1 / 44

Chapter 14 – Resource Planning

Chapter 14 – Resource Planning. Elephants are the only animals that can't jump. It's possible to lead a cow upstairs but not downstairs. Our eyes are always the same size from birth, but our nose and ears never stop growing. SCARY!!!

Download Presentation

Chapter 14 – Resource Planning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Chapter 14 –Resource Planning • Elephants are the only animals that can't jump. • It's possible to lead a cow upstairs but not downstairs. • Our eyes are always the same size from birth, but our nose and ears never stop growing. SCARY!!! • A crocodile cannot stick its tongue out. • Emus and Kangaroos can not go backwards.

  2. Learning Objectives • Describe enterprise resource management • Describe the evolution of ERP Systems • Describe the benefits and costs of ERP systems • Provide an overview of MRP • Explain the different types of demand • Describe the objectives of MRP • Describe the inputs needed for MRP • Explain MRP operating logic

  3. Learning Objectives (continued) • Describe action notices • Use different lot size rules with MRP • Describe the role of capacity requirements planning (CRP) • Calculate the work loads at critical work centers using CRP

  4. Enterprise Resource Planning • What Is ERP? • Software designed for organizing and managing business processes • Modules share information across all business functions • Can share customer sales data with the supply chain to help with global replenishment • All modules are fully integrated and use a common database – some PC based

  5. Integration of ERP

  6. ERP Modules-4 Categories • Finance and accounting • Investment, cost, asset, capital, and debt management • Budgets, profitability analysis, and performance reports • Sales and marketing • Handles pricing, availability, orders, shipments, & billing • Production and materials management • Process planning, BOM, product costing, ECN’s, MRP, allocates resources, schedules, PO’s, & inventory • Human resources • Workforce planning, payroll & benefits, & org. charts

  7. Evolution of ERP • First generation ERP • Managed all routine internalbusiness activities • From order entry to after-sales customer service • Lacked supply chain support modules (added in second generation)

  8. Evolution of ERP • Second Generation ERP • Late 1990’s software integrated supply chains • Systems focused on decision-making • SCM modules include linear programming (LP) and simulation support • SCI capability allows collection of intelligence along the entire supply chain • ASP suppliers set-up and run systems for others

  9. Integrating ERP and E-Commerce • Many companies with ERP use e-commerce • E-commerce needs to interface with ERP • Cybex International is a good example: • Needed to integrate B2C and B2B transactions • Cybex installed a Peoplesoft, Inc. ERP system • Reduced BOM’s from 15,200 to 200, suppliers from 1000 to 550, paperwork by 2/3 • Reduced supplier material shortages and customer order-to-ship time from 4 to 2 weeks

  10. Benefits of ERP Implementation • ERP presents a holistic view of the business functions from a single information and IT architecture • Increases organizational information flow • Increases ability to incorporate better management control, speedier decision making, and cost reductions • Allows replacement of disparate systems e.g. Exxon-Mobile used ERP to replace 300 different systems • A study of ERP implementations reports that benefits typically start 8 months after implementation with median annual savings of $1.6 million

  11. Cost and Implementation Issues • Major suppliers are SAP, Peoplesoft, Oracle, and Baan. Also smaller PC based suppliers. • Costs for larger ERP systems range from hundreds of thousands to several million dollars. • Outside consultants are usually involved in selection, configuration, and implementation. • Consultant costs can run up to 3 times the cost of the system itself according to a Gartner Group study. • Added costs also include additional people, new computer hardware, and the cost to develop a new, integrated database • Successful implementation requires leadership and top management commitment to a vision for the business

  12. Evolution of Material Planning Systems • Back in the sixties, manufacturing planning systems were reorder point systems that simply determined when and how much to order • FirstMRP systems translated a master schedule of final products into time-phased net requirements for subassemblies, assemblies, and parts • Closed-loop MRP included production planning, master scheduling, and capacity requirements • In mid 1970’s, MRPII systems added functionality to plan and execute all internal functions

  13. An Overview of MRP • MRP uses the concept of backward scheduling to determine how much and when to order and replenish • The CRP module checks to make sure the scheduled work load profile is feasible • The MPS module contains the authorized schedule • The BOMmodule contains the product structure for each unique product • The Inventory Record module keeps track of the inventory status for each item in the database • MRP output includes schedules for all internal activities and parts as well as orders for all supply chain items

  14. Input/Output - MRP Process

  15. Types of Demand • There are two types of demand. • Independent Demand • Is the demand for finished products • Does not depend on the demand of other products • Needs to be forecasted • Dependent Demand • Is the demand derived from finished products • Is the demand for component parts based on the number of end items being produced and is managed by the MRP system

  16. Objectives of MRP • Determines the quantity and timing of material requirements • Determines what to order (checks BOM), how much to order (lot size rules), when to place the order (need date minus lead time), and when to schedule delivery (on date needed) • Maintain priorities • In a changing environment, MRP reorganizes priorities to keep plans current and viable

  17. Building a CD Cabinet With MRP

  18. MRP Inputs - Authorized MPS • From the authorized MPS, we calculate when we need to have replenishment orders of CD cabinets; when we need a new MPS order.

