MSD II Week 2 Update P13265: Motorcycle Safety Lighting and Portable Electronics Charging System
Major Week 2 Action Items • Finalize all Test Plans- Mike • Complete with minor changes finalized today • Prepare, Cut, and Gelcoat all Molds- Tyler • In Progress • Machine Polycarbonate- Ben • In Progress • Order all Major Parts-Mike • Complete • Development of XBee Units-TJ • In Progress
Mike: Action Items Status • Finalize Test Plan • Complete, minor edits left • Want to review light, temp, and humidity tests • Carve and Gelcoat Chest Strap Mold • Incomplete • Not started; waiting for Tyler and Killian to make revisions to design (excepted completion today) • Test Lights and Order Lens Covers • In Progress • Tested lights, amber are not bright enough • Specs may be incorrect from company
Mike: Action Items Status • Contact Berquist • Complete • Sending free samples of Liqui-Bond thermal adhesive for Tx PCBA
Mike: Next Steps for Week 3 • Carve Chest Strap Mold & Gelcoat ~ 4 Hours • Lens covers will start week 4 after backpack shell is complete ~ 15 Hours • Order all remaining parts ~ 2 Hours
Tyler: Action Items Status • Cut Model into Parts • Complete • Glue Foam Parts to Mold Bases • Complete • Gelcoat & Seal Molds • In Progress • Scheduled for today • Sand and Possibly Polish Molds • In Progress • Will be completed this weekend
Tyler: Next Steps for Week 3 • Prep Mold ~ 0.5 Hours • Manufacture Shell ~ 1-2 Hours
Ben: Action Items Status • Machine Polycarbonate • In Progress • Polycarbonate arrived late tuesday but I was unable to begin machining until this morning due to other classwork • Most of the work will be done this weekend • Because of changed dimensions, we will now need 2 12"x12" sheets • All pieces are cut to size, excluding the top (insufficient material) • Create subsystem test plans for Quick connect safety and functionality • complete
Ben: Next Steps for Week 3 • Finish electronics housing box (15-18 hours) • Start work on Tx box
Eric: Action Item Status • Order Remaining Electronic Components • Incomplete/ In Progress / Complete • Explain • Continue MSP430 Development • Incomplete/ In Progress / Complete • Explain • AI #3 • Incomplete/ In Progress / Complete • Explain
Eric: Next Steps for Week 3 • Next Steps 1 ~ Approx. Hours • Next Steps 2 ~ Approx. Hours • Next Steps 3 ~ Approx. Hours
TJ: Action Items Status • Code and Debug XBee units • In Progress • Arrived Tuesday, will continue coding this weekend • Continue MSP430 Dev • In Progress • Poked around on TI website and examined tools available to generate code • Complete Electronics Board-Level TP • Complete • Developed checklist to review after population, as well as sub-systems tests
TJ: Next Steps for Week 3 • Debug XBee Units ~ 10 Hours • Program MSP430 ~ 20 Hours • Populate PCBs once they arrive ~ 10 Hours
Major Week 3 Action Items • Development of XBee Units • TJ • Prepare, Cut, and Gelcoat all Molds • Mike & Tyler • Machine Polycarbonate • Ben • Program MSP430 • TJ & Eric • Populate PCBs • TJ & Eric