An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. December 2021

  2. Tower 4A & 4B 4B 4A TOWER STATUS MILESTONES ACHIEVED • 4A terrace water proofing completed. 4A External painting in progress. 4B above terrace OHT completed. 4B external sealant work in progress. 4A 14th floor doors fixing completed. 4A 14th floor Windows fixing completed. 4A internal painting in progress. 4B 14th floor tiles work in completed. 4B balcony railing completed. 4B doors & windows 8th floor in progress. • 4A Installation of windows/doors up to 14th floor completed. 4B Completion of doors/ windows up to 7th floor. • • • • • • UPCOMING MILESTONES • • • 4A completion of erection of lifts, common lobbies and common staircases. 4B Completion of doors/windows up to 10th floor. • • • Actual site photograph PROGRESS TIMELINE July 21 August 21 September 21 October 21 November 21 Construction Updates

  3. Tower 5A & 5B 5B 5A TOWER STATUS MILESTONES ACHIEVED • 5A OHT top slab reinforcement in progress. 5A External sealant works in progress. 5B OHT top slab work in progress. 5B External sealant works in progress. 5A 14th floor doors fixing Completed. 5A 14th floor Windows fixing Completed. 5A internal painting in progress. 5B 11th floor tiles work in progress. 5B water proofing completed. • 5A installation of external windows/doors up to 14th floor completed. 5B completion of flooring up to 10th floor. • • • • UPCOMING MILESTONES • • • 5A Completion of erection of lifts, common lobbies and common staircases. 5B completion of flooring up to 14th floor. 5B completion of doors/windows up to 3rd floor. • • • • • Actual site photograph PROGRESS TIMELINE July 21 August 21 September 21 October 21 November 21 Construction Updates

  4. Tower 3C, 3D & 3E 3C 3D TOWER STATUS MILESTONES ACHIEVED • • • • 3E Above terrace works in progress. 3C GF roof slab completed. 3D GF roof slab completed. 3E internal waterproofing completed. 3E internal putty works 10th floor in progress. 3E flooring works 11th floor in progress. • 3E completion of flooring up to 3rd floor. 3C & 3D Completion of 1st (first) slab. • • UPCOMING MILESTONES • INTERNAL 3E • 3E completion of flooring up to 7th floor. 3C & 3D completion of 5th (fifth) slab. • Actual site photograph PROGRESS TIMELINE July 21 August 21 September 21 October 21 November 21 Construction Updates

  5. Tower 2B, 2C, 2D & 2E 2B 2C MILESTONES ACHIEVED TOWER STATUS • • • • • 2B GF roof slab in progress. 2E Terrace slab completed. 2C 12th floor roof slab in progress. 2D 12th floor roof slab in progress. 2E waterproofing works 9th floor in progress. 2E putty works 1st floor in progress. • • • 2E completion of terrace slab. 2C & 2D Completion of 13th slab. 2B Completion of 1st slab. • UPCOMING MILESTONES 2D 2E • • • 2E completion flooring 1st to 3rd 2C & 2D completion of terrace slab. 2B Completion of 5th slab. Actual site photograph PROGRESS TIMELINE July 21 August 21 September 21 October 21 November 21 Construction Updates

  6. Tower 1A, 1B, 1C & 1D 1A 1B TOWER STATUS MILESTONES ACHIEVED • • • 1A Basement roof slab completed. 1B Basement roof slab completed. 1C Ground floor roof slab in progress. 1D Ground floor roof slab in progress. • • 1B, 1C & 1D Completion of 1st (first) slab. 1A Completion of first slab. • UPCOMING MILESTONES 1C 1D • • 1B, 1C & 1D completion of 5th (fifth) slab. 1A Completion of 5th slab. Actual site photograph PROGRESS TIMELINE July 21 August 21 September 21 October 21 November 21 Construction Updates

  7. Other Activities Clubhouse TOWER STATUS • • • • Clubhouse internal plastering works in progress. STP above truss work and internal water proofing in progress. UG Sump raft in progress. Podium pour1, pour 2 & pour3 concrete complete & pour4 works in progress. Actual site photograph PROGRESS TIMELINE July 21 August 21 September 21 October 21 November 21 Construction Updates

  8. Site Office : Provident Parksquare Judicial Layout, KanakapuraRd, Bengaluru, Karnataka 560062 Regional Office : Provident Housing Limited No.8, UlsoorRoad, Bengaluru-560 042 Tel: 080-44555544 Email : crm@providenthousing.com (Subject line –Project name/ unit number) Call Us : +91 -80-67724001 / 1 860 208 0000 Web : www.providenthousing.com RERA Registration Number : Phase 1 : PRM/KA/RERA/1251/310/PR/180217/002476 Phase 2 : PRM/KA/RERA/1251/310/PR/180507/001648 Phase 3 : PRM/KA/RERA/1251/310/PR/180507/001671 Phase 4 : PRM/KA/RERA/1251/310/PR/190129/002307 Phase 5 : PRM/KA/RERA/1251/310/PR/200226/003305