1 / 34

CLAIMS STUDY

Erik M. Rosenwood Hamilton Moon Stephens Steele & Martin, PLLC and Jeff Todd Insurance Management Consultants, Inc. CLAIMS STUDY. LARGE ARCHITECTURAL CLAIM. An architect was retained to provide architectural and engineering services for a sports facility in a northern state.

reia
Download Presentation

CLAIMS STUDY

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Erik M. Rosenwood Hamilton Moon Stephens Steele & Martin, PLLC and Jeff Todd Insurance Management Consultants, Inc. CLAIMS STUDY

  2. LARGE ARCHITECTURAL CLAIM • An architect was retained to provide architectural and • engineering services for a sports facility in a northern state. • The prime architect then retained a local architect and structural • engineer. The design team provided a performance • specification for a standing seam metal roof. WWW.DESIGNPROFESSIONAL.ORG

  3. LARGE ARCHITECTURAL CLAIM • Questions to Consider: • Owners Needs (financing, tax issues, timing, interest payments) • Direct vs. Consequential Damages • Limitation of Liability • Fees • Amount of Insurance • Indemnification from other parties • Clearly defined scope WWW.DESIGNPROFESSIONAL.ORG

  4. LARGE ARCHITECTURAL CLAIM • About three years after substantial completion, a section of the dome blew off during a windstorm. The roof was • repaired for $250,000. The sports dome’s property insurer paid for the repairs and two years later filed suit against • the prime architect. The city filed their own lawsuit, claiming $5,000 in damages, which was the amount of their • deductible, and other unspecified damages. Both suits alleged negligence, breach of contract, and breach of • warranty. A reservation of rights was issued on the breach of warranty claim since professional liability insurance • does not provide coverage for express warranties and guarantees. WWW.DESIGNPROFESSIONAL.ORG

  5. LARGE ARCHITECTURAL CLAIM • Questions to Consider: • Possible problems on project? • Early settlement or litigate? • Client management • Publicity • Effect on other projects/relationship with other parties to suit WWW.DESIGNPROFESSIONAL.ORG

  6. LARGE ARCHITECTURAL CLAIM • Shortly after the claims were filed and while warranty work was being performed on the dome, it was determined • that there were structural problems with the standing seam roof. In addition, the city identified problems with the • parapet walls, the placement of the vapor barrier below the roof, and the attachment of the standing seam metal • roof. The city also raised concerns about snow accumulation and resulting avalanches. WWW.DESIGNPROFESSIONAL.ORG

  7. LARGE ARCHITECTURAL CLAIM • The design team pointed to the roof manufacturer as having primary responsibility for the problems arising out of • the standing seam metal roof, including the wind damage, failure of the bolts attaching the roof to the structural • deck, and failure of the bottom supporting purlins of the roof. • The design team also argued that the structural overload that occurred on the southeast corner of the dome • resulted from unusual and unanticipated weather conditions instead of design error. The roof was overloaded by a • 500-year snow event that would not have been considered in design. WWW.DESIGNPROFESSIONAL.ORG

  8. LARGE ARCHITECTURAL CLAIM • Going Back to our Questions to Consider: • Limitation of Liability • Early settlement or litigate? • Indemnification from other parties • Clearly defined scope – What was minimum design criteria? 50 year storm event? 100 year? 500 year? Hurricanes Hugo or Katrina? WWW.DESIGNPROFESSIONAL.ORG

  9. LARGE ARCHITECTURAL CLAIM • The city subsequently increased the amount of their lawsuit to $8 million. Damages included $1 million to deal with the snow load issues. The contractors and the roof manufacturer were added as codefendants. WWW.DESIGNPROFESSIONAL.ORG

  10. LARGE ARCHITECTURAL CLAIM • Although there were many defenses that would be raised during negotiation, the design team still faced exposure • for the claims relating to the vapor barrier and parapet walls, faulty on-site observation of the flashing and roof detail, avalanching snow and snow management issues, and failure to detect contractor errors in the attachment of • the roof. The design team was involved in all phases of the project, including design, shop drawing review, and • construction observation. The contractors and the roof manufacturer faced substantial liability for the condition of • the roof and improper installation. WWW.DESIGNPROFESSIONAL.ORG

  11. LARGE ARCHITECTURAL CLAIM • The city decided wanted a complete replacement of the roof structure and installation of snow fences, ground level roofs, and landscaping to address avalanching. Cost: $5 million. In addition, the city had out-of-pocket expenses of $1.7 million, bringing their total claim to $6.7 million. The defendants attempted to convince the city that a realistic recovery was $2.5 million. The city demanded $5 million. Defendants countered with $1.7 million, which included $1 million from the design team. The city indicated that the public would never accept a settlement for less than the cost of the planned repairs. The city said that they would rather accept a judge’s decision for substantially less than agree to compromise its claims for less than $5 million. WWW.DESIGNPROFESSIONAL.ORG

