1 / 12

Wadsa-Armori-Gadchirolli

Wadsa-Armori-Gadchirolli ( 49.50 Km. NON - Electrified)

Download Presentation

Wadsa-Armori-Gadchirolli

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Wadsa-Armori-Gadchirolli • (49.50 Km. NON - Electrified) • Remarks :-The project report initially submitted in 2001 with ROR of (-) 8.19%. Board instructed to recalculate the ROR as 50% of project cost is to be borne by Govt. of Maharastra.Revised report was submitted on 17.01.03 with ROR of (-) 3.78%.Updated report of RETS submitted on 18.12.08 at the cost of Rs. 186.06 with ROR of (-7.46). Now fresh updating has been done in July -10 with the cost of Rs. 232.40 crores & ROR is (-)3.88% & with 50% cost sharing by State Govt. ROR (-)0.40% • Action Plan :- Further directive yet to receive from Railway Board.

  2. Raigarh-Mand (63 Km. Electrified)Remarks :-Survey was completed by outsourcing and report submitted to board on 27.7.09 @ cost- of Rs 310.64 Crs ROR- (+)29.58%. As per announcement in Railway Budget 2010-11 updating of survery done at the cost of Rs. 344.20 crores & ROR (+) 26.33% Action Plan :- Further directive yet to receive from Railway Board.

  3. 3. Raipur-Dhamtari including Abhanpur - Rajim Branch line.(67.20 Km Electrified) Remarks :- The alignment within Raipur Town was resurveyed as 1995 alignment is not feasible. The project report was submitted on 8-12-07. Railway Board advised to conduct fresh survey on 10.11.09. Project cost Rs 278 crores & ROR (+)14.40% with sharing 2/3 cost by State Govt. Report is submitted to Board on 13.07.10 Action Plan :- Further directive yet to receive from Railway Board.

  4. 4. Preliminary Engineering Cum Traffic Survey for Gauge conversion of Nagpur-Nagbhir (106.15 km) (Non – Electrified) Remarks :- Report submitted to Railway Board on 22.12.09. Railway Board has advised to re-examine the cost. After complying the obsevation, the abstract estimate report submitted to Rly. Board on 12.11.10. At the cost of Rs. 376.83 Crores & ROR (+) 1.50%. Action Plan :- Further directive yet to receive from Railway Board.

  5. 5.Korba-Lohardaga new line (via Dharamjaygarh, Pathalagaon, Jashpurnagar.) (326 Km. Electrified) Remarks:- Updating of RET Survey done at the cost of Rs.2443.74 Crores.& ROR (-) 7.37%. Report submitted to Railway Board 01.02.11. Action Plan :- Further directive yet to receive from Railway Board.

  6. 6. Gevra Road - Pendra Road new line (via Dipka, Sindurgarh & Pasan.) (121 Km. Electrified) Remarks :- Railway Board sanctioned updating vide letter No.2009/W-1/Genl/sur/09-10 dated 24.06.2010. Updated report submitted on 11.1.11 at the cost of `. 867.03Crores &ROR(+)17.36%. Action Plan :- Further directive yet to receive from Railway Board.

  7. Gotegaon-Ramtek via Seoni- (275Km)Remarks :-Board has sanctioned updating vide letter No.2009/W-1/Genl/sur/09-10,dated:-24.6.10. Updated abstract estimate vetted by accounts and ROR under calculation by Optg. Deptt. Action Plan :- Further directive yet to receive from Railway Board.

  8. Raipur-Jharsuguda via Bhatgaon Sarangarh(310Km Electrified) RETSRemarks :-RailwayBoard has sanctioned updating vide letter No.2009/W-1/Genl/sur/09-10 dated:-24.06.2010. Updated report & abstract estimate submitted to Board on 28.12.10 at the cost of `.2161.37Crores & ROR(+)16.70 %. Action Plan :- Further directive yet to receive from Railway Board.

  9. Updating of Reconnaissance Engineering cum Traffic Survey for a new line between Barwadih - Chirimiri (Ambikapur) (182 Kms. Electrified)Remarks :-RailwayBoard has sanctioned updating vide letter No.2009/W-1/Genl/sur/09-10, dated:-24.6.10 updating done & ROR calculation with Traffic deptt. Action Plan :- Report will be submitted shortly after ROR calculation.

  10. 10. Jharsuguda-Durg 4th line (360 km)Remarks:-To conduct 4th line Survey letter received from by Railway Board from 02.12.09. Terms & references yet to be decided. RITES has been contacted for simulation. They have submitted their offer. Tender finalized.

  11. Dongargarh to Kota (Pendra Road) via Khairagarh-Chhuikhadan-Gandai -Sahaspur - Lohara-Kawardia Bodh -Pendra Road (220 kms)RETSRemarks :- Out sourcing contract finalized. Field work has been commenced from Kota end & completed as per initial alignment. Railway Board advised to examine alternative route which is in process.

  12. 12. Durg – Nagpur 3rd line (256 Km.) RETSRemarks :- Survey is being conducted through outsourcing. Tender finalized. Field work of 172 Km between RJN-BRD done & balance is in progress.

More Related