1 / 10

Task7: NUSTAR2 - Design and Prototype Construction of a Radiation-Resistant Magnet

Task7: NUSTAR2 - Design and Prototype Construction of a Radiation-Resistant Magnet. C. Mühle GSI Task leader: G. Moritz /GSI. High-radiation area. Design parameters and layout of the Super-FRS. Recap of first year. Original idea: Use of superconducting radiation resistant dipoles

rania
Download Presentation

Task7: NUSTAR2 - Design and Prototype Construction of a Radiation-Resistant Magnet

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Task7: NUSTAR2 - Design and Prototype Construction of a Radiation-Resistant Magnet C. Mühle GSI Task leader: G. Moritz /GSI

  2. High-radiation area Design parameters and layout of the Super-FRS

  3. Recap of first year • Original idea: • Use of superconducting radiation resistant dipoles • Investigation of radiation loads: • Heat load on the cryogenic system for a 5 ton magnet: ≈ 2.3 kW (expected FAIR cryogenic power: 20 kW) => economic operation not possible • Decision • Normal conducting magnets with mineral insulated cable (MIC) • Surveying and alignment system for high-radiation areas • Not directly influenced by this decision • => Main work in 2006 was dedicated to the conceptual design of a dipole with MIC

  4. Conceptual design of a dipole with MIC: Cooling • Cooling options: • direct: hollow conductor • indirect: solid conductor + radiator • Direct cooling: • Advantage: good heat transfer • Disadvantage: radiolysis • Indirect cooling: • Advantages: • pressure drop and cooling power can be designed independently from coil • no radiolysis • water and power connectors separated • Disadvantage: limited heat transfer • Decision: indirect cooling

  5. Conceptual design of a dipole with MIC: Coil • Conductor: • Cable Size 19mm x 19mm • Sheath Thickness 1 mm • Insulation Thickness 1 - 1.5 mm • Cond. Area 190 mm2 • Unit Length 100m • Radiator: • Copper plate 12 mm thick • Stainless steel tube 10x1mm • Coil system: • 2 x 192 turns, 12 columns, 2 x 16 layers • 2 x 8 double pancakes • ≈ 100 m conductor per single pancake • total conductor length ≈ 3.2 km

  6. Conceptual design of a dipole with MIC: Yoke • Requirements: • α=11°, r=12.5m, Bmax=0.15-1.6T L=2.39m • Useful aperture 380x140mm (ΔB/B≤±2x10-4) • Gap height 170mm • Yoke design • H-type • Curved • Laminated • thickness 2 bis 4 cm • cut by laser • final milling of pole profile • Cross section 2740mm x 2020 mm • Yoke weight 85 t • Pole shims but no active correction • Longitudinal split into 3 parts

  7. Conceptual design of a dipole with MIC: Dipole operation • I=610A • P=122kW • Cooling • ΔT=21.9K • 79.2 l/min @ 1bar • Conductor temperature: • Return water temperature +40K

  8. Construction of a prototype dipole with MIC • To be done in the remaining project time: • Manufacturing design • Production of tooling and first (test) double pancake • Production of full coil • Production of yoke • Assembly of final magnet • Time scale • ≈ 1 year => close to the limit, but still feasible • Cost estimation of prototype magnet incl. tooling: 1.5 M€ • Budget • This task: 568 k€ (50%EU,50%GSI) • Budget gap: ≈ 950 k€ • Redirect money from other tasks • Finance remaining gap by GSI

  9. Surveyingand alignment system for high-radiation areas • Measurement concept and simulation of alignment approach nearly finished • Photogrammetric solution on Super-FRS target area working platform with four cameras on two movable vehicles • Sequential photogrammetric survey of inaccessible areas during shutdown

  10. Surveying and alignment system for high-radiation areas Problems to solve: • mounting and fiducialization of excentric magnet points • Penetration of shielding between magnets and working platform • Remote-controlled adjustment of magnet positions (radiation! weight!)

More Related