RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) CATEGORY-II
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) CATEGORY-II
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Name of the Contractor : M/s R.M.M &BRC (JV) Agreement Amount : Rs. 57.97Crs. Agreement Date : 03-03-2005 Period of Completion : 24 Months (8 milestones) Date of completion : 03-03-2007 Package No. 13/Cat-II : Excavation of High level right main canal, distributary system including construction of CM & CD works from Sangambanda BR to feed ayacut of 18400 Acres. • Investigation completed : Completed • Designs : 9.2 KM approved against 24 KM • Execution (Main canal) : 15 KM length in progress against total length of 24.00KM • Qty. of earth work done : 6.00Lakh Cum against 37.32 Lakh Cum. • Qty. of concrete work done : 500 cum against 3500 cum • No. of Machinery : Deployed = 15Nos (Excavators =2 Nos.,Tipper-8Nos., T Roller- 2Nos., Dozers = 1 Nos., Water tank -1No.Crushing plant-1No.) • Land Acquisition : Required 1000 Acres, Requisition : 260 acres, Acquired – 81 acres • Expenditure : Rs. 14.90 Crs. against Rs. 57.97 Crs., • Mob. Adv. Paid : Rs. 2.90 Crs. • Mob. Adv. Recovered : Rs. 2.90 Crs. • Bottlenecks : Land Acquisition
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Name of the Contractor : M/s VPR– Coromandal (JV) Agreement Amount : Rs. 68.94Crs. Agreement Date : 05-03-2005 Period of Completion : 24 Months (8 milestones) Date of completion :24-02-2007 Package No. 14/Cat-II : Excavation of High level left main canal, distributary system including construction of CM & CD works etc. to feed an ayacut of 35,800 Ac. Under Sangambanda BR, • Investigation : Completed (40.645 KM) • Designs : Main canal completed (40.465 KM) • Execution (main canal) : 28.75KM length in progress against total length of 40.645 KM • Qty. of earth work done : 18 Lakh Cum against 26.20 Lakh Cum. • Qty. of concrete work done : 1500 cum • No. of Machinery : Deployed = 29Nos (Excavators = 6 Nos., Dozers = 2 Nos, Tippers = 21Nos. etc) • Expenditure : Rs. 29.88 Crs. against Rs. 68.94 Crs., • Mob. Adv. Paid : Rs. 6.88 Crs. • Mob. Adv. Recovered : Rs. 1.68 Crs. • Land Acquisition : Required 1867 Acs, Requisition : 651 Acquired– 205.54 Acres
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. 15/Cat-II : Investigation, design, estimation and excavation of canal distributary system including construction of CM & CD works from Yenukunta BR, Waddewata (V), Kottakota (M), Mahabubnagar (D) to feed about 14,000 Acres upto Rangasamudram BR. Name of the Contractor : M/s Prathibha – Ch MR- (JV) Agreement Amount : Rs. 51.27 Crs. Agreement Date : 05-03-2005 Period of Completion : 24 Months (8 milestones) Date of completion : 05-03-2007 • Investigation : Completed (30.25 KM) • Design : 26.75 KM approved against 30.25 KM • Execution (main canal) : 13 KM length in progress against total length of 30.25 KM • Qty. of earth work done : 5,70,000 Cum against 20,00,000 Cum • No. of Machinery : Deployed = 28Ns (Excavators = 6 Nos., Tippers=20Nos, Leveller =2No.) • Land Acquisition : Required 943 Acres, Requisition :407Acs. Acquired – 218.71Acs. • Expenditure : Rs. 8.12 Crs. (Inc. Mob. Adv. Rs. 5.12 Crs.) against Rs. 51.27 Crs.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Name of the Contractor : M/s RNS-GSR & Co. (JV) Agreement Amount : Rs. 70.80Crs Agreement Date : 02-03-2005 Period of Completion : 24 Months (8 milestones) Date of completion : 02-03-2007 Package No. 16/Cat-II : Excavation of canal distributary system – including construction of CM & CD works from Ranga Samudram to feed an ayacut of 21,000 Acres. • Investigation (HPs) : Length 58Kms finalised against 81Kms • Execution : Excavation in 1.5 KM length in progress against total length of 81.00 KM • Qty. of earth work done : 10,000 Cum against 16,00,000 Cum • No. of Machinery : Deployed = 15 Nos (JCB-1No.Excavators = 4 Nos, Tippers-2Nos, S.Crushers- 2Nos, Hard top jeep-4Nos) • Expenditure : Rs. 3.54Crs. (Mob. Adv. Only) against Rs. 70.80 Crs. • Land Acquisition : Required 1415 Acres, Requisition: 162.34Acres Acquired – Nil • Bottle Necks : Land Acquisition
