1 / 18

Last Two Years – 22 outages for total of 304 hours (12+ days)

Last Two Years – 22 outages for total of 304 hours (12+ days). Electrical Distribution Condition. Feeder lines are over utilized and failing. Cable, conduit, and vaults are failing. Too many buildings Share the same lines. SUBSTATIONS - Old/Obsolete - Fail to meet standards of access

raanan
Download Presentation

Last Two Years – 22 outages for total of 304 hours (12+ days)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Last Two Years – 22 outages for total of 304 hours (12+ days)

  2. Electrical Distribution Condition

  3. Feeder lines are over utilized and failing Cable, conduit, and vaults are failing Too many buildings Share the same lines

  4. SUBSTATIONS - Old/Obsolete - Fail to meet standards of access - Not compatible with RMP

  5. STADIUM SUBSTATION UPGRADE

  6. MEDICAL SUBSTATION REPAIRS AND UPGRADES

  7. RED BUTTE SUBSTATION UPGRADES

  8. TRANSFORMER REPLACEMENTS REQUIRED

  9. FAILED CIRCUIT BREAKERS TO BE FIXED

  10. BEFORE EXAMPLES OF SWITCH REPLACEMENTS BEFORE AND AFTER AFTER

  11. BEFORE AFTER EXAMPLES OF SWITCH REPLACEMENTS BEFORE AND AFTER

  12. Stadium substation construction schedule March 2013 – October 2013 Impacts: Power outages, equipment deliveries, and work around parking lots

  13. Campus-wide electrical distribution schedule March 2013 – December 2014 Phase 1: Lower & Upper Campus

  14. Electrical Distribution Lower Campus Ductbank Routing

  15. Electrical Distribution Upper Campus Ductbank Routing

  16. Resources • Construction impacts map • Current projects page • @UofUFM • Scott Jefferson, scott.jefferson@fm.utah.edu

More Related