Flexenclosure eCentre DRP VODACOM MOÇAMBIQUE
Flexenclosure participants • Thomas Gustafsson, Customer Project Manager • Johan Thörnberg, Electricaland Cooling resp. • Mattias Stensson, Architectural and Structural resp.
AC System • ATS design for 3 sources (grid and twogensets) • Design for max 400Amp 400V TN-S system (275kW) • Distribution accordingtosinglelinedrawing. (7233-E-001_Rev.02) • Control system ATS based on PLCsystem incl: monitoring system for electricalpower and cooling system
DC and Invertersystem • Main cabinet prepared for 24 rectifier @ 2900W tot 69,6kW • Extension cabinet prepared for 24 rectifier @ 2900W tot 69,6kW • Total capacity139,2kW • Cable cabinetbetweenmain and ext. cabinet • Recitifier 31pcs @ 2900W tot 89,9kW • Invertercabinet prepared for 20pcs inverter @ 1500VA tot 24kW/30kVA • Invertermodules 10pcs @ 1500VA tot 12kW/15kVA • Three batterycabinetand 48V batteri Enersys 12V190FT (48 block) • Battery backup time< 55 min @ 85 kW, 2h @ 42,5 kW
Cooling System • 4pcs DX-units @ 35,6kW • Return air temperature 28°C • Supply air temperature 17°C • Ambient temperature40°C
Raisedfloor system • Concentratedloads 5kN • Uniform distributed loads 8kN/m² • Floortilesureface ”Granit”
Fire fighting system • FM200 system • Extinguishant control panel • Detection system
Timeschedulingaccto layout rev 03 and current PO • Production finish – pick-up 2012-12-12 • Planned site start 2013-01-24 • Hand over 2013-02-08