  12. LARGE ARCHITECTURAL CLAIM • Going back to our Questions to Consider: • Owners Needs – consider your owner’s motivations • Public Entities • CASE IN POINT – THE IDIOT SON-IN-LAW WWW.DESIGNPROFESSIONAL.ORG

  13. LARGE ARCHITECTURAL CLAIM • The design team became the target of the city’s claims. The city contended that the entire roof needed to be • removed because the original design failed to include a protective waterproof underlayment beneath the standing • seam roof. The city also alleged that the design team: • ● improperly placed the vapor barrier beneath the roof; • ● failed to specify the use of a waterproof gypsum board beneath the roof; and • ● failed to properly accommodate in the design the collection of snow and snow avalanching resulting from the • configuration of the roof. WWW.DESIGNPROFESSIONAL.ORG

  14. LARGE ARCHITECTURAL CLAIM • The city also argued that the contractors failed to: • ● supply a custom-designed roof as required by the plans and specifications; • ● properly place steel purlins and attachments as required to secure the roof to the metal structure; • ● provide sufficient structural capacity to accommodate snow loads; and • ● properly install flashing at the top and bottom portions of the standing seam metal roof. • The city also argued that the design team was jointly liable for its failure to identify or prevent these defects. WWW.DESIGNPROFESSIONAL.ORG

  15. LARGE ARCHITECTURAL CLAIM • The attorney for the design team estimated that the costs to the design team to prepare this case for trial would • be approximately $500,000. The design team decided to attempt a separate settlement with the city. • The city’s demand of the design team was $4 million in • damages. The design team countered with an offer of $1.8 million. The city eventually came back with a demand of • $3,350,000, The design team finally • settled the city’s claim for $2.4 million. Legal fees, expert expenses, and the policyholder’s deductible added • $1,270,000 to the cost, bringing the total cost for this claim to $3,670,000. WWW.DESIGNPROFESSIONAL.ORG

  16. READY TO TRY AGAIN? WWW.DESIGNPROFESSIONAL.ORG

  17. LARGE ENGINEERING CLAIM • An architect retained a mid-size structural engineering firm to provide the structural design for an assisted • living facility. After the engineer started the lateral design, the client made several design changes, which • included an increase in the height of the facility (it went from a six floor to a seven-floor facility). In addition, • the mechanical penthouse was changed from a metal floor to a cement floor. WWW.DESIGNPROFESSIONAL.ORG

  18. LARGE ENGINEERING CLAIM • Questions to Consider: • Owners Needs (financing, tax issues, timing, interest payments) • Changes During Project – What impact to structure? • Direct vs. Consequential Damages To Schedule? To coordination of trades? To Scope? • Change in team/personnel? • Changes comply with permit? With code? • Communication? (E.g., “Square footage” and “Youth Area” • DOCUMENTATION? WWW.DESIGNPROFESSIONAL.ORG

  19. LARGE ENGINEERING CLAIM • The contractor also suggested reducing construction costs by tiering one side of the building to create a stair-step • effect. The engineer noted that this revision had a significant effect on the lateral design of the building and the • distribution of the lateral loads in the north-south direction. Loads on several of the frames changed and required • redesign. The addition of a seventh floor changed the requirements on the steel framing, brace frames, and • foundations. The resulting redesign was performed on a fast-track basis. WWW.DESIGNPROFESSIONAL.ORG

  20. LARGE ENGINEERING CLAIM • The client also decided that he did not want to use mechanical units through the wall and requested a different • mechanical system. Because of this change, it was no longer possible to pass the mechanical system underneath the • steel framing—the system would have have to pass through the steel framing. The engineer was redesigning to • accommodate this request when the contractor informed the engineer that the redesign was delaying the project. WWW.DESIGNPROFESSIONAL.ORG

  21. LARGE ENGINEERING CLAIM • Back to our Questions to Consider: • Changes During Project – effect on schedule • Changes comply with permit? With code? • Communication? • DOCUMENTATION? WWW.DESIGNPROFESSIONAL.ORG

  22. LARGE ENGINEERING CLAIM • During the pouring of the second-floor slab, a portion of the metal deck adjacent to one of the stairs collapsed. • The engineer noticed that the metal deck had not been laid in conformance with the requirements of the contract • documents. In addition, the thickness of each slab varied from what the documents specified. At this time, the • contractor was fired, and the construction manager took over. WWW.DESIGNPROFESSIONAL.ORG

