Coherent Web Sustaining Engineering Plan. Coherent Web Sustaining Engineering Overview. The Coherent Web team will: Utilize two-week development “sprints” to plan and track implementation activities. Perform weekly reviews of newly submitted NCRs
E N D
Coherent Web Sustaining Engineering Overview • The Coherent Web team will: • Utilize two-week development “sprints” to plan and track implementation activities. • Perform weekly reviews of newly submitted NCRs • NCR priority is assigned based on submitter request and CW Team analysis. • If possible, a target version will be designated. • Categorize NCR into two categories: • “Milestone Activities” – new features that are included in Coherent Web milestones. • “Sustaining Engineering” – internally or externally submitted enhancements and fixes. • As needed, work with the Advisory Group to coordinate schedule and testing • The Coherent Web users will: • Submit enhancement requests or bug reports to the Coherent Web Team • Currently: All items submitted to the Coherent Web Team via email (esdis-cw@lists.nasa.gov) • Future: Items submitted through the Coherent Web Trouble Ticket Tool (Milestone 2) • Include a requested priority (see subsequent slide) with request • Include a need-by date (optional) with request
NCR Priorities • Translating Priority into Development Start Date • Critical CMS items worked immediately • Critical & Severe Content items worked immediately • All other items will be planned in a subsequent Coherent Web sprint. • All enhancements have the same priority • Enhancements will be reviewed to determine if they will be implemented and in which version
Sprint Timeline • NCR Testing & Deployment • When possible, items will be immediately applied to the operational website. • Some items, such as “Milestone Development” activities, will require a staged deployment. In these instances, changes will be applied to the Earthdata UAT environment. The CW Team, issue submitter, and/or Advisory Group, will then perform the necessary user acceptance testing prior to Operational deployment
Sprint Scheduling • Proposed 2011 Sprints • Sprint “2011-1“ - 10/3 – 10/14 • Sprint “2011-2“ - 10/17 – 10/28 • Sprint “2011-3“ - 10/31 – 11/11 • Sprint “2011-4“ - 11/14 – 12/2 (Extended due to Thanksgiving) • Sprint “2011-5“ - 12/5 – 12/16 • Sprint “2011-6“ - 12/19 – 12/30 • Notifications regarding issue completion will come either from the CW Team or the CW Ticket Tracking tool. • Until a tool is developed, all communications will come from the CW Team. • Each sprint plan will be published to the informational page on the Earthdata website for historical referencing and planning purposes.