Allen Park Presbyterian Church Facility Study 2007-08
Facility Study 2007-08 History • Doug Pretty introduces Bill McCarthy, McCarthy & Smith, to Pastor Doug Blaikie. • Doug Pretty and Bill McCarthy met with members of Building Committee in July 2007 to explain what and how a Facility Study could be accomplished.
Facility Study 2007-08 History • August 2007 - Building Committee hires architects Wilkie & Zanley and construction manager McCarthy & Smith to conduct Facility Study which will lead to conceptual drawings, estimated costs and schedule.
Facility Study 2007-08 History • Summer/Fall 2007 Onsite investigating, discussions with city conducted by Wilkie & Zanley. • Preliminary concepts presented in September 2007 to Building Committee. Committee directs team to further study additions option.
Facility Study 2007-08 History • McCarthy & Smith prepares cost estimates and schedule options. • Team presents report to Building Committee on December 19, 2007.
Building Committee Concerns • Fellowship Hall (Old Building) • Barrier-free access to lower and main levels • Multi-purpose space, air-conditioned • Church services in summer • Social/fellowship activities • Youth group activities • Additional columbarium space and inventory • Develop shower space for annual outreach programs • Develop designated storage areas • Upgrade electrical service to facilities
Building Committee Concerns • Main Church (New Building) • Barrier-free restroom facilities
Scenarios to Consider • Scenario #1 • Construct barrier-free addition and associated site work • Construct columbarium addition and associated basement storage • Barrier-free restrooms (Main Church) $1,300,000 Alternate for Development of Office Area $30,000
Options to Consider • Scenario #2 • Construct the multi-use addition at a later time. $1,300,000 Alternate for shower room facilities $20,000 Cost is based on 2008 construction dollars. Average price escalation per year is 4-5%.
Options to Consider • Scenario #3 • Construct both scenarios at the same time.(Represents a cost savings achieved through less redundant general condition and supervision costs.) $2,500,000
Schedule • Project Review and Approvals • Present to session committee 1/16/08 • Present to congregation at annual meeting 1/20/08 • Congregation to vote on project2/10/08?
Schedule • Design • Design Phase • Review and approval(5-1/2 months) 2/11/08 - 7/30/08
Schedule • Bid/Award • Bid/Award Phase(1 month) 8/1/08 - 8/29/08
Schedule • Construction • Scenario #1 • Barrier-free entrance addition • Columbarium addition • Assorted interior remodeling(6 months) • Barrier-free restrooms (main church) 9/15/08 - 3/27/09
Schedule • Construction • Scenario #2 • Multi-use addition(8 months) TBD
Schedule • Construction • Scenario #3 • Additions, entrance & multi-purpose • Columbarium addition • Interior remodeling9/15/08 - 5/30/09
Ken Lieber, Co-chair John Dam Shirley Slatka Jim Kinard Fern Brandt Doug Blakie, Pastor John Wilkie Bill McCarthy Jim Bebe, Co-chair Barry Davis Kelly Ellis Larry Templin Melody Jones, Associate Pastor Dave Zanley Steve Banchero AcknowledgementsAllen Park Presbyterian Church Building Committee Wilkie-Zanley, Architects McCarthy & Smith, Construction Managers
Allen Park Presbyterian Church Facility Study 2007-08