An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. September 2021

  2. Tower 1 TOWER STATUS MILESTONES ACHIEVED • • • • • • • • • Finishing work in progress. Door polishing & Window grill work in progress. MEP work in progress. External painting. False ceiling & bison board work in progress. Door fixing 120 flats completed. Internal door 115 flats completed. External 1st paint 100% completed. SD fixing 120 flats completed. Lift gladding service lift completed. Bison board work 100 flats completed. Stilt floor IPS work completed. • • • UPCOMING MILESTONES • • • 1st coat paint complete 120 flats. Bison board & false ceiling 100%. Terrace OTS covering 100%. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  3. Tower 2 TOWER STATUS MILESTONES ACHIEVED • • • • • • • Except Hoist, External plastering completed. Tile dado & flooring in progress. Verified flooring in progress. External primer work in progress. External plaster 98% completed. Toilet dado & flooring 170 flats completed. Flooring tile 90 flats completed. 1st coat putty 225 flats completed. 2nd coat putty 205 flats. External primer 90% completed. • • • UPCOMING MILESTONES • • • • • • • External plaster 100% complete. Waterproofing 100% complete. Toilet dada 230 flats complete. Floor tile work 180 flats complete. 1st coat putty 100% complete. 2nd coat putty 100% complete. External 1st coat Primer 100% complete. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  4. Tower 3 TOWER STATUS MILESTONES ACHIEVED • • • • • Putty work in progress. Tile work in progress. Stilt floor material removing & Plumbing work in progress. External plaster 98% completed. 1st coat Putty work complete 120 flats completed. 2nd coat putty completed 96 flats. Tile work completed 120 flats. Toilet dado & flooring 120 flats completed. External primer 98% completed. • • • • UPCOMING MILESTONES • • • • • • External plaster 100% complete. 2nd coat putty 120 flats. Tile work complete 120 flats. External primer 100% complete. Kitchen counter 50 flats complete. South side staircase floor complete. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  5. Tower 4 TOWER STATUS MILESTONES ACHIEVED • • • • • Finishing work in progress. Door fixing work in progress. False ceiling work in progress. Stilt floor MEP work in progress. Finishing work 111 flats completed. Service lift gladding & passenger lift gladding completed. Stilt floor Screed completed. Bison board work 110 flats & false ceiling work 120 flats completed. 1st coat paint 55 flats completed. 2nd coat paint 53 flats completed. • • • • • UPCOMING MILESTONES • Finishing work will complete. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  6. Tower 5 TOWER STATUS MILESTONES ACHIEVED • • • • • • • • • • • Tile work in progress. Putty work in progress. Kitchen granite in progress. Stilt floor Block work in progress. External primer work in progress. Upvcwork in progress. Tile work completed 60 flats. Toilets dado & flooring 60 flats. 2nd Coat putty 88 flats completed. Lift waterproofing completed. External primer 95% completed. Windows fixing 105 flats completed. Kitchen counter 18 flats completed. • • UPCOMING MILESTONES • • Tile work complete 120 flats. Stilt floor columns plaster & wall plaster complete 100%. 2nd coat Putty work complete 120lats. Lift Plaster complete 100%. External primer 100% complete. Kitchen counter 60 flats completed. Actual site photograph • • • • PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  7. Tower 6 TOWER STATUS MILESTONES ACHIEVED • • • • • • • • • • • • • Tile work in progress. Putty work in progress. Door fixing work in progress. Kitchen granite work in progress. Tile work completed 96 flats. Toilet dado & flooring 90 flats completed. Putty completed 120 flats. 2nd coat putty work completed 108 flats. Internal plastering 100% completed. Service lift gladding work completed. External primer 100% completed. External 1st painting 80% completed. IPS concrete work completed. UPCOMING MILESTONES • • • • • Tile work complete 120 flats. Putty work complete 100%. Passenger lift gladding work complete. External primer complete 100%. External 1st coat paint complete 100%. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  8. Tower 12 TOWER STATUS MILESTONES ACHIEVED • • • • • • • Wall & ceiling 1st Coat putty work in progress. External wall Primer work in progress. Toilet rough plaster work in progress. Tile marking in progress. 1st coat putty completed 95 Flats. Toilet rough plaster 108 flats completed. External wall plaster 100% completed. Toilets & utility white wash 100% completed. External primer 95% completed. Basement IPS flooring completed 70%. • • • UPCOMING MILESTONES • • • • • 1st coat putty completed 120 Flats. Toilet rough plaster 100% complete. External wall plaster 100% complete. External primer 100% complete. Basement IPS flooring 100% complete. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  9. Tower 13 TOWER STATUS MILESTONES ACHIEVED • • • • • • • • • Terrace floor & Waterproofing screed concrete in progress. External plastering in progress. Internal Wall & ceiling plaster in progress. Toilet waterproofing & screed work in progress. External primer in progress. Flats ceiling plaster completed 192 flats. Toilet waterproofing completed 140 flats. Toilet screed completed 120 flats. External plastering completed 75% Internal wall plaster completed 179 flats. External wall primer 50% completed. 1st coat putty 107 flats completed. Terrace waterproofing & concrete 12 flats completed. • • • UPCOMING MILESTONES • • • • • • • • Flats ceiling plaster complete 100%. Toilet waterproofing complete 150 flats. Toilet screed complete 150flats. External plastering complete 85%. Internal wall plaster complete 100%. 1st coat putty complete 120 flats. Terrace waterproofing complete 100%. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 September 21 Construction Updates

  10. Site Office : Provident Kenworth 6-1-33, Inner Ring Rd, ShivrampalliVillage, ShivarampallyJagir, Hyderabad, Telangana 500052 Regional Office : Provident Housing Limited No.8, UlsoorRoad, Bengaluru- 560 042 Tel: 080-44555544 Email : crm@providenthousing.com(Subject line – Project name/ unit number) Call Us : +91 - 80-67724001 / 1 860 208 0000 Web : www.providenthousing.com