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. 17/Cat-II : Investigation, design, estimation and execution for converting the existing Rangasamudram tank, near Sri Rangapuram (V) Pebbair (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II) Name of the Contractor : M/s A L S-KVR(JV) Agreement Amount : Rs. 41.50 Crores Agreement Date : 07-03-2005 Period of Completion : 24 Months (8 milestones) Date of completion : 07-03-2007 • Investigation : Completed • Designs (Earth Bund & Weir) : 80% approved • Execution : Started • Qty. of earth work done : Cut off trench excavated for a length of 1.50 KM • Expenditure : Rs. 2.08 Crs. (Mob. Adv. Only) against Rs. 41.50 Crs. • Land Acquisition : Required 2452.30Acres, Requi.: 2526.11Acrs Acquired – Nil • Bottle Necks : Land Acquisition
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. 18/Cat- : Investigation, design, estimation and execution for convesting the existing Shankarasamudram tank, near Knaipally (V) Kothakota (M), Mahabubnagar district as balancing reservoir under Bhima Lift Irrigation Project (Lift-II) Name of the Contractor : M/s Sri Avanthika Saivenkata (JV) Agreement Amount : Rs. 42.10 Crores Agreement Date : 14-03-2005 Period of Completion : 24 Months(8 Mile Stones) Date of completion : 14-03-2007 • Investigation : Completed (3.69 KM) • Designs (Earth bund & Weir) : 80% of designs approved. • Execution : Yet to start (Water in the Tank & objections of Kanepally (V) for want of inclusion of village in R & R Package. • Expenditure : Rs. 2.11 Crs. (Mob. Adv. only) against Rs. 42.10 Crs. • Land Acquisition : Required 2220 Acres, Requisitioned: 1491Ac. Acquired – 1436 acres
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Name of the Contractor : M/s G. H. Reddy & Associates K.K.R & Co. (JV), Agreement Amount : Rs. 36.90 Crores Agreement Date : 19-02-2005 Period of Completion : 24 Months (Milestones : 8) Package No. 19/Cat-II : Shankara Samudram Balancing Reservoir Right Main canal. • Investigation : Completed (39 KM) • Designs (HPs & Structures): approved • Execution : 34 KMlength in progress against total length of 39 KM • Qty. of earth work done : 5.5 Lakh Cum against 6 Lakh Cum. • Qty. of concrete work done: 2500 cum against 30,000 cum • Structure : 25 Nos. executed against 110 Nos. • Expenditure : Rs. 16.68 Crs. against 36.79Crores • Mob. Adv. Paid : Rs. 3.68 Crs. • Mob. Adv. Recovered : Rs. 0.70 Crs. • Land Acquisition : Required 800 Acres, Requisitioned 459 Acs Acquired – 236 acres
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. 20/Cat- : (i) Formation of Earth Dam of Budpur with FRL +352m (ii) Construction of spillway, (iii) Construction of Head Regulator to let out into left and right main canals. Name of the Contractor : M/s KNR-SLEC (JV), Hyd. Agreement Amount : Rs. 36.98Crs Agreement Date : 07-03-2005 Period of Completion : 24 Months (8 milestones) • Investigation : Completed (6.10 KM) • Designs : Approved • Execution : Qty. of earth work 5.64 Lakh cum completed. • Expenditure : Rs. 15.43 Crs. (Inc. Mob. Adv. Rs. 3.43 Crs.) against Rs. 36.98Crs. • Mob. Adv. Recovered : Rs. 1.37 Crs. • Machinery deployed : Excavator-1No., Tippers-5No., Dozer-1No., Other M/C-7Nos. • Land Acquisition : Required 2073.11 Acres, Requisitioned- 2073.11 Acs Acquired – 358Acs.
