1 / 20

Twin Cities Army Ammunition Plant

Twin Cities Army Ammunition Plant. 2007 Remedial Actions at TCAAP Site C Excavation/Stabilization/Disposal of Contaminated Soils, Placement of Soil Covers, and Construction of Replacement Wetland. U.S. Army Corps of Engineers

portia
Download Presentation

Twin Cities Army Ammunition Plant

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Twin Cities Army Ammunition Plant 2007 Remedial Actions at TCAAP Site C Excavation/Stabilization/Disposal of Contaminated Soils, Placement of Soil Covers, and Construction of Replacement Wetland U.S. Army Corps of Engineers Shaw Environmental, Inc.

  2. Site C-2 Remedial Action • Work Plan Clarification (WPC) No. 41 – Borrow soils sampling and excavation plan. • Construction Start Date – 7/16/07. • Excavation/Stabilization/Disposal of contaminated soils from 63 grids at Site C-2. • Placement of approximately 38,000 cubic yards (cy) of fill material and 5,000 cy of topsoil for the soil cover construction (58 Grids and portions of the ditches required a minimum of 4 feet of soil cover due to contamination remaining in place). • WPC No. 42 – Over-excavated soils. • Construction of a Replacement Wetland located north of Site C-2 (~2 acres).

  3. Site C-2 Remedial Action • WPC No. 43 – Burn Area. • Excavation/Stabilization/Disposal of ~200 cy of contaminated soil at the southern end of the wetland. • Final Survey • Construction Completion Date - 10/5/07.

  4. Site C-2 Pre-Excavation

  5. Site C Site C-2 Excavation of Contaminated Soils

  6. Site C Site C-2 Excavation of Contaminated Soils and Verification of Elevation

  7. Site C Site C-2 Stabilization of Contaminated Soils

  8. Site C-2 Site C-2 Load Out of Contaminated Soils

  9. Site C-2 Site C-2 Load Out of Contaminated Soils

  10. Site C-2 Site C-2 Grading

  11. Site C-2 Site C-2 Final Grade

  12. Site C Replacement Wetland Clearing and Grubbing

  13. Site C Replacement Wetland Excavation of soils from Wetland Area

  14. Site C Replacement Wetland Installing the Swale and Placing Rock

  15. Site C Replacement Wetland Installing the Swale and Placing Rock

  16. Site C Replacement Wetland Removal of the Existing Weir

  17. Site C Replacement Wetland Burn Area

  18. Site C Replacement Wetland Burn Area Sampling

  19. Site C Replacement Wetland Wetland Final Grade

  20. TCAAP Osprey

More Related