SEEP 2 – BRIEF INFORMATION Serbia, November 16, 2011. METHODOLOGY AND SELECTION CRITERIA IN SEEP TECHNICAL IMPROVEMENTS. Methodology and Selection Criteria.
E N D
SEEP 2 – BRIEF INFORMATIONSerbia, November 16, 2011 METHODOLOGY AND SELECTION CRITERIA IN SEEP TECHNICAL IMPROVEMENTS
Methodology and Selection Criteria 1 “Preliminary Energy Audits”prepared by SEEA trained energy auditors – visiting nominated buildings, determining current situation, suggestion of potential ee measures to be implemented, selection of optimal package of ee measures according to investment and pay-back and estimation of preliminary investment ee package 2 Ranking buildings according to preliminary investment and pay –back value 3 List of selected buildings, i.e. “scope of the Project”, made by line ministries 4 Based on the scope of the Project, Technical Consultant (TC) is selected for design, producing bidding documents, supervision and for monitoring “before” and “after” implementation of ee measures
Methodology and Selection Criteria 5 Based on 1, visits to schools and coordination with schools administrators and local authorities, TC recomends acceptance or revision of the originally proposed energy saving measures and makes “Evaluation Reports” for each school with suggestion of measures package and estimation of investment costs 6 Monitoring “Before” 7 Procurement procedure and selection of Contractor for works 8 Monitoring “After” and preparation of “Final Report”
Methodology and Selection Criteria 21 EE Measures savings 40% the most effective measures 1 Replacement of windows and doors 2 Thermal insulation of façade walls 3 Attic insulation 4 Hydro and thermal flat roof insulation 5 Repair works and thermal insulation of (pitched)roof covering 6 Installation of thermostatic valves with balancing combining 1 to 6 INVESTMENT PACKAGES A, B, C… 1 Investment 2 Pay back = Investment / Energy costs
Selection Criteria Preliminary investment cca 280.000 EUR – School Evaluation Report: New Boiler house = One School more Preliminary investment cca 260.000 EUR – School in Pozega Thermal insulation of roof needs roof reconstruction: 144.000 EUR Increases preliminary costs 55% End Users Request: “Jarane, nemoj mi šminkat fasadu, krov ti meni popravi!” Translation: “Listen, my friend, do not paint walls, I do not know what to do with damaged roof!” But roof reconstruction is not ee measure... Package A EE Measures cca 200.000 EUR Package B New Boiler House cca 200.000 EUR
Methodology and Selection Criteria SELECTION CRITERIA LIFE-CYCLE-COST OF THE INVESTMENT
Techical Improvements in Specifications WINDOWS • More detailed information related to manufacturing and installing windows will be presented at ES “Sveti Sava”, Velika Plana, on Friday, October 14th, 9:00h
Techical Improvements in Specifications PVC White Profiles • Six – chamber, window frame 86 – 88 mm • Lead free • Non recycled (Rehau, Veka) or recycled in inner parts (Profine) • U value is 1,1 W/m2K – compared between Rehau, Profine and Veka, Profine has U = 1,0 W/m2K (others have 1,1 W/m2K) • Guarantee – 10 years PVC Colored Profiles • Colored profiles are to be generally all-around reinforced • Guarantee – 5 to 10 years Instead of coloured profiles: ALUFUSION Al (outer part of profile) plus PVC (inner part of profile)
Techical Improvements in Specifications Double and triple glazed glass packages • U value is 1.1 for double glazed, and 0.6 for triple glazed packages • Low emission coating is applied • Argon charging • Warm edge spacer between glasses • Middle glass pane in triple glazed package has to be ultra clear low iron glass
Techical Improvements in Specifications Background Ventilation Device (BVD) • U value is max 2,3 W/m2K • A-weighted normalized sound level difference D = 27dB(A) • With insect screen • When closed, the device shall be air tight for up to 650 Pa pressure difference • Glass reduction 80 mm • Guarantee – 10 years
Techical Improvements in Specifications Façade thermal insulation • More detailed information related to producing of contact facade will be presented at Faculty of Science, Kragujevac, on Friday, October 14th, 15:00h • Picture: CC Nis, Physical Medicine and Neurology Building
Techical Improvements in Specifications Façade thermal insulation • Stone wool contact façade • Thermal insulation is mineral/stone wool, thickness d=10 cm • Instead silicate, façade finish layer shall be silicone plaster, minimum grain size 2mm • The contact façade installation procedure has been specified, and shall be done in accordance with façade manufacturer’s instructions • Works should be performed by qualified and appropriately trained workers (certified by façade system manufacturer) • Guarantee – 10 years
Techical Improvements in Specifications Wolfine membrane system for flat roof insulation • More detailed information related to Wolfine membrane system will be presented at Technical school, Smederevo, on Thursday, October 13th, 14:00h • Extremely high permeability and easy installation Reconstructions of energy supply systems • More detailed information related to rehabilitation of heating systems will be presented at Faculty of Science, Kragujevac, on Friday, October 14th, 15:00h • Renewable and alternative energy sources