280 likes | 366 Views
Cryogenic system in P4: Possible options. (Mostly for RF & beam scrubbing). S. Claudet & U. Wagner. LHC Workshop, “Chamonix XlV” January 2005. Content. Brief recall of present situation Concerns Cooling capacity Pressure stability Coupling with items operated at higher pressure
E N D
Cryogenic system in P4:Possible options (Mostly for RF & beam scrubbing) S. Claudet & U. Wagner LHC Workshop, “Chamonix XlV” January 2005
Content • Brief recall of present situation • Concerns • Cooling capacity • Pressure stability • Coupling with items operated at higher pressure • Periodic cavity conditioning and developments • Possible alternative cooling schemes • Summary
Getting familiar with the subject Interface to be further studied & finalised !!! Global overview ?!? • LHC Design report, p 134 for description of ACS cryogenics and requirements • Schematic views: • Single cavity module: LHCACSGA0006 • QRL sector 3-4: LHCLSQR_0041 • QRL sector 4-5: LHCLSQR_0042 • Minutes of meetings between RF & Cryo • Minutes of LHC Hardware Commissioning
Layout UX45, top view ACS QRL QUI QURC
Layout UX45, side view ACS QRL WRL QUI
Cooling capacity (1/3) “LHC Design report”, recently completed by AB/RF
Cooling capacity (2/3) Some margin left at Nominal mode Nominal mode: no need for capacity upgrade Chamonix 2004, p 252 Equivalent capacity [kW]
Cooling capacity (3/3) • Lack of capacity • of the 4.5 K • Refrigerators • Ultimate mode: obvious need • for capacity • upgrade Chamonix 2004, p 252 Equivalent capacity [kW]
Capacity for beam scrubbing • Turbine upgrade decided in 2004, (contract F529) • Cooling capacity in line with hydraulic capacity of beam screens Chamonix 2004, p 253 Equivalent capacity [kW]
Pressure stability (1/2) SM18 Pressure [mbar] LHe level [mm]
Pressure stability (2/2) SM18 Pressure [mbar] Request: 1.350 bar ± 15 mbar Try with Line D (60m3) as buffer and return valve in QUI for Pressure control If not OK, then use return control valve of module for Pressure control Nota: LHe level control at low possible value will increase GHe volume for intrinsic pressure stability
Coupling via return line D (1/3) • During some operating modes, QRL - Line D will be operated at pressures above Cavities Maximum Allowed Working Pressure Cool-down: 3.5 B to 1.3 B Sector quench: 6 to 15 B Warm-up: 1.3 to 3.5 B 2.0 B Safety device 1.550 B Beam Dump 1.500 B High Voltage off 1.450 B RF off 1.350 B Nominal value
Coupling via return line D (2/3) Initial ramp: dTmax* < 75 K Chamonix 2004, p 206 Normal cooldown of a LHC sector • Cool-down of ACS to be started when QRL- line D pressure is low enough • Compatible with overall schedule 300-4.5 K Start of ACS and DFBs cooldown + 2 d to 1.9K * max temp. difference across magnet G. Riddone, AT Department LHC Project Workshop, Session 6 - Chamonix January, 21 2004
Coupling via return line D (3/3) Industrial cryogenic check-valve installed in refrigerators, DFB’s
Conditioning & tests requirements Not critical, even if frequent quenches at the beginning • Commissioning or conditioning: • After installation before beam: 6 months • After yearly warm-up to 300 K: 1 week • After a short stop (T ≤ 50 K): 1-2 hours • Repeated request: • “Need to have the possibility of doing RF work if machine is down for some time (magnet replacement, …)” Could be a good idea, but not yet the baseline !!!
