ERCOT Nodal Schedule Market Participant Workshop

This workshop aims to review the ERCOT schedule terminology, assumptions, and activities for 2009 and 2010, with a focus on market participant-facing activities. Participants must adhere to antitrust laws.

reedl
Download Presentation

ERCOT Nodal Schedule Market Participant Workshop

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. ERCOT Nodal Schedule Market Participant Workshop January 7, 2009

  2. Antitrust Admonition ANTITRUST ADMONITION ERCOT strictly prohibits Market Participants and their employees who are participating in ERCOT activities from using their participation in ERCOT activities as a forum for engaging in practices or communications that violate the antitrust laws. The ERCOT Board has approved guidelines for members of ERCOT Committees, Subcommittees and Working Groups to be reviewed and followed by each Market Participant attending ERCOT meetings. If you have not received a copy of these Guidelines, copies are available at the Client Relations desk. Please remember your ongoing obligation to comply with all applicable laws, including the antitrust laws.

  3. Agenda Review Workshop Goal Review ERCOT Schedule Terminology Review ERCOT Schedule Assumptions Review Workshop Approach Discuss 2009 Market Participant Activities Discuss 2010 Market Participant Activities Market Participant Schedule View Wrap-up & Next Steps

  4. Workshop Goal Market Participants and ERCOT staff work together to identify additional Market Participant-facing activities and milestones that should be included in the ERCOT Nodal Schedule

  5. ERCOT Project Schedule Terminology • Project activity: • Description of work to be performed • Milestone: • End of a set of activities that marks the completion of a work package. Milestones have a zero-day duration. • Critical Path: • Sequence of integrated project activities that add up to the longest overall duration. This determines the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (i.e. there is no float on the critical path). • Market Participant Milestone View: • View of the Nodal schedule that includes those activities and milestones that are needed for MP schedule development • Note: Not all milestones are on the critical path – only those whose tasks have no float. The SEM Go-Live milestone is important, but it is not on the critical path. However, it needs to be included in the MP Milestone View.

  6. ERCOT Schedule Terminology – Environment & Activities

  7. ERCOT Schedule Assumptions • Market participant activities in EDS environment do not begin until there is a final validated network model across EMS/NMMS/MMS applications • ERCOT preserved previous critical path for MPs; EDS4 with approved sequence of 10.5 months prior to go-live • 7.5 months of testing prior to the 168-hour test • 1 month for 168-hour test • 2 months Go-Live sequence • Market participants continue to support required activities, including telemetry, network model, and other activities in 2009

  8. Workshop Approach • Morning Session: 2009 Market Participant Activities • Proposed Activity Description • Desired ERCOT and Market Participant Outcomes and Benefits • Tasks and milestones that should be added to schedule • Afternoon Session: 2010 Market Participant Activities • Proposed Activity Description • Desired ERCOT and Market Participant Outcomes and Benefits • Tasks and milestones that should be added to schedule

  9. 2009 Market Participant Activities • Focused Input Testing (Telemetry & State Estimator) • Resource Transmission Equipment Registration • Verifiable Cost Submissions (EDS4 Release 8.4) • MOTE Launch • SEM (NMMS Tool) Go Live • MP Connectivity Testing & Re-Qualification (EDS 4 Release 9.1)

  10. Focused Input Testing (Telemetry & State Estimator)

  11. Resource Transmission Equipment Registration

  12. Verifiable Cost Submissions (EDS 4 Release 8.4)

  13. MOTE Launch

  14. SEM (NMMS Tool) Go Live

  15. MP Connectivity Testing & Re-Qualification (EDS 4 Release 9.1)

  16. 2010 Market Participant Activities • Planning Model Go-Live • Real Time LMPs published (EDS 3 Release 5) • LFC Testing (EDS 3 Release 6) • CRR Auction Market Trials (EDS 3 Release 7) • Commercial Operations Market Trials (EDS 4 Release 8) • Outage Scheduler Market Trials (EDS 4 Release 9.2) • DAM/RUC/SASM Market Trials (EDS 4 Release 9.3) • Pre-168 Hour Test (EDS 4 Release 9.4) • 168 Hour Test

  17. Planning Model Go-Live

  18. LFC Testing (EDS 3 Release 6)

  19. Real Time LMPs Published (EDS 3 Release 5)

  20. CRR Auction Market Trials (EDS 3 Release 7)

  21. Outage Scheduler Market Trials (EDS4 Release 9.2)

  22. DAM/RUC/SASM Market Trials (EDS4 Release 9.3)

  23. Commercial Operations Market Trials (EDS4 Release 8)

  24. Pre-168 Hour Test (EDS4 Release 9.4)

  25. 168 Hour Test

  26. Market Participant Schedule View • Description of potential view of participant schedule –

  27. Wrap-up • Action Item Review • Next Steps