An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. An-Najah National University Faculty of Engineering Civil Engineering Department Construction Project Management “Medical Center In Al-Daheria” Prepared by: Bara Qadomi ShadiArar TaherDeeb Supervisor : Eng. BarraqJumaa 2011-2012

  2. Graduating project consists of two parts : ** The first part includes preparing a theoretical research. ** The second part includes the application of the principle in construction project management.

  3. Project Overview " Medical Center in Al_Daheria " Location: exists in Al-Sadka near Al_Daheria town This project consists of 487 m2 ground floor with 56 m2 water well and 523 m2first floor.

  4. Object: • The main objective of the second part of graduation project will help in understanding the project and calculating quantity of the project and know how we can use management to reach the most economy, safety, minimum duration and good quality of the project. • Assumption: • The project was divided in several units. • The project will performed by a local construction company. • The electrical and mechanical work will be given to a subcontractor. • Fixed the value of dollars with local coin (1 dollars= 3.6NIS).

  5. Site plan for the project Medical Center In Al-Daheria

  6. Work Breakdown Structure (WBS)

  7. Activity List & Coding

  8. Bar Chart

  9. Sample of calculation • Calculation for foundation: • Calculate of concrete: Volume of concrete = number * length * width * depth = 15 * 2.5 * 2.25 * 0.6 = 50.6 m^3

  10. Sample of calculation • Calculate of steel:

  11. S-Curve

  12. The Project At 4 December 2011 From the figure the project is over budget (CPI=0.98) and behind schedule (SPI=0.96)

  13. Column in bill Quantity

  14. Result After determine the quantity, duration and dependency between activities then use primavera project to get this result: * The total duration of the project is (359) day. * The total price of the project is(793593$). The price include: 1- The Engineering Supervision is (31744$) which it is 4% of total price. 2- The profit is 10% of total price (79359.3$).

  15. Result

  16. The Risk Case In 4december 2011 the project is delayed 13 days, the cause of the delayed is stopping of money discharge. Our solution: The external works is begin at 2 April 2012 , the cause of the farther start is to facilitate the construction work and material importing . So we can built the external works partially that don’t disrupting construction works. This step will decrease the total duration of the project.

  17. The project at 20 july2011

  18. The project at 20 july2011

  19. Thanks For Your Attention