost • Contract cost • Project cost • Contingency • Operation & Maintenance Benefits to Cost Ratio (BCR)

  10. Engineering Procurement Construction Contracts • For large and long term dredging projects, it is better to devise a programmatic management approach to help control costs and reduce some of the indirect costs to projects. • A program management approach that would seek to reduce overall indirect costs would employ large engineering/design-procurement-construction (EPC) contracts for the project. • These large contracts that are program oriented would replace the numerous separate design and construction contracts. • Reduction of scheduled construction calendar time that requires the presence of construction companies with their management structures and other overhead costs that are charged directly to the construction project. • Fewer mobilizations and work location changes that reduce the total distances that materials, equipment, and people must travel. • Reduced prices of labor, materials, and transportation. • Reduced indirect project costs and general direct project costs. Owner – administer contract management EPC Contractor – Single point of responsibility, communication and coordination Vendor Special consultants Sub-contractor ---------- --------- Cost Reduction

  11. Public Private Partnership • Government control (participation and ownership) with private efficiency and capital • Access to a broader range of financing • Access to additional capital • Fewer constraints on accessing capital (e.g. annual appropriation) • Risk sharing (specificity, complexity, uncertainty) • Lower costs of service through specialization Cost Reduction

  12. Public Role • Establishing infrastructure • Establish a regulatory framework • Establish a business environment • Encourage economic opportunity • Encourage private investment • Protect labor interest • Private Role • Generate a rate of return • Handle operational aspects • Manage commercial risks • Propose and implement investment policy • Incentives for high performance and competitive tariffs • Play a crucial role in fostering efficient logistics development Cost Reduction

  13. Government Vs. Private Clients • Labor Laws • Taxes • Fuel Cost • Schedule (delivery dates / investment returns) • Location (intracoastal / navigation) • Environmental • Reclamation / Disposal • Project Size (Economy of Scale) • Negotiate / Industry Competition Cost Reduction