Offshore Wind J. McCalley. Introduction – structures and depth. Most existing off-shore wind today is in shallow water. M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf. Introduction – structures and depth.
E N D
Offshore Wind J. McCalley
Introduction – structures and depth Most existing off-shore wind today is in shallow water. M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf.
Introduction – structures and depth Foundation technology for offshore wind can borrow much from designs of ocean-based oil and gas wells. Technology White Paper on Wind Energy Potential on the U.S. Outer Continental Shelf, Minerals Management Service Renewable Energy and Alternate Use Program, U.S. Department of the Interior May 2006, http://ocsenergy.anl.gov/documents/docs/OCS_EIS_WhitePaper_Wind.pdf.
Introduction – shallow water foundations Three types of foundations used in shallow water: Least common Most common
Introduction – shallow water foundations M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf.
Introduction – transitional depth foundations 30-90m depths M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf.
Introduction – deep water foundations >60m depths M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf.
Introduction - 2010 offshore capacity Europe, at the end of 2010, had 1,136 offshore wind turbines installed and connected to the grid on 45 wind farms in 9 countries, with capacity of 2,946 MW
Introduction – EU growth in wind TOTAL EU OFFSHORE WIND AT END OF 2010 IS 2913 MW Source: European Wind Energy Association, “Wind in power: 2010 European statistics,” Feb 2011, http://ewea.org/fileadmin/ewea_documents/documents/statistics/EWEA_Annual_Statistics_2010.pdf.
Life cycle costs • Turbine cost is 1/3 (lower than inland wind) • Support structure is 1/4 (much higher than inland wind) • Grid connection is significant (higher than inland wind) • O&M is 1/4 (higher than inland wind) Offshore wind may scale better than inland wind M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf.
US Wind Resource US offshore wind resource at 90 m above the surface 9m/s 3m/s M. Schwartz, D. Heimiller, S. Haymes, and W. Musial, “Assessment of Offshore Wind Energy Resources for the United States,” NREL/TP-500-45889, June 2010, at http://www.nrel.gov/docs/fy10osti/45889.pdf.
US Coastal and Great Lakes Bathymetry The East coast and the Gulf of Mexico have extensive areas of shallow water relatively far from shore. On the West coast, the continental shelf descends rapidly into the deep water category. The water depth also increases rapidly away from shore around Hawaii. In the Great Lakes region, Lake Erie and portions of Lake Ontario can be characterized as shallow; the other lakes are primarily deep water, with narrow bands of shallow and transitional water near the shore. Bathymetry: The measurement of depth of water in oceans, seas, or lakes. M. Schwartz, D. Heimiller, S. Haymes, and W. Musial, “Assessment of Offshore Wind Energy Resources for the United States,” NREL/TP-500-45889, June 2010, at http://www.nrel.gov/docs/fy10osti/45889.pdf.
US Coastal and Great Lakes Bathymetry From National Oceanic and Atmospheric Administration NOAA National Geophysical Data Center, U.S. Coastal Relief Model, Retrieved date goes here, http://www.ngdc.noaa.gov/mgg/coastal/crm.html
Offshore wind resource by wind speed, water depth, distance from shore 1 n.m. = 1.15077 mi 1 n.m. = 1.852 km These are for Georgia, but the below reference has similar data for all coastal states and great lakes. M. Schwartz, D. Heimiller, S. Haymes, and W. Musial, “Assessment of Offshore Wind Energy Resources for the United States,” NREL/TP-500-45889, June 2010, at http://www.nrel.gov/docs/fy10osti/45889.pdf.
Offshore wind resource by wind speed, water depth, distance from shore 1 n.m. = 1.15077 mi 1 n.m. = 1.852 km These are for Oregon, but the below reference has similar data for all coastal states and great lakes. M. Schwartz, D. Heimiller, S. Haymes, and W. Musial, “Assessment of Offshore Wind Energy Resources for the United States,” NREL/TP-500-45889, June 2010, at http://www.nrel.gov/docs/fy10osti/45889.pdf.
