SOFTWARE PROJECT MANAGEMENT. Project Time Management Dr. Ahmet TÜMAY, PMP. Activity Sequencing Techniques. Pr ecedence Diagramming Method (AON) 4 Type Dependencies FS,FF,SS,SF. Duration Estimation Techniques. Three Point Estimates (PERT). Schedule Development Techniques.
E N D
SOFTWARE PROJECT MANAGEMENT Project Time Management Dr. Ahmet TÜMAY, PMP
Activity Sequencing Techniques Precedence Diagramming Method (AON) 4 Type Dependencies FS,FF,SS,SF
Duration Estimation Techniques Three Point Estimates (PERT)
Schedule Development Techniques Critical Path Method
Control Schedule Techniques Earned Value Analysis, Kazanılmış Değer Analizi EV: Earned Value (Kazanılmış Değer) PV: Planned Value (Planlanan Değer) SPI: Schedule Performance Index SV: Schedule Variance SPI = EV / PV SV = EV - PV
Example EV: Earned Value (Kazanılmış Değer) PV: Planned Value (Planlanan Değer) SPI: Schedule Performance Index SV: Schedule Variance SPI = EV / PV SV = EV - PV