1 / 63

St. Peter Claver School Reconstruction & Rehabilitation Project 2009-2014

St. Peter Claver School Reconstruction & Rehabilitation Project 2009-2014. ST. PETER CLAVER SCHOOL: THE NEW VISION! A FIVE YEAR VISION. SCHOOL PROFILE. ESTABLISHED: SEPTEMBER 1862 POPULATION PRIMARY SCHOOL: 885 Students 439 Girls 446 Boys

Download Presentation

St. Peter Claver School Reconstruction & Rehabilitation Project 2009-2014

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. St. Peter Claver School Reconstruction & Rehabilitation Project2009-2014

  2. ST. PETER CLAVER SCHOOL: THE NEW VISION! A FIVE YEAR VISION

  3. SCHOOL PROFILE ESTABLISHED: SEPTEMBER 1862 POPULATION PRIMARY SCHOOL: 885 Students 439 Girls 446 Boys PRESCHOOL: 27 Students 17 Girls 10 Boys TOTAL: 912 Students NUMBER OF BOYS: 456 NUMBER OF GIRLS: 456

  4. SCHOOL PROFILE ESTABLISHED: SEPTEMBER 1862 POPULATION PRIMARY SCHOOL: 939 Students 470 Girls 469 Boys PRESCHOOL: 30 Students 19 Girls 11 Boys TOTAL: 969 Students NUMBER OF BOYS: 480 NUMBER OF GIRLS: 489

  5. STAFF 2009-2010 1 Administrative Principal 2 Administrative Vice Principals 2 Preschool Teachers 35 Primary School Teachers (Infant 1-Standard 6)

  6. GOALSOF THEPROJECT

  7. Construct two two- storey concrete buildings with 28 new classrooms . • Construct two fences to secure the infrastructure of the school. • Rehabilitate 2 existing buildings with 13 classroom • Rehabilitate the existing school library • Provide furniture for the whole school • Improve the recreational facilities of the school.

  8. PROJECT OVERVIEW PROJECT #1 PRESCHOOL Rehabilitation $60,000.00 Additional 3 classrooms for the Standard One $30,000.00 *Social Security to Pledge towards the project.

  9. PROJECT OVERVIEW PROJECT #2 Construction of the first two- Storey 14 classroom building with principal’s office and bathrooms. Estimated cost Bze$1.3 M

  10. PROJECT #3 Construction of the second two-Storey 14 classroom building with principal’s office and bathrooms. Estimated cost Bze$1.2 M

  11. PROJECT #4 Construction of two fences Rehabilitation of 2 existing buildings Rehabilitation of existing library Estimated cost Bze$700,000

  12. FURNITURE Estimated cost Bze$500,000 TOTAL........BZE $4,501,000

  13. PHASES OF THE PROJECT

  14. GROUND WORK • PROJECT PROPOSALS forwarded to various agencies • ENGINEER from BNE has visited • DISTRICT EDUCATION MANAGER has pledged support • VENEZUELAN AMBASADOR has visited • MINISTER OF EDUCATION has visited • AREA REPRESENTATIVE has visited • ENGINEER from MOE has visited • STAKEHOLDERS MEETING

  15. PROJECT #1(370 Students)

  16. Reconstruction of 14 classrooms two storey Building with Principal’s Office & Bathrooms Estimated Cost (Including Furniture): BZE $1.3 MILLION Funding Sources Identified : Belize Natural Energy SPCS Parent Teachers Association Management & Ministry of Education

  17. MAIN STREET PRESCHOOL (3 Classrooms)

  18. JOSE MARIA NUNEZ STREET STANDARD ONE (4 Classrooms)

  19. JOSE MARIA NUNEZ STRRET INFANT TWO (4 Classrooms)

  20. RECONSTRUCTION • INFANT TWO BUILDING: 4 CLASSROOMS • STANDARD ONE: 4 CLASSROOMS • PRESCHOOL: 3 CLASSROOMS

  21. SCOPE OF WORK • Demolition of the existing buildings with special care given to the asbestos roof. • Closure of School (1 week) during demolition. • Purchasing of 11 temporary classroom buildings to house 370 students( a third of the total school population) over a one year period. • Construction of a new14 classroom 2 storey building with principal’s office and bathrooms.