Horns Rev Wind Farm - Denmark J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004. “The wind farm is located at the Danish west coast and is sited 14-20 km offshore in the North Sea, connected to shore with AC at 150 kV….a single 150 kV sub sea-power cable is in operation. Since the turbines are connected with 34 kV, an additional platform with the 34 to 150 kV transformer was necessary.” North Sea! M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf. 34 to 150 kV transformer
North Sea Offshore, Existing & Under construction, 7/2011 Of 2913 MW EU offshore, 1866 MW is in North Sea EXISTING Under cnstrctn K. Veum, L. Cameron, D. Hernando, M. Korpas, “Roadmap to the deployment of offshore wind energy in the central & southern North Sea: 2020-2030,” July 2011, at www.windspeed.eu/media/publications/WINDSPEED_Roadmap_110719_final.pdf.
North Sea Offshore Potential K. Veum, L. Cameron, D. Hernando, M. Korpas, “Roadmap to the deployment of offshore wind energy in the central & southern North Sea: 2020-2030,” July 2011, at www.windspeed.eu/media/publications/WINDSPEED_Roadmap_110719_final.pdf.
North Sea Offshore Potential (both shallow and deep water) (mainly deep water) (mainly shallow water) (little shallow or deep water K. Veum, L. Cameron, D. Hernando, M. Korpas, “Roadmap to the deployment of offshore wind energy in the central & southern North Sea: 2020-2030,” July 2011, at www.windspeed.eu/media/publications/WINDSPEED_Roadmap_110719_final.pdf.
Interactions between sea use functions K. Veum, L. Cameron, D. Hernando, M. Korpas, “Roadmap to the deployment of offshore wind energy in the central & southern North Sea: 2020-2030,” July 2011, at www.windspeed.eu/media/publications/WINDSPEED_Roadmap_110719_final.pdf.
Typical offshore layout M. Robinson and W. Musial, “Offshore wind technology overview,” October 2006, http://www.nrel.gov/docs/gen/fy07/40462.pdf. J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004.
DC-thyristor vs DC-VSC HVDC transmission uses either thyristor-based converters or voltage source converters (VSC). Most DC designs for offshore wind utilize VSC because VSC is more economic at these lower power ratings. S. Meier, S. Norrga, H.-P. Nee, ‘’New voltage source converter topology for HVDC grid connection of offshore wind farms,’’ at http://www.ee.kth.se/php/modules/publications/reports/2004/IR-EE-EME_2004_013.pdf.
AC vs DC-thyristor vs DC-VSC Self-commutated voltage source converter AC DC Line commutated current source converter. AC DC M. Bahrman, HVDC Transmission Overview, .
An interesting idea On-shore power grid Wind farm Sea-bed transmission VSC VSC VSC VSC PMG AC DC AC DC AC Wind turbine On-shore power grid Wind farm Sea-bed transmission VSC VSC PMG DC AC AC Wind turbine
AC vs DC-thyristor vs DC-VSC • AC requires no converter station but has high charging (capacitive) currents that become excessive for long distances. An important issue with AC is whether to step up to transmission voltage in the sea and then transport over high voltage or transport over lower (34.5 kV) voltage and step up to transmission inland. • DC-thyristor has very high power handling capability but converter stations are expensive, and they have short-circuit limitations and therefore locational constraints. • DC-VSC (voltage-source converters) have lower power-handling capabilities, but converter stations are less expensive and they have no short-circuit limitations and can therefore be located anywhere. J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004.
AC vs DC-thyristor vs DC-VSC Switchgear & converters J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004.
Losses vs. distance for different AC voltage Compare 132 kV to 34 kV for 250MW transmission Compare 132 kV to 34 kV for 100MW transmission Compare 132 kV to 34 kV for 50MW transmission Power losses for HV (132 kV) and MV (34 kV) J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004.