Simplified cooling scheme 4.5 K Refrigerator Warm Compressor Station Warm recovery line (≤300 K; ≤1.1 bar) MP HP LP Cold Box SC Cavities Fall-back for “low intensity” Safety System Back flow limitation D (20 K; 1.3 bar) C (4.5 K; 3.0 bar) QRL QUI Safety System • Open points: • Interface valves located in QRL Service Module • Safety system (control valve, safety valve, bursting disc) • Back flow limitation
Alternative cooling schemes, why? • To provide the possibility to discharge helium gas at a lower pressure than nominal 1.350 bar, increasing availability of sc cavities operation • To keep availability at least as it is now • While reviewing possible options, why not giving the possibility to operate the sc cavities independently from the sectors
Option 1: Warm return • Advantage: • (Cool-down) / Warm-up even if line D > 1.4 bar • Recovery of ACS static losses after sector quench • Allows short period of operation if line D > 1.4 bar 4.5 K Refrigerator Warm Compressor Station Warm recovery line (≤300 K; ≤1.1 bar) MP HP LP ? Cold Box Coupler cooling SC Cavities Safety System D (20 K; 1.3 bar) C (4.5 K; 3.0 bar) QRL QUI Safety System Rather easily implemented
Layout UX45, side view ACS QRL Detailed integration study needed to confirm the concept WRL Warm Recovery Line (WRL) always along QRL
Option 2: Cold return supply & 4.5 K Refrigerator Warm Compressor Station Warm recovery line (≤300 K; ≤1.1 bar) MP HP LP ? Cold Box Coupler cooling SC Cavities Safety System Kept as back-up ? D (20 K; 1.3 bar) C (4.5 K; 3.0 bar) QRL QUI Safety System • Advantage: • Cool-down / Warm-up even if line D > 1.4 bar • Recovery of ACS static losses after sector quench • Allows quick re-connection after quench • Allows short period of operation if line D > 1.4 bar • Allows operation independently from QRL / Magnets Disadvantage: • New valve box & lines • Intervention on 2 lines • Not easily implemented
Layout UX45, top view • Additional lines as by-pass of QUI, via a valve box ACS QRL QUI QPLB - QULA: Lines between refrigerators & QUI • Feasibility to be confirmed • Detailed integration study needed to confirm the concept
Option 3: “Process wish” 4.5 K Refrigerator Warm Compressor Station Warm recovery line (≤300 K; ≤1.1 bar) MP HP LP To be defined Cold Box Coupler cooling SC Cavities Safety System Kept as back-up ? D (20 K; 1.3 bar) C (4.5 K; 3.0 bar) QRL QUI Safety System • Advantage: • Cool-down / Warm-up : no limitation • No limitation due to quench • Allows operation independent from QRL / Magnets • Disadvantage: • Not likely to be possible
Option 4: Dedicated compressor 4.5 K Refrigerator Dedicated compressor Capacity boost to be defined Warm Compressor Station MP HP LP Cold Box Coupler cooling SC Cavities Safety System Kept as back-up ? D (20 K; 1.3 bar) C (4.5 K; 3.0 bar) QRL QUI Safety System • Advantage: • Cool-down / Warm-up : no limitation • No limitation due to quench • Operation independent from sector Disadvantage: • Coupling with 4.5K Ref. not certain if possible
Option 5: Dedicated Ref. (at last!) Dedicated Compressor 4.5 K Refrigerator Warm Compressor Station Dedicated Cold Box MP HP LP Cold Box Coupler cooling SC Cavities Safety System Kept as back-up ? D (20 K; 1.3 bar) C (4.5 K; 3.0 bar) QRL QUI Safety System • Advantage: • Cool-down / Warm-up : no limitation • No limitation due to quench • Operation independent from sector • Disadvantage: • Where and how to install this now ?
Layout UX45, top view (5) • ACS • QRL • Cooling capacity critical for ultimate beams, something will have to be done ! • Integration study needed surface-shaft-cavern
Summary options Data provided as indications, to be further studied if necessary
Summary • The reference solution needs to be implemented, with simple adaptations (control & check valves) to prevent perturbation due to back pressure from line D • A back-up return via the warm recovery line would prevent from major pressure excursions above 1.5 bar Option 1 • Any alternative cooling scheme will need a modification of the corresponding cryogenic distribution line (after concerned service module) • Additional capacity will be triggered by needs for ultimate beams or (bad!) operational experience Option 2,3,4, 5 Option 5
Acknowledgements The authors would like to thank all colleagues who contributed to this work: E. Ciapala, R. Losito, P. Maesen, O. Brunner Y. Muttoni L. Serio, G. Riddone, L. Tavian