  22. Wiring of the new building • Installation of ceiling fans in the new classrooms • Painting of the new building • Furnishing of new classrooms

  23. FURNITURE PRESCHOOL: 3 classrooms 50 armchairs 12 learning centre tables 2 teachers desks & chairs 3 bookshelves 3 cupboards 1 kitchenette with sink

  24. INFANT TWO: 4 classrooms 120 armchairs 8 learning centre tables 4 teachers desks & 12 chairs 4 bookshelves 4 cupboards 4 chalk boards

  25. STANDARD ONE: 4 classrooms 120 armchairs 8 learning centre tables 4 teachers desks & 12 chairs 4 bookshelves 4 cupboards 4 chalk boards

  26. PRINCIPAL’S OFFICE Teachers’ Lounge & Print Room 1 Principal’s desk and 5 chairs 1 table to seat 20 teachers and 20 chairs for meetings and workshops 1 chalkboard 2 bookshelves 2 file cabinets 2 cupboards 1 kitchenette and sink

  27. PRINT ROOM • 3 WALL TO WALL BOOK SHELVES • 1 COMPUTER STATION • 3 TABLES FOR RISOGRAPHS & PRINTERS • 2 CUPBOARDS TO STORE SUPPLIES

  28. PROJECT #2(226 Students)

  29. Reconstruction of 14 classrooms two storey Building with Principal’s Office & Bathrooms Estimated Cost (Including Furniture): BZE $1.2 MILLION Funding Sources Identified : VENEZUELAN GOVERNMENT SPCS Parent Teachers Association Management & Ministry of Education

  30. MAIN STREET, STANDARD FIVE (6 Classrooms)

  31. MAIN STREET, STANDARD Six (4 Classrooms)

  32. RECONSTRUCTION OF TWO BUILDINGS MAIN STREET • STD V BUILDING: 6 CLASSROOMS • STD VI BUILDING: 4 CLASSROOMS

  33. SCOPE OF WORK • Demolition of the existing buildings • Construction of a new14 classroom 2 storey building to accommodate (226 students) with principal’s office and bathrooms. • Wiring of the new building • Installation of ceiling fans in the new classrooms • Painting and furnishing of the new building

  34. STANDARD FIVE: 6 classrooms 120 armchairs 12 learning centre tables 6 teachers desks & 18 chairs 6 bookshelves 6 cupboards 6 chalk boards

  35. STANDARD 6: 4 classrooms 120 armchairs 8 learning centre tables 4 teachers desks & 12 chairs 4 bookshelves 4 cupboards 4 chalk boards

  36. PRINCIPALS OFFICE Teachers Lounge 1 Principal’s desk and chair 1 table to seat 20 teachers and 20 chairs for meetings and workshops 1 chalkboard 2 bookshelves 2 file cabinets 2 cupboards

  37. PROJECT #3(363 Students)

  38. Rehabilitation of three buildings & Construction of fence School Library building Cost: BZE $700,000.00 Funding Partners: Social Investment Funding SPCS Parent Teachers Association Management & Ministry of Education

  39. JOSE MARIA NUNEZ STREET PUNTA GORDA TOWN INFANT ONE (6 Classrooms)

  40. School Library

  41. Standard 2 & 3 (7 Classrooms)

  42. REHABILITATION OF THREE BUILDINGS FRONT STREET • STD 2 & 3 BUILDING: 7 CLASSROOMS • INFANT I BUILDING: 6 CLASSROOMS • SCHOOL LIBRARY

  43. INFANT ONE Total cost $31,524.13 (COST OF FURNITURE NOT INCLUDED) SCOPE OF WORK Change Windows Electrification Ceiling Fans (6 per class) Painting Installation of burglar bars

  44. INFANT ONE: 6 classrooms 150 armchairs 12 learning centre tables 6 teachers desks & 18 chairs 6 bookshelves 6 cupboards 6 chalk boards

  45. STANDARD 2 & 3 Total Cost $86,323.78 (COST OF FURNITURE NOT INCLUDED) SCOPE OF WORK • Change Windows • Electrification • Ceiling Fans (6 per class) • Painting • Installation of burglar bars

  46. STANDARD 2 & 3: 8 classrooms 300 armchairs 16 learning centre tables 8 teachers’ desks & 24 chairs 8 bookshelves 8 cupboards 8 chalk boards

  47. SCHOOL LIBRARY Total cost $31,524.13 (COST OF FURNITURE NOT INCLUDED) SCOPE OF WORK Change Windows Electrification Ceiling Fans (10) Painting of building Installation of burglar bars Replastering of outside walls Furnishing of library

More Related