ALICE overview and Requirements L.Jirdén 10.3.03

ALICE overview and Requirements L.Jirdén 10.3.03. ALICE experiment environment Architecture ALICE DCS Systems Back-end Detectors Services External systems Planning Status Conclusion. ACR. racks in c-rooms. gas distribution. PLUG. ~50m. racks in cavern. ~15m. ALICE DETECTOR.

reece
Download Presentation

ALICE overview and Requirements L.Jirdén 10.3.03

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ALICE overview and RequirementsL.Jirdén 10.3.03 • ALICE experiment environment • Architecture • ALICE DCS Systems • Back-end • Detectors • Services • External systems • Planning • Status • Conclusion

  2. ACR racks in c-rooms gas distribution PLUG ~50m racks in cavern ~15m ALICE DETECTOR BEAM ALICE experimental area ~55m

  3. Services External Systems electricity DCS Back-end cooling LHC ECS gas Offline magnet Trigger DCS infrastr. safety DAQ access ITS TPC MUON pixel strip drift T T p hv hv hv hv hv lv lv lv lv lv Detectors Controls Context

  4. LV CONTROL Functionality (FSM) COMPUTER Logging Access handling ALICE Control Room PVSS Config. Alarm handling OPC client PVSS LV CU DCS network Counting Room COMPUTER LV DU Functionality (FSM) OPC server Alarm handling Logging PCI-CAN Config. Device driver CAN-bus LV Physical Device Cavern PVSS CAN contr. LV Power Detector Architecture ALICE follows JCOP guidelines All required tools and components expected in the “Framework”

  5. Framework Concept USER APPLICATION Supervisory layer Dbase FRAMEWORK: Back-end Tools and components DCS network Process layer USER APPLICATION FRAMEWORK: Front-end Tools and components Field layer Field-bus DEV 1 DEV 2

  6. ALICE USER APPLICATION JCOP JCOP ALICE Supervisory layer FRAMEWORK CONDIT FSM ALARM DB access ARCHIV PVSS CONFIG LOG ARCHIV EXP CONFIG LOG FEE CONFIG COMMUNICATION WEB PVSS CONFIG DCS network DBMS ALICE DCS Back-end

  7. ALICE USER APPLICATION JCOP JCOP ALICE Supervisory layer FRAMEWORK CONDIT FSM ALARM DB access ARCHIV PVSS CONFIG LOG ARCHIV EXP CONFIG LOG FEE CONFIG COMMUNICATION WEB PVSS CONFIG DCS network DBMS Process layer Standard: JCOP Specific: ALICE COMMUNICATION ALICE USER APPLICATION Standard: JCOP Specific: ALICE DEVICE DRIVERS Field layer Field-bus ALICE DEV 1 DEV 2 … and Front-end ALICE

  8. Detectors DCS … ITS TPC TRD TOF HMP ZDC FMD T0 V0 PMD EMC COS Detectors SPD SDD SSD RO FC PHO MU HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV CAL CPV TRI TRA LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV subsystems FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP COO COO COO COO COO COO COO COO COO COO COO COO COO GAS GAS GAS GAS GAS GAS GAS GAS GAS TS LSR ROD TS LIQ ALI PLS

  9. Detectors: HV, LV DCS … ITS TPC TRD TOF HMP ZDC FMD T0 V0 PMD COS Detectors SPD SDD SSD RO FC PHO MU CAL CPV TRI TRA EMC CAEN JCOP standardISEG JCOP standardFUG ALICE specificWIENER JCOP standardCAEN JCOP standardAREM PRO ALICE specific HV subsystems LV

  10. FEE PC JCOP ALICE CONTROL ROOM PVSS DIM client DCS network PC PC PC PC Front End Device (FED) JCOP + ALICE FEE PC … COUNTING ROOMS DIM server interface JTAG PROFIBUS ETHERNET Etc. VME PROFIBUS ETHERNET JTAG + private link FEE H/W FEROM CAVERN JTAG + DDL … ON DETECTOR SPD FEE SSD FEE TPC FEE TRD FEE Front-End Electronics 18 different FEE architectures in ALICE!!

  11. TMP PC Monitoring application ALICE CONTROL ROOM PVSS OPC clients DCS network PC OPC server COUNTING ROOMS PCI-CAN ELMB ELMB CAVERN ELMB ELMB ON DETECTOR ELMB ELMB Temperature Monitor JCOP

  12. CERN Services Detector Services Prim. Services ALICE DCS Control Super- vision Super- vision TCR ACR network DIP DIP Process control PX UX Process control P2 • Detector Services • Racks, crates • Detector Cooling • Detector Gas • Det. Infrastructure • Detector Safety • Primary Services • Prim. Electricity • Prim. Cooling • Prim. Gas • Magnet • Personal Safety Services

  13. CERN Services PC DCS Back-end MAGNET GAS ELECTR CSS PVSS ST SCADA ST SCADA ST SCADA ST SCADA TECHNICAL CONTROL ROOM ALICE CONTROL ROOM DIP client DIP Server DIP Server DIP Server DIP Server JCOP TECHN network DCS network STATUS Monitoring applications COOLING ST SCADA DIP Server JCOP Services

  14. RCO Monitoring & control application PC ALICE CONTROL ROOM PVSS JCOP OPC clients DCS network PC PC ST/EL + JCOP JCOP OPC server OPC server COUNTING ROOMS PCI-CAN Process control application PLC CAVERN RACK RACK ELMB ELMB R-POWER ON DETECTOR ESS + JCOP Rack control

