Plans, Specifications and Estimate (PS&E)

Plans, Specifications and Estimate (PS&E) Kelli Sparkman Local Agency Liaison, Region 3 January 30, 2009 Ready…Set…GO!! PS&E documents are used to advertise, award and administer construction contracts.

Download Presentation

Plans, Specifications and Estimate (PS&E)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Plans, Specifications and Estimate (PS&E) Kelli Sparkman Local Agency Liaison, Region 3 January 30, 2009

  2. Ready…Set…GO!! • PS&E documents are used to advertise, award and administer construction contracts. • These documents must be reviewed and approved by ODOT (non-certified) or an “approving authority” (certified)

  3. Resources • Non-Certified Agencies: See LAG Manual Section B, Chapter 11 • Certified Agencies: See LAG Manual Section C, Chapter 11 • User’s Guide to PS&E Delivery See Office of Pre-letting website (http://www.oregon.gov/ODOT/HWY/OPL; click on “Manuals, Forms, etc” on the left side; click on “Guides”)

  4. Key Items for PS&E approval: • Civil Rights Compliance • Wage Rates • Quality Control • Must be in compliance with the applicable, current, ODOT approved edition of various design standards and guidelines • FHWA Form 1273 • Must be included, ODOT inserts • Affirmative Action, EEO, OJT & DBE • ODOT determines goals and aspirational targets

  5. Key Items for PS&E approval: • Buy America Requirements • Any waivers must be approved by FHWA • Traffic Control Plans • “Full” or “Simplified” Transportation Management Plan (TMP) is required on all projects • Sole Source Justification • Patented and Proprietary Items • Local Agency Supplied Materials • Warranty/Guarantee

  6. Time Table for ODOT PS&E Submittals • Due NO LATER THAN 24 calendar days prior to the planned start of the advertisement length • For Full Federal Oversight (FFO) projects, add 3 weeks to the due date • PS&E due dates are assigned by the Office of Pre-letting (OPL) when the bid date is scheduled • Submittal due by 8:00 am on due date • ODOT employees can access submittal information from OPL’s “Bid Date Planning and Status Report” link on the OPL website

  7. Final PS&E Submittal Checklist • Cover sheet contains project specific information • Requires signature from LAL, ODOT Area Manager and ODOT Technical Center Manager • If any item is marked “NO” in the “Completed?” column, a PD-02 exception letter, approved by ODOT’s Deputy Director, will be required • “on file” means all relevant information is in the project master file and available for audit

  8. PS&E Package Contents *Two paper copies are required with Full Federal Oversight (FFO) projects

  9. Office of Pre-letting Tasks • Import PS&E Estimate into Trns*port database and generate Bid Sheets. • Obtain Chief Engineer Signature on Plans Title Sheet. • Conduct a “fatal flaw” review of the PS&E package. • Comments will be sent to the LAL with recommended action • Prepare advertisement and submit to ODOT Contractor Plans for publishing. • Coordinate with FHWA during PS&E to obtain approval to advertise all projects with Federal funds. • Process electronic addenda for publishing on the internet. The QA Engineer will prepare the new bid schedule for the addenda based on items identified in the addenda letter. • Review the PS&E Estimate and prepare the Engineer’s Estimate. • Engineer’s Estimate is to be kept confidential • Archive final special provisions with addenda.

  10. QUESTIONS?