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. 21/Cat-II : Investigation, Designs and excavation of left main canal, distributary system including construction of CM & CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres Name of the Contractor : M/s S.V.E.C Co., Hyd. Agreement Amount : Rs. 60.39 Crores Agreement Date : 25-02-2005 Period of Completion : 24 Months (milestones) • Investigation : completed (32 KM) • Designs (HPs & Structures) : Length 28.65 Km approved against 37.825Kms. • Execution (Canal) : 28.10KM length in progress against total length of 37.825KM • Structures : 13 Nos. executed against 79 Nos. • Machinery deployed : 10Nos. (Tippers-4Nos, Poclains-4Nos, DRR-1No,Dozer-1No.) • Land Acquisition : Required 1386 Acres, Requisitioned: 316Acs Acquired – 98 Acs. • Expenditure : Rs. 18.04 Crs. (inc. mob. Adv. Rs. 6.04 Crs.) against Rs. 60.39 Crs. • Bottle necks : Land acquisition – not handed over by Revenue authorities
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. 22/Cat- : Investigation, Designs and excavation of right main canal, distributary system including construction of CM & CD works from budpur Balancing reservoir, Budpur (V), Atmakur (M), Mahabubnagar (D) to feed about 32,000 Acres Name of the Contractor : M/s S.V.E.C Co., Hyd. Agreement Amount : Rs. 26.73 Crores Agreement Date : 25-02-2005 Period of Completion : 24 Months (8 milestones) • Investigation : Completed (15.025 KM) • Design (HPs) : Approved • Execution (Canal) : 14.50KM length in progress against total length of 15.025KM • Qty. of earth work done : 2.86 Lakh cum against 2.95 Lakh cum • Qty. of concrete work done: 5200 cum • Structures : 23 Nos. executed against 54 Nos. • Expenditure : Rs. 14.68 Crs. (Inc. Mob. Adv. Rs. 2.68 Crs.) against Rs. 26.73 Crs. • Mod. Adv. Recovered : Rs. 0.73 Crs. • Machinery deployed : 13Nos. (Tippers-4Nos, Poclains-7Nos, DRR-1No,Dozer-1No.) • Land Acquisition : Required 354 Acres, Requisitioned: 212Acres Acquired – 128 Acs. • Bottlenecks : Land acquisition
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. OC (Pkg. 27): Investigation, Design, excavation of left main canal, distributary system including construction of CM & CD works from Sankarsamudam Balancing Reservoir . Name of the Contractor : M/s KNR Const. Ltd. & BPL (JV) Agreement Amount : Rs. 149.40Crs. Agreement Date : 9/2005 AGREEMENT DATE : 9/2005 INVESTIGATION and DESIGNS are in PROGRESS Financial – Rs. 7.47 Crores (Mob. Adv. Only) against Rs. 149.40 Crores • Land Acquisition: • Required : 3,000 Acs. • Requisitioned : 169.95 Acs. • Acquired : Nil
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. EPC / OC- : LIFT-I : Design, manufacture, supplying & erection of pumps, motors, electro mechanical works, including tunnel, cistern and pump house etc. Name of the Contractor : M/s Patel Engineering Ltd. Agreement Amount : Rs. 383.349Crores Agreement Date : 07-03-2005 Period of Completion : 30 Months (10 milestones) • Investigation :Completed (3.0725 KM) • Designs (Tunnel, Pump House, Surge pool, Cistern): 2.70 KMapproved against 3.0705 • Execution : Excavation in progress (approach channel, tunnel, surge pool & Pump house) • Qty. of earth work done : 5.50 Lakh Cum against 7.82 Lakh Cum. • No. of Machinery : Deployed = 8 Nos (Excavators = 6 Nos., Dozers = 2 Nos. etc) • Land Acquisition : Required 250 Acres, Requisitioned 218Acs Acquired – 111 Acs. • Expenditure : Rs. 52.16 Crs. against Rs. 383.34 Crs. (Mob. Adv paid – Rs. 19.58 Crs.) • Mob Adv. Recovered : Rs. 1.61 Crs. • Bottlenecks : Land Acquisition
RAJIV LIFT IRRIGATION SCHEME (BHIMA PROJECT) Package No. EPC / OC- : Design and execution of Stage-I and stage-II pumping stations of lift-II at Thirumalayapalli & Kothakota (M), Mahabubnagar (D) on EPC basis. Name of the Contractor : M/s NEC – NCC – MAYTAS (JV) Agreement Amount : Rs. 391.55 Crores Agreement Date : 14-03-2005 Period of Completion : 30 Months • Investigation : Completed (3.132 Kms) • Designs (Tunnel, Pump House, Surge pool, Cistern): Approved • Execution : Excavation 0.383Km in progress (approach channel, tunnel, surge pool & Pump house) • Qty. of earth work done : 1,70,000 Cum against 5 Lakh Cum. • No. of Machinery : Deployed = 18 Nos (Excavators = 4 Nos., Dumpers = 12 Nos., Dozers = 2 Nos. etc) • Land Acquisition : Required 135 Acres, Requisitioned 67 Acs. Acquired – Nil • Expenditure : Rs. 71.58 Crs. against Rs. 391.55 Crs. • Mob. Adv. Paid : Rs. 19.58 Crores. • Mob. Adv. Recovered : Rs. 6.00 Crores.