  15. COO PC Monitoring & control application ALICE CONTROL ROOM PVSS JCOP OPC clients DCS network PC ST-CV + JCOP OPC server COUNTING ROOMS To ST-CV SCADA Process control application PLC COOLING PLANT 11 plants CAVERN ON DETECTOR Cooling control

  16. GAS PC Monitoring & control application ALICE CONTROL ROOM PVSS EP/TA1 + JCOP follow-up OPC clients DCS network PC OPC server COUNTING ROOMS Process control application PLC 8 plants GAS PLANT CAVERN ON DETECTOR Gas control

  17. DSS PC Monitoring & control application ALICE CONTROL ROOM PVSS OPC clients JCOP + ALICE DCS network PC OPC server COUNTING ROOMS Process control application Remote IO PLC SENSORS ACTUATORS SENSORS ACTUATORS CAVERN SENSORS ACTUATORS ON DETECTOR Safety (DSS)

  18. INF Monitoring applications PC ALICE CONTROL ROOM PVSS OPC clients DCS network PC OPC server COUNTING ROOMS BF PCI-CAN • B-field • Space Frame alignment • Vacuum Pipe alignment SF VP CAVERN ON DETECTOR ELMB SENSORS Infrastructure JCOP ? JCOP

  19. External Systems LHC OFFL Finite State Machinesbuilt with SMI comm. Via DIM ECS JCOP DCS TRG DAQ In PVSS env: FSM tools SMI Partitioning tools • Main tasks • Experiment partitioning • Synchronization

  20. LHC OFFL ECS operator operator DCS TRG DAQ DET A DET A DET A DET B DET B DET B DET n DET n DET n .. .. .. Experiment Partitioning EXPERIM CONFIG

  21. DET A DET A DET A DET B DET B DET B DET n DET n DET n .. .. .. Experiment Partitioning EXPERIM CONFIG LHC OFFL ECS DCS TRG DAQ operators operators DCS TRG DAQ

  22. FEE Configuration FEE CONFIG LHC OFFL ECS synchronization Via DCS Via DAQ DCS TRG DAQ DDL synchronization DIM server FEE H/W FED

  23. FEE Configuration: ex. DAQ in charge FEE CONFIG LHC OFFL ECS Via DCS Via DAQ DCS TRG DAQ Monitoring CU Trigger status CU Configuration CU DDL Monitoring DU DIM server Trigger status DU Configuration DU FEE H/W FED

  24. 2002 03 04 05 06 07 DET PRE-INST FINALINST COM-MISS BEAMOP DCS ARCHITECTURE URD PVSS, FrontEnd tools + comm. ENG. SOLUTIONS FSM, SMI PROTOTYPE SUBSYSTEM Db access, Configuration, data vis. Services, network PROTOTYPE SUB-DET CONTR. Distributed systems, operation, final version TEST WITH DETECTOR EQUIPMENT INSTALL DCS INFRASTRUCTURE INSTALL DETECTOR DCS DCS Planning

  25. Status Detector URD’s 1st draft URD exists Discussion started Not started PHO MU CAL CPV TRI TRA DCS … ITS TPC TRD TOF HMP ZDC FMD T0 V0 PMD EMC COS Detectors SPD SDD SSD RO FC HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV subsystems FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP COO COO COO COO COO COO COO COO COO COO COO COO COO GAS GAS GAS GAS GAS GAS GAS GAS GAS TS LSR ROD TS LIQ ALI PLS

  26. Status Prototypes 1st version exists started not started PHO MU CAL CPV TRI TRA DCS … ITS TPC TRD TOF HMP ZDC FMD T0 V0 PMD EMC COS Detectors SPD SDD SSD RO FC HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV HV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV LV subsystems FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE FEE TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP TMP COO COO COO COO COO COO COO COO COO COO COO COO COO GAS GAS GAS GAS GAS GAS GAS GAS GAS TS LSR ROD TS LIQ ALI PLS

  27. JCOP ALICE • JCOP + • Discussion forum, exchange of ideas, architecture issues • Common interface to CERN services: Gas, electricity, etc. • JCOP ALICE • Used so far: PVSS, FW: CAEN HV, ISEG HV (temp), FSM tools, SMI • Plan to use: all (or most) deliverables as listed in JCOP Program Plan • ALICE JCOP • ISEG FW integration • PVSS application for rack control • ALICE expects • The timely delivery of JCOP deliverables • Long term support of JCOP deliverables (by support groups)

  28. Usefulness of JCOP • How well does JCOP cover ALICE needs? • all (almost) will be used by ALICE • Limited success: • GIF: useful as a service but limited feedback for controls • Rack Control: limited outcome until recently • Fields not covered: • Connection to FEE • FEE configuration • Connection to TRG/DAQ • Common purchasing • Radiation issues

  29. Technology choices • Is PVSS a good choice? • Limited experience in ALICE so far • Improvements and adaptations needed • Seams adequate for ALICE needs • Long term existence/support/evolution is uncertain • However… • Having made a choice which might be on the limit is better than no choice at all !

  30. Conclusion • ALICE DCS requirements defined to ~ 70% today • Prototyping of sub-system solutions started • ~75% are common solutions - JCOP • ~25% are dedicated solutions - ALICE • Not many JCOP deliverables materialized so far, however… • ALICE relies fully on the timely delivery of projected JCOP tools and components • ALICE collaboration with JCOP globally very positive