River Road/Bradley Park Drive/Green Island Drive. Intersection Improvements. Timeline. Concept Meeting-Feb 29,2008 Design Started- Aug 2009 ROW Plans – June 2011 DOT permit approved – Sept 2011 Design 90% complete – Dec 2011 Project Scheduled for Bid FY13
E N D
River Road/Bradley Park Drive/Green Island Drive Intersection Improvements
Timeline • Concept Meeting-Feb 29,2008 • Design Started- Aug 2009 • ROW Plans – June 2011 • DOT permit approved – Sept 2011 • Design 90% complete – Dec 2011 • Project Scheduled for Bid FY13 • Project delayed for Roundabout review – Jan 2013
Cost Estimates • Traditional Design • Traditional Signal/Lanes- $927,000 • Spent to Date-$158,531.96 • Roundabout Design • Roundabout-$ 1,748,000-$ 2,265,769 • Variance – ROW, Utilities, Drainage • Added Design Costs - $154,000 • Require DOT permit • Additional funding required - $1 - $1.5 million
Guidance Requested • Continue with Traditional Design • Project ready for ROW • Redesign as Roundabout • Identify funding source • Initiate redesign (6 months) • ROW (6-9 months) • Project ready for construction in 12-15 months