1 / 17

Prince2 foundation Updated Exam PDF (Questions & Answers) - Prince2-Foundation Passleader

Enjoy your success in PRINCE2 Certification Exams with our PRINCE2 Foundation Exam Dumps!!! Prince2-Foundation Dumps Questions Answers with PRINCE2 Foundation Exam Practice Test software is a success leading way towards your PRINCE2 Prince2-Foundation Exam. All the Prince2-Foundation Questions Answers are tested and approved by professional experts to assure 100% success in PRINCE2 Certification exam. Get huge discount 20% discount off on all products by using this coupon code “lps20”. Visit us for more information<br>https://www.passleaders.com/Prince2-Foundation-exam.html

passleaders
Download Presentation

Prince2 foundation Updated Exam PDF (Questions & Answers) - Prince2-Foundation Passleader

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Prince2-Foundation PRINCE2 Foundation Exam

  2. Enjoy your success in PRINCE2 Certification Exams with our PRINCE2 Foundation Exam Dumps!!! Prince2-Foundation Dumps Questions Answers with PRINCE2 Foundation Exam Practice Test software is a success leading way towards your PRINCE2 Prince2-Foundation Exam. All the Prince2- Foundation Questions Answers are tested and approved by professional experts to assure 100% success in PRINCE2 Certification exam. https://www.passleaders.com/Prince2-Foundation-exam.html

  3. Did You Know! https://www.passleaders.com/Prince2-Foundation-exam.html

  4. You Don’t need to take any stress for the preparation of Prince2-Foundation Exam because we will provide you real Exam questions answers, Passleaders provide you some demo question answer of Prince2-Foundation Dumps. https://www.passleaders.com/Prince2-Foundation-exam.html

  5. QUESTION 1, Upon what environment is PRINCE2 based? A. Operational B. Configuration C. Programme D. Customer/supplier Answer: D https://www.passleaders.com/Prince2-Foundation-exam.html

  6. QUESTION 2, Which is NOT a requirement of a Stage Plan? A. Produced to an appropriate level of detail to enable day-to-day control B. Produced near to the end of the previous management stage C. Approved and signed-off by Project Assurance D. Approved at the end of a management stage Answer: C https://www.passleaders.com/Prince2-Foundation-exam.html

  7. QUESTION 3, Which may be funded from a risk budget? A. Capturing identified threats and opportunities in the Risk Register B. Specific management responses to a project's threats and opportunities C. Producing risk summaries for inclusion in Highlight Reports D. Any remaining open risks after the project has been closed Answer: B https://www.passleaders.com/Prince2-Foundation-exam.html

  8. QUESTION 4, Which role is part of the project management team? A. Change Authority B. Quality assurance C. Stakeholder D. Corporate or programme management Answer: A https://www.passleaders.com/Prince2-Foundation-exam.html

  9. QUESTION 5, Which is a purpose of a Configuration Management Strategy? A. Provide a record of each configuration item and any important relationships between them B. Define how theproducts and their versions will be identified C. Define whether a project will use a risk budget D. Identify who will set up the Quality Register Answer: B https://www.passleaders.com/Prince2-Foundation-exam.html

  10. QUESTION 6, Identify the missing words in the following sentence. The purpose of the Starting up a Project process is as much about [?] as it is about requesting authorization to initiate viable projects, A. producing an achievable Project Plan B. preventing poorly-conceived projects from ever being initiated C. obtaining approval from all stakeholders D. setting up the required project controls Answer: B https://www.passleaders.com/Prince2-Foundation-exam.html

  11. QUESTION 7, What product should be used to confirm the version number of ail products in a particular stage? A. Issue Register B. Product Status Account C. Product Description D. Configuration Item Record Answer: B https://www.passleaders.com/Prince2-Foundation-exam.html

  12. QUESTION 8, What do customer's quality expectations identify? A. Standards that must be used in order to meet the level of quality needed B. Skills required to develop the project product C. Measurable definitions of the attributes required for a set of products to be acceptable to the customer D. Reviewer names for each product Answer: A https://www.passleaders.com/Prince2-Foundation-exam.html

  13. QUESTION 9, Whose approval is needed to replace a Stage Plan with an Exception Plan? A. Corporate orprogramme management B. Project Board C. Project Manager D. Team Manager Answer: B https://www.passleaders.com/Prince2-Foundation-exam.html

  14. QUESTION 10, Which is NOT considered when defining risk tolerance? A. A Project Board's attitude towards risk taking B. The allocated risk budget C. An organization's risk appetite D. The amount of risk a Project Board considers acceptable Answer: B https://www.passleaders.com/Prince2-Foundation-exam.html

  15. Why Choose US! https://www.passleaders.com/Prince2-Foundation-exam.html

  16. https://www.passleaders.com/Prince2-Foundation-exam.html

  17. Good luck Passleaders provides you guaranteed success in Prince2-Foundation Dumps as we have latest Prince2-Foundation Exam Dumps. Click Here following link to download Prince2-Foundation Braindumps. https://www.passleaders.com/Prince2-Foundation-exam.html

More Related