King Fahd University of Petroleum and Minerals Department of Construction Engineering and Management. Important Causes of delay in Public Utility Projects in Saudi Arabia. CEM - 510. Presented By: Tariq Al-Wabil 20 December 2003. Authors: Mohamed I. Al-Khalil Mohamed A. Al-Ghafly.
E N D
King Fahd University of Petroleum and MineralsDepartment of Construction Engineering and Management Important Causes of delay in Public Utility Projects in Saudi Arabia CEM - 510 Presented By: Tariq Al-Wabil 20 December 2003 Authors: Mohamed I. Al-Khalil Mohamed A. Al-Ghafly Instructor: Dr. Soliman Al-Mohawis
GUIDELINES • INTRODUCTION• PREVIOUS STUDIES• MAIN CAUSES OF DELAY• SUMMARY & CONCLUSION• Q & A Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱIntroduction Purpose: To determine the most important delay factors so that efforts can be made to control these factors. OWNER . CONSULTANT . GENERAL CONTRACTOR SUB CONTRACTOR MATERIAL SUPPLIER Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱPrevious Studies • 37% according to the contractors. • 84% according to the consultants. • 70% of Public Utility Projects subject to delay. • 39% of Original Project duration. Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱMain Causes of Delay • Six major Categories 1 - Contractor performance 2 - Owner administration 3 - Early planning and design 4 - Government regulations 5 - Site and environmental conditions 6 - Site supervision • Sixty Causes of Delay (Handout) Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱMain Causes of Delay • Material • Equipment • Manpower • Project management • Project Finance 1 - Contractor performance (1 - 29) Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱMain Causes of Delay • Slow decision making • Progress Payment • Coordination with other authorities 2 - Owner Administration (30 - 41) Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱMain Causes of Delay • Low qualification of A/E • Changes in the scope of the project 3 - Early Planning & Design (42 - 45) Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱMain Causes of Delay • Difficulty in obtaining work permits. • Tendering System 4 - Government Regulations (46 - 49) Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱMain Causes of Delay • Different from area to another • Site survey by the contractor • Work interference by Contractor 5 - Site & Environmental Conditions (50 - 54) Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱMain Causes of Delay • Qualification of Consultant Engineer’s Staff. • Submittal Approval • Inspection & Testing 6 - Site Supervision (55 - 60) Important Causes of delay in Public Utility Projects in Saudi Arabia
ٱSUMMARY & CONCLUSION • Cash flow Problem • Work Permits. • Tendering System Important Causes of delay in Public Utility Projects in Saudi Arabia
Degrees Financial Limits of Saudi Contractor Important Causes of delay in Public Utility Projects in Saudi Arabia
Contractor Classification Certificate Important Causes of delay in Public Utility Projects in Saudi Arabia
Q & A Important Causes of delay in Public Utility Projects in Saudi Arabia
Thank You Important Causes of delay in Public Utility Projects in Saudi Arabia