An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. HO Upgrade: QC and Production Preparation in India Shashi Dugad India-CMS Meeting, BARC 30 July 2010

  2. 2009 version of SiPM control board fabricated and assembled in Jan 2010 It was tested at FNAL by Sergey…. worked flawlessly. Order for production version has been placed with same company in June-2010 Pilot production PCB fabrication is in process Pilot production boards will be tested at FNAL/CERN after which bulk order for fabrication for all 3 rings can be given. Plan to make control boards for entire HO in India Quality control of all boards to be done at CRL, Ooty SiPM Control Board Status Shashi Dugad, ECR Meeting, 28 July 2010 2

  3. SiPM Control Board Fabricated in Indian company by CRL, Ooty in Jan.2010 Shashi Dugad, ECR Meeting, 28 July 2010

  4. Quality Control of SiPM Board • QC testing of SiPM boards at CRL, Ooty • Standalone DAQ • External amplifiers (developed by Princeton) will be used for SiPM readout (no QIE Electronics) • 3 preamp boards required for testing were fabricated by Princeton (Chris etal.) in April-2010. Will be read out via VME. • Prototype test stand for QC set up. • Team: Arjan, Rajesh, Shashi Shashi Dugad, ECR Meeting, 28 July 2010

  5. Test Setup developed at CERN with Cascade-Amplifier as Front End Team: A. Heering, B. Rajesh, Shashi Shashi Dugad, ECR Meeting, 28 July 2010

  6. Results from CERN-B28 Setup Shashi Dugad, ECR Meeting, 28 July 2010

  7. Summary of B28 Results Shashi Dugad, ECR Meeting, 28 July 2010

  8. Quality Control of SiPM at CRL, Ooty • Standalone DAQ at CERN and Ooty developed with VME readout under Linux • Trigger rate of > 1kHz achieved with good data integrity • Prototype system with Princeton’s amplifier works well (single p.e. resolution) • This working prototype framework will be expanded to further automate quality control of SiPM boards Shashi Dugad, ECR Meeting, 28 July 2010

  9. Data Taking SETUP at CRL, Ooty Amp Bias Monitor I2C Box Shashi Dugad, ECR Meeting, 28 July 2010 9 Slow Control

  10. First results – Day 1 LED + Pedestal Distributions LED Pedestal Tail Shashi Dugad, ECR Meeting, 28 July 2010 10

  11. Amplifier Bias voltage 9.5 ( file No 220) 1 pixel ~ 5.2 counts 1 pixel ~ 4.91 counts Shashi Dugad, ECR Meeting, 28 July 2010 11 11

  12. Data taking setup • The I2C cable shielded with Aluminum foil and the I2C box • kept away from the control card • Amplifiers mounted on Perspex and bias connected for all 3 cards 12

  13. Summary • Pilot production version of Control board will be ready within a month after receiving all files (Gerbers & assembly) from FNAL • Production and QC of all control boards and SiPM mounting board to be carried out at CRL, Ooty • Good progress on the quality control setup at CRL, Ooty • Data taking at CRL, Ooty able to resolve single p.e. after modifying mounting arrangement for amplifiers Shashi Dugad, ECR Meeting, 28 July 2010 13