Tower R TOWER STATUS MILESTONES ACHIEVED • Above terrace works completed. Preparation for waterproofing work in progress. Gypsum 11th floor completed. Tilling 2nd & 3rd floor in progress. Balcony railing 12th floor completed. Putty works 4th & 5th floor in progress. Walls completed. • UPCOMING MILESTONES • • • • • Flooring 2nd floor. UPVC 1st floor. • Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates
Tower Q TOWER STATUS MILESTONES ACHIEVED • Above terrace works completed. Preparation for waterproofing work in progress. Gypsum 11th floor completed. Balcony railing 12th floor completed. Putty works 2nd floor in progress. Walls completed. • UPCOMING MILESTONES • • • Flooring 1st floor. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates
Tower P TOWER STATUS MILESTONES ACHIEVED • Above terrace works completed. Gypsum 1st floor in progress. Balcony railing 8th floor completed. Walls completed. • • UPCOMING MILESTONES Flooring 1st floor. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates
Tower N TOWER STATUS MILESTONES ACHIEVED • • Terrace slab completed. Parapet wall work in progress. • • 12th floor roof slab completed. 12th floor walls completed. UPCOMING MILESTONES 1st floor flooring. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates
Tower M TOWER STATUS MILESTONES ACHIEVED • • Shear wall in progress. Basement roof slab shuttering in progress. Completion of Foundation. UPCOMING MILESTONES Completion of Ground floor roof slab. Actual site photograph PROGRESS TIMELINE April 21 May 21 June 21 July 21 August 21 Construction Updates
Tower L TOWER STATUS MILESTONES ACHIEVED • • Foundation works completed. Shear wall work in progress. Completion of foundation. UPCOMING MILESTONES Completion of Ground floor roof slab. Actual site photograph PROGRESS TIMELINE June 21 July 21 August 21 Construction Updates
Tower K TOWER STATUS MILESTONES ACHIEVED • • Excavation works in progress. Foundation works in progress. Excavation in progress. UPCOMING MILESTONES Completion of Excavation. Actual site photograph PROGRESS TIMELINE July 21 August 21 Construction Updates
Site Office : Provident Equinox - #myhomemylife Mysore Road - NICE Junction, Bangalore, Karnataka 560060 Regional Office : Provident Housing Limited No.8, Ulsoor Road, Bengaluru- 560 042 Tel: 080-44555544 Email : crm@providenthousing.com (Subject line – Project name/ unit number) Call Us : +91 - 80-67724001 / 1 860 208 0000 Web : www.providenthousing.com RERA Registration Number : PRM/KA/RERA/1251/310/PR/190525/002576 PRM/KA/RERA/1251/310/PR/190529/002585