70 likes | 153 Views
Activities Status and Plan for the week. D. Giugni / INFN Milano. Harnesses Stacking Status. Set 6 General : Set assigned to A34 Status All HV-NTC stack are done Set 7 General : Set assigned to A12 Status All HV Harnesses are “prepared” Set 8 General :
E N D
Activities Status and Plan for the week D. Giugni / INFN Milano Monday Meeting 2011-02-27
Harnesses Stacking Status • Set 6 • General : • Set assigned to A34 • Status • All HV-NTC stack are done • Set 7 • General : • Set assigned to A12 • Status • All HV Harnesses are “prepared” • Set 8 • General : • Set assigned to A56 • Status • All HV Harnesses are “prepared” • Set 9 • General : • Set assigned to A78 • Status • All HV Harnesses are “prepared” • Open Issues • Need to terminate with LEMO connectors IPS-3 and OPS-5. • Set 1 C34 (X0)Done (final test pending on OSP LV) • Set 2 No change since last week • General • Keep using set as Harnesses “replacement” • Status • All usable Harnesses “Prepared” and tested • Open Issues • Need several repairs. Not started yet • Set 3 No changes since last week • General • Set assigned to C12 • Status • Almost done: OSP LV need to be stacked • Set 4 No changes since last week • General • Set assigned to C78 • Status • Almost done: OSP LV to be STACKED • Set 5 No changes since last week • General • Set assigned to C56 • Status • Almost done: OSP LV to be STACKED
Mechanics and parts for soldering • Stiffened and bonded PP0 boards • ISP C-side: All done • ISP A-Side: A34 (ready for final test on Tuesday morning) • OSP: None • Production rate driving factor: Boards availability • Corrugated panels: • ISP: 6 out of 16 delivered • OSP: None out of 16 • Production rate driving factor: SLA parts delivery We have parts available for 2 more ISP’s before next batch (expected this week!!!) Monday Meeting 2011-02-27
Soldering Sequence, Status and Planning: ISP: 10 cal days OSP: 14 cal days • ISP C34 (X0) completed • ISP C12 (X1) completion: Tuesday 28/2 (tomorrow) HV soldering 20% completed • ISP C78 (X2) completion: This week: Th 1/3 PS soldering 80% • ISP C56 (X3) completion:Next week: Tu 6/3 PS soldering 10% • ISP A34 (X4) start when ISP C12 is completed (completion on Fr. 9/3) • ISP A12 (X5) start when ISP C78 is completed (completion on Mo 12/3) • ISP A56 (X6) start when ISP C56 is completed (completion on Fri. 16/3) • ISP A78 (X8) start when ISP A34 is completed (completion on Mo 19/3) Monday Meeting 2011-02-27
Soldering [cont’ed] • OSP C34 start when ISP A12 is completed (completion on Mo. 26/3) • OSP A34 start when ISP A56 is completed (completion on Fr. 30/3) • OSP A12 start when ISP A78 is completed (completion on Mo. 2/4) • OSP A56 start when OSP C34 is completed (completion on Mo. 9/4) • OSP A78 start when OSP A34 is completed (completion on Fr. 13/4) • OPS C12 start when OSP A12 is completed (completion on Mo. 16/4) • OSP C56 start when OSP A56 is completed (completion on Mo. 23/4) • OSP C78 start when OSP A78 is completed (completion on Mo. 27/4) Monday Meeting 2011-02-27
PP0 boards delivery dates Boards are assumed to be delivered “tested” and ready to go for bonding. These are the required delivery dates: • ISP C34, C12, C56, C78: All done • ISP A34 : done • ISP A12: today Monday 27/2 • ISP A56: Th 1/3 • ISP A78: Mo 5/3 • OSP C34 Mo 5/3 • OSP A34 Mo 12/3 • OSP A12 Mo 12/3 • OSP A56 Mo 19/3 • OSP A78 Mo 26/3 • OPS C12 Mo 26/3 • OSP C56 Mo 2/4 • OSP C78 Mo 9/4 Monday Meeting 2011-02-27
Schedule for this week • Stacking • Full speed on the stacking: OPS LV 3, 4, 5, 6 (OPS LV 1 is done now) • Keep going stacking SET 7, 8 and 9. Note Set 9 needs to mount LEMO connectors • Corrugated panel bonding: Produce the other 2 ISP corrugated panel with the remnant SLA parts. New (full SLA set will be available this week!!) keep going with all the ISP’s • BackBone Not at high priority this week. It will restart when Valery is back next week • PP0 boards stiffening and Alu Block bonding • Continue to bond the rest of the ISP A side boards. • Soldering • Finish up ISP C12 Load A34 • Finish up ISP C78 Load A12 • Continue soldering on ISP C56 • Post Soldering Assembly Final Assembly Trial (X-1) • No activities this week Monday Meeting 2011-02-27