NL Service Challenge Plans

NL Service Challenge Plans. Kors Bos, Sander Klous, Davide Salomoni (NIKHEF) Pieter de Boer, Mark van de Sanden, Huub Stoffers, Ron Trompert, Jules Wolfrat (SARA), Hans Blom, Freek Dijkstra, Paola Grosso (UvA), Peter Michielse (NCF) Serv.Chall.Mtng. – Taipei – March 26, 2005.

pello
Download Presentation

NL Service Challenge Plans

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NL Service Challenge Plans Kors Bos, Sander Klous, Davide Salomoni (NIKHEF) Pieter de Boer, Mark van de Sanden, Huub Stoffers, Ron Trompert, Jules Wolfrat (SARA), Hans Blom, Freek Dijkstra, Paola Grosso (UvA), Peter Michielse (NCF) Serv.Chall.Mtng. – Taipei – March 26, 2005

  2. Updated Planning • March: SC2, sustained 100 MB/s disk-disk DONE! • April: new disks, new network DONE! • May: new hardware, install & test SRM/dCache • June: tape tests, reduced bandwidth • July: SC3, sustained 50 MB/s disk-tape • August: vacation 

  3. Rembrand Cluster: New disksthanks to group of the UvA • Used a cluster of 4 nodes for SC2: • The whole cluster is bigger (9 nodes) • 64-bit dual Opteron at 2 GHz and 3 GB RAM • 2 (SATA) data and 1 system disk 250 GB per node • Reached ~40 MByte/s writing • 1 Gb/s fiber NIC • Now upgraded to: • 12 disks (250 GB) per node • 4 nodes RAID0, and 4 nodes RAID5 • Test with RAID5 system shows ~100 MByte/s writing ? • Test with RAID0 not done yet • 10 Gb/s fiber NIC on all nodes

  4. More new hardwareto connect to SARA SAN Arrived: • 3 Dell Power Edge 1850 • 32-bit dual Xeon at 3.0 GHz and 4 GB RAM • 2 SCSI system disks • I/O Riser card • 1 Dell PowerConnect 5324 Not yet arrived: • SGI TP9300 Storage array • 14 x 250 Gbyte SATA disks • 2 x 9940B tape drives

  5. SC3 set up 10 Gb/s Force10 UvA cluster 1 Gb/s Internal Gigabit Network 1 Gb/s SAN HSM Shared FS Fiber Channel LCG tape drives New hardware

  6. New Network10 Gbit/s tests 10 G/sec has been configured • Problem: WAN-PHY to LAN-PHY conversion • Borrowed Foundry from Canadians (Wade Yong) • Univ. of ALberta may keep it until end July June: Vancouver 10G/sec tests • For 3 weeks • We swap our 10G with their 2 x 1G • End June: swap back

  7. May • tests with 10 G and new disk array • Huub, Sander • Install and test SRM & dCache on new hardware • Mark, Ron

  8. June • Swap network with Vancouver • Pieter, Paolo • First tape tests • Mark, Huub,Ron • End June • swap back • final preparations for SC3