  19. MRP Inputs-Inventory Records • System checks the inventory record for each BOM item to see if inventory is available or if a replenishment order is needed to build the cabinets.

  20. MRP Inputs-Bills of Material • A BOM lists all of the items needed to produce one CD cabinet • The BOM is exactly like a recipe for baking a cake • The BOM’s must be complete and accurate and can only be changed by an ECN • MRP BOM’s are indented bills of materials

  21. A Product Structure Tree

  22. A 0 L (20) B (2) C (1) D (3) E (2) 1 F (4) L (2) H (3) K (5) I (2) J (1) G (2) 2 3 L (6) L (2) M (2) L (20) M (3) K (1) L (2)

  23. A 0 1 L (20) B (2) C (1) D (3) E (2) 2 6 2 2 3 1 2 3 2 4 8 5 2 F (4) L (2) H (3) K (5) I (2) J (1) G (2) 2 3 3 3 5 3 3 3 2 3 L (6) L (2) O (2) M (2) L (20) M (3) N (1) L (2)

  24. ASSEMBLY TIME CHART

  25. The MRP Explosion Process • Using table 14-6 and the product structure tree, we will work through an example of how the MRP explosion process would calculate the requirements for building a CD cabinet. On the next slide we start with the cabinet top to illustrate how MRP calculates the gross requirements for this component.

  26. Inventory Records - Components • It was noted on the previousslide that theparent item (CD Cabinet) has planned orders in periods 3, 6, and 9. • Its children (top, bottom, door, left & right side, shelves, and supports) have gross requirements in periods 3, 6, and 9.

  27. Inventory Records - Components

  28. Inventory Records– Components(cont.)

  29. Inventory Records – RemainingComponents

  30. Inv. Records – RemainingComponents (cont.)

  31. A 0 NA 0 L4L 1

  32. A 0 NA 0 L4L 1 B C D

  33. MRP Action Notices • Action Notices: • Indicate items that need a production planner’s attention • Are created when: • a planned order needs to be released, • due dates need to be adjusted, or when • there is insufficient lead time for normal replenishment • Often require planners to rush or expedite orders • Action Bucket: • Is the current period where we take actions such as releasing, rescheduling, or canceling orders • A positive quantity in current period’s planned order row means that an order must be released

  34. Example Comparing Lot Size Rules:Three common lot sizing rules used within MRP Systems are fixed order quantity (FOQ), lot for lot (L4L), and period order quantity (POQ). Cost comparison is based on Inventory holding costs ($0.10 per period) and ordering cost ($25 per order). In this example POQ is best at $133.50.

  35. Capacity Example: The CRP module uses data from MRP. We calculate workloads for critical work centers based on open shop orders and planned shop orders. These shop orders are translated into hours of work by work center and by time period.Table 14-11 show items scheduled for work Center 101. • Available Capacity = 4 machines x 2 shifts x 10 hours per shift x 5 days per week x 0.85 utilization - x 0.95 efficiency • Available Capacity = 323.0 standard hours

  36. Workload Graph for Work Center 101: CRP enables a company to evaluate both the feasibility of the MRP system and how well the company is using its critical work centers.

  37. Resource Planning Across the Organization • Since MRP determine the quantity and timing of materials needed, it affects several functional areas • Accounting future material commitments based on MRP output • Marketing is primarily concerned with MPS as the MRP reveals potential material shortages • Information systems maintains the MRP and the MPS

  38. Chapter 14 Highlights • ERP is software designed for organizing and managing all business processes by sharing information across functional areas using a common database and a single computer system. • First generation ERP systems (MPR) managed manufacturing activities only. Second generation systems or SCM –software incorporated the supply chain. The current trend is integrating e-commerce and ERP. • Tangible benefits from ERP include control of operations and a host of information to manage all financial aspects of a business. Systems can be very expensive.

  39. Chapter 14 Highlights (cont.) • MRP systemsare designed to calculate material requirements from dependent demand items. MRP uses backward scheduling to determine activity start dates. • The objective of MRP are to determine quantity and timing of material requirements to keep schedule priorities updated and valid. • MRP needs three inputs: the authorized MPS, the BOM file, and the inventory records file. • Once the MPS has been input, MRP checks inventory availability. If a need is determined, MRP checks the BOM file for material needed, then generates planned orders.

  40. Chapter 14 Highlights (cont.) • MRP output includes actions notices to release planned orders, reschedule orders, or adjust due dates. • Different lot sizing rules (FOQ, Period Q, L4L) generate different order quantities and order frequencies. • The CPR module uses planned orders and open shop orders to see if available capacity is sufficient to meet schedules. • CPR calculates the workloads at critical work centers by using planned orders generated by MRP. These planned orders are multiplied by the standard times to calculate individual work center loads.

More Related