An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Preparing an INTERREG IVC application: Financial and legal aspects Anne-Cécile RENARD, Finance Officer, INTERREG IVC JTS

  2. Partner Funding • Funding for partners from the EU + Norway • 75% / 85% ERDF co-financing rate depending on the Member State in which the partner is located (address!) (50% for Norway) • 25% / 15 % partner’s own financing from own funds or other public sources on national, regional or local level (50% for Norway) • no ERDF advance payments

  3. Partner Funding • Partners from EU-MS + Norway

  4. Partner Funding • Funding for partners from Switzerland • special funding available • funding directly managed by Switzerland • information provided by national contact point

  5. Partner Funding • Partners from outside EU/Norway/Switzerland • Participation possible • No co-financing from IVC programme • Funding maybe available through other EU-instruments (IPA, ENPI) • INTERREG IVC co-financing for activities outside EU/Norway/Switzerland possible if • limited to 10% of project’s IVC budget • costs budgeted, borne, paid by partner from EU/Norway • explicitly mentioned and justified in AF

  6. Partner Funding Partner Funding – Further Points of consideration • Is there a co-financing statement for each partner (EU + non-EU partner)? Is it on letter headed paper? Stamped? Signed? Does it confirm the amount of national co-financing as indicated in the Application form?

  7. Financial Management CA checks + compiles all data into Payment Request to EC Reporting and Control System Certifying Authority Progress Reports checked by Project Officer and Financial Officer in JTS Joint Secretariat/ Managing Authority Expenditure controlled by LP-controller and collection of PP cost statements Lead Partner (LP)/ Expenditure controlled by PP-controller Project Partner Project Partner Project Partner

  8. Financial Management • Country-specific control requirements • Organisation of the control = MS responsibility • Main types of systems (depending on MS) • Centralized system: certification through • Central public control or • Central private controller Central = at national or regional level • Decentralized system: certification through internal/external public and private controllers • chosen by partner from a shortlist established by MS or • proposed by partner and approved by central approbation body • Information per Member State on INTERREG IVC website

  9. Financial Management Financial Management – Further Points of Consideration • Explain who will carry out financial management? In-house or external? • Describe reporting and control procedure taking account of • role of Lead partner • reporting periods • January – June; PR submission 1 October • July – December; PR submission 1 April • country specific control requirements • ERDF payment to LP within approx. 3 weeks after approval of PR • Include this information also under Component 1 • Preparation + submission of Progress reports, receipt of ERDF + disbursement to partners = activity • Progress reports = output

  10. Eligibility • Preparation phase: costs are eligible • subject to project approval • within limit of EUR 30,000 • For first call: between 1 January 2007 and date of submission of AF to JTS (for first call = max.15 January 2008) • To be reported with Progress Report 1 • Project implementation phase: costs are eligible if • incurred after date of MC approval • paid before finalisation month quoted in the AF

  11. Budget • The budget lines • Staff • Administration for personnel employed • Travel and Accommodation by partners in AF only! • Equipment • External Expertise and Services • Sub-Projects for mini-programmes only

  12. Budget • Staff • Personnel costs for the time spent by staff on carrying out project activities (Full-time or percentage of total working time) • Only for personnel directly employed by the partner organisation listed in AF • Employee’s gross salary + employer’s charges

  13. Budget • Administration • Stationery • Photocopying • Mailing • Telephone, fax, Internet • Heating, electricity • Office rent, furniture, maintenance Don’t artificially inflate this budget line through inclusion of indirect cost categories (overheads) that lack a clear project link.

  14. Budget • Travel and Accommodation • Choice of most economic form of transport • In compliance with national or internal rules • Daily allowances possible if national or internal practice • Equipment • Purchase of material necessary for project implementation • Usually IT equipment • Should not exceed 5% of total costs

  15. Budget • External Expertise • Examples: • External project coordination or financial management • External financial control • Website design and hosting • Drafting, lay out printing of newsletters, studies and surveys • External event organisation, meeting room rental and catering • Interpretation and translation • External speakers and participants in meetings

  16. Budget • External Expertise • All expenses paid by the partners on the basis of • Contracts/agreements (public procurement!) • Invoices/requests for reimbursement to external providers (incl. staff, admin, travel etc.) • External = anyone who is not employed by partner institutions

  17. Budget • Sub-projects • For mini-programmes only • Forecast expenditure on sub-projects to be selected in open calls for proposals and transparent assessment + selection procedure.

  18. Budget • Budget - Further points of consideration • VAT – not eligible if recoverable • In-kind contributions - not eligible in INTERREG IVC

  19. Budget • Budget – Further Points of consideration • Did you respect budget recommendations (min/max ERDF)? • Is the total budget justified by project duration, scope + complexity of activities and partnership? • Does the detailed budget by budget line + component reflect the activities? • Is the ratio “administration/staff” below 25% (recommended)? • Is the ratio “Component 1/total budget” below 20% (recommended)? • Is the ratio “equipment/total budget” below 5% (recommended)? • Is the expertise and equipment necessary for project implementation (make specifications self-explanatory!)?

  20. Budget • Shared costs • Responsible partner has to provide to all partners taking over a share of common costs • request for reimbursement • all relevant supporting documentation • Responsibility of each partner to include share of common costs in own financial report and to obtain confirmation from controller (according to country specific control requirements) • Recommendation: • limit as much as possible shared costs to budget line “external expertise and services” • include procedure in partnership agreement • procedure for sharing and reporting costs to be checked with national controllers of each individual partner concerned.

  21. Budget • Payment forecast • Forecast of costs paid out during reporting periods • January – June • July – December • To be prepared carefully as projects not reporting in time and in full risk losing funds

  22. Further Information • Operational programme • Programme manual • Programme website • JTS + Info Points • National contact points Thank you for your attention!