An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. August 2021

  2. Tower A Tower A Tower A TOWER STATUS MILESTONES ACHIEVED • • External plastering in progress. External compound wall in progress. 7th floor tiling in progress. 8th floor staircase putty in progress. • Completion of construction walls. • • UPCOMING MILESTONES • Completion of flooring. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates

  3. Tower B Tower B Tower B TOWER STATUS MILESTONES ACHIEVED • • External painting in progress. Head room masonry in progress. Up to 9th floor internal plastering completed. 6th floor tiling in progress. Internal wall putty work in progress. • Completion of construction walls. • • • UPCOMING MILESTONES • Completion of flooring. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates

  4. Tower C Tower C Tower C TOWER STATUS MILESTONES ACHIEVED • • South elevation external view. 8th floor internal plastering in progress. 4th floor internal wall putty work in progress. Compound wall work in progress. • Completion of 8th floor block work. • • UPCOMING MILESTONES • Completion of 9th floor block work. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates

  5. Tower D Tower D Tower D TOWER STATUS MILESTONES ACHIEVED • • South elevation external view. 5th floor internal plastering in progress. Terrace floor slab shuttering in progress. Up to 8th floor block work completed. • Completion of 8th floor block work except 805 flat. • • UPCOMING MILESTONES • Completion of 9th floor block work. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates

  6. Site Office : #TooGoodHomes - Provident Neora Near Manyata Tech Park, Off Thanisandra Main Road, Bengaluru, Karnataka 560064 Regional Office : Provident Housing Limited No.8, Ulsoor Road, Bengaluru- 560 042 Tel: 080-44555544 Email : crm@providenthousing.com (Subject line – Project name/ unit number) Call Us : +91 - 80-67724001 / 1 860 208 0000 Web : www.providenthousing.com RERA Registration Number : RERA No.: PRM/KA/RERA/1251/472/PR/180808/001982