1. Regional Transmission Network Development: Implications for Trade and Investment
12. 2004 – April – energy cooperation protocol between Romania and Turkey at ministries level
The first mentioning of the cable project
2005 - June – MOU between Transelectrica and TEIAS for the HVDC link project
Main scope : to prepare the oportunity study by a joint project team
2006 – November - JPP ( joint position paper ) between Transelectrica and TEIAS
Approval of the opportunity study;
Decision to continue the study at feasibility study level
2007 – first attempt to launch the feasibility study with minority financing of private investors ( 50 % Swedish grant available )
No success; replacement of the private investor with Nuclearelectrica
2008 – first tender for the FS in new financing conditions;
Incompatibility of the grant with open tender requirements
2009 – secont tender; contract signature in June
33. Activities to be done in parallel with the feasibilty study Preliminary business model
List of main commercial, regulatory and financial hypothesys
Documentation on the business experience of existing commercial interconnectors in EU
Discussions and clarifications with the regulatory authorities
Legal due diligence for the preliminary business model
TOR for the complete business study
Exploration and identification of potential private partners
Letters of intent
Develop procedure for the selection of the private investors
Full clarifications on TEIAS participation in the project, including Turkish applicable legislation
Preliminary legal preparations for the project company ( SPV )