  23. LARGE ENGINEERING CLAIM • Back to our Questions to Consider: • Change in team/personnel? • Communication? DOCUMENTATION? WWW.DESIGNPROFESSIONAL.ORG

  24. LARGE ENGINEERING CLAIM • A project review was conducted, and it was noted that there were problems with the lateral load calculations. • Further bracing was required to accommodate any further construction. Although the engineer had revised the • framing to accommodate the design changes, he had not changed the load calculations. The construction manager • stopped the steel order and requested a review from another structural engineering firm. • Unfortunately, the client was funding this project from an $8 million profit earned from the sale of another • building. Due to tax law, he had only a limited amount of time with which to reinvest that profit, or he would have to • pay taxes on it. WWW.DESIGNPROFESSIONAL.ORG

  25. LARGE ENGINEERING CLAIM • Back to our Questions to Consider: • Owners Needs (financing, tax issues, timing, interest payments) • Direct vs. Consequential Damages • Limitation of Liability • Amount of Insurance WWW.DESIGNPROFESSIONAL.ORG

  26. LARGE ENGINEERING CLAIM • The engineer was concerned about a large claim developing as a result of the alleged delays to the project. • Although there were several possible defenses, it was clear that the engineer had exposure for failing to review and • correct the framing calculations after redesign. The engineer also failed to raise concerns about the allotted time for • the redesign. • The engineer retained an attorney, and letters were sent to the architect regarding unnecessary delays created by • the client, original contractor, and construction manager. WWW.DESIGNPROFESSIONAL.ORG

  27. LARGE ENGINEERING CLAIM • In the opinion of the structural engineer, recommended repairs were over-engineered • and would cost more than $2 million. The fees for the client’s expert exceeded $85,000, which the client wanted • the engineer to pay; this demand was rejected. The engineer’s expert suggested using lightweight concrete to reduce • the load. While the product was more expensive, the increase was only approximately $150,000. This • recommendation was followed, and the final floors were successfully poured. WWW.DESIGNPROFESSIONAL.ORG

  28. LARGE ENGINEERING CLAIM • Back to our Questions to Consider: • Early settlement or litigate? • Client management • Effect on other projects/relationship with other parties to suit • Have enough insurance? WWW.DESIGNPROFESSIONAL.ORG

  29. LARGE ENGINEERING CLAIM • The client then demanded that both the architect and structural engineer pay their full policy limits and waive all • fees for the project. The architect had a $2 million policy limit, and the structural engineer carried a $500,000 • limit. In addition, the architect began billing the structural engineer for time spent assisting with the proposed • repairs. The architect also withheld roughly $100,000 from the engineer for other joint projects. WWW.DESIGNPROFESSIONAL.ORG

  30. LARGE ENGINEERING CLAIM • At mediation, the construction manager presented an $800,000 claim for direct material and labor costs, plus • another $1.2 million for the 4.5 month delay. The client’s claim included loss of use of the facility for 4.5 months, a • $1.7 million tax loss, and a claim that there was additional vibration since the floor was constructed of lightweight • concrete. Total claims from all the parties exceeded $6.75 million. Actual damages were estimated to be closer to • $2.4 million. WWW.DESIGNPROFESSIONAL.ORG

  31. LARGE ENGINEERING CLAIM • The engineer requested settlement for the remainder of the policy limit, but due to the structural engineer’s • indemnity agreement with the architect, settlement was not possible unless the architect settled, as well. Expenses • reduced the engineer’s policy to approximately $450,000. In addition, the architect’s carrier was unwilling to offer • more than $300,000, despite a request from the architect to pay what remained of his policy limits (about $1.9 • million). Eventually, the architect settled for an undisclosed amount. The remaining policy limit was paid on behalf of • the structural engineer and, as part of the settlement, both the architect and the structural engineer agreed to waive • their fees for the project. WWW.DESIGNPROFESSIONAL.ORG

  32. GENERAL RULES TO PROTECT YOURSELF • Try to Anticipate Problems • Clearly define your scope • Have the Right Insurance Coverage • Know how a claim will by handled by • your carrier WWW.DESIGNPROFESSIONAL.ORG

  33. GENERAL RULES TO PROTECT YOURSELF • Document Your Good Work • Watch What You Say in E-Mails / Have • a Document Retention Policy that will • Protect You • CALL YOUR BROKER OR YOUR • ATTORNEY AT THE FIRST SIGN OF • PROBLEMS!!! WWW.DESIGNPROFESSIONAL.ORG

  34. QUESTIONS? Erik M. Rosenwood Hamilton Moon Stephens Steele & Martin, PLLC and Jeff Todd Insurance Management Consultants, Inc. WWW.DESIGNPROFESSIONAL.ORG

More Related