Breakover distances for AC vs DC • I believe this is for net present worth of {investment + operating costs} but source does not say. But displayed concepts are right: • AC w/farm voltage transmission is only right for short distances at low power • AC w/offshore transformation is right for medium distances at medium power • DC is right for long distances or at high power transfer. J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004.
STANDARD NETWORK TOPOLOGIES FARM-VOLTAGE TRANSMISSION OFF-SHORE TRANSFORMATION RADIAL (STRING) STAR This is similar to inland topologies, but here, the location of the step-up transformer is more influential in the economics of the design. J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004.
Costs, Reliability & Losses Off-shore windfarms “For large scale OWFs a combination of these basic layouts is commonly used, where several strings of turbines are connected to the shore connection point. Its advantages are the simpler cable laying pattern and the shorter cable lengths compared to a strictly star layout. The disadvantages occur with cable failure, because all the turbines upward the failure site on a string have to be switched off and cannot be connected to the grid until the failure has been repaired. Especially during periods of harsh sea conditions in winter the required repair time can be months. Also the number of turbines which can be connected to a string is limited by the power carrying capability of the cable used. With growing turbine power output, the star connection offers the possibility to reduce cable losses by clustering small groups of turbines to high voltage transformer stations as shown in layout IV. Also in case of cable failure at a turbine connection only the single turbine where the failure occurred has to be switched off, the remaining turbines connected to the transformer platform can stay in operation. The big disadvantage is the required transformer platform.” J. Schachner, “Power connections for offshore wind farms,” MS thesis, TUDelft, 2004.
Wake Interactions Wakes behind wind turbines at Horns Rev K. Veum, L. Cameron, D. Hernando, M. Korpas, “Roadmap to the deployment of offshore wind energy in the central & southern North Sea: 2020-2030,” July 2011, at www.windspeed.eu/media/publications/WINDSPEED_Roadmap_110719_final.pdf.
Off-shore wind farm siting “In view of the recent findings on wakes within offshore wind farms and on wind speed deficits behind these wind farms, the WINDSPEED project considers that, within a defined area, only 30% of the total should realistically be occupied by wind farms. It is assumed that any large scale deployment of offshore wind will likely take the form of multiple wind farm clusters uniformly spaced, allowing adequate distance between each cluster to mitigate the impact of inter wind farm wake losses and the resulting lost production and wake turbulence loading …The remaining 70% shall provide space for wind speed recovery and dissipation of wake turbulent energy, but also possibly permit some form of navigation throughout the area …This provides opportunities for co-use/co-existence with other sea uses such as shipping and fishing.” “D” is turbine diameter. K. Veum, L. Cameron, D. Hernando, M. Korpas, “Roadmap to the deployment of offshore wind energy in the central & southern North Sea: 2020-2030,” July 2011, at www.windspeed.eu/media/publications/WINDSPEED_Roadmap_110719_final.pdf.
North Sea HVDC Network? “For those scenarios in which some form of offshore grid is assumed to develop – the In the Deep and Grand Design scenarios – the results from the DSS were used to define a number of potential OWE clusters along with onshore connection points. An offshore grid was then designed that interconnects these wind clusters and onshore connection points in such a way as to optimise the investment cost of the grid against the benefit it provides by increased trade opportunities and connections to the new offshore wind generation units.” K. Veum, L. Cameron, D. Hernando, M. Korpas, “Roadmap to the deployment of offshore wind energy in the central & southern North Sea: 2020-2030,” July 2011, at www.windspeed.eu/media/publications/WINDSPEED_Roadmap_110719_final.pdf.
Wind-motivated networks? Is there a “multi-farm collection network” problem that is general/common to both inland & offshore? There would be differences in implementation, but design method may be very similar.
Wind-motivated networks? Some thinking on novel designs: T. Hammons, V. Lescale, K. Uecker, M. Haeusler, D. Retzmann, K. Staschus, S. Lepy, “State of the Art in Ultrahigh-Voltage Transmission,” Proceedings of the IEEE, Vol. 100, No. 2, February 2012.