Central Valley Flood Protection Board Approval of Project Cooperation Agreement Amendment No. 3, Acceleration of Partner Funds for the Folsom Dam Joint Federal Project . Folsom Dam Joint Federal Project (JFP). Multi-agency effort under the CVFPB approved Folsom Dam Modifications Project
E N D
Central Valley Flood Protection BoardApproval of Project Cooperation Agreement Amendment No. 3, Acceleration of Partner Funds for the Folsom Dam Joint Federal Project
Folsom Dam Joint Federal Project (JFP) • Multi-agency effort under the CVFPB approved Folsom Dam Modifications Project • Design and construct the JFP to meet Federal, State, and local objectives for Folsom Dam • Improves the ability to manage large flood events by lowering the spillway elevation to allow more water to be released earlier in a flood event
Project Status and Schedule 8. 2017/Q3: TESTING, COMMISSIONING & SITE RESTORATION CONSTRUCTION 9. 2017/Q3: Water Control Manual Complete 4. 2014/Q3: Control Structure Construction Complete 7. 2017/Q3: Upstream & Downstream Construction Complete 5. 2014/Q2: Cutoff Wall Construction Complete
Project Partnering Agreement (PPA) PPA (11-Feb-05) Amendment 1 (24-Aug-09) Amendment 2 (28-Apr-10) Amendment 3 – Acceleration of Funds Project Partnering Agreements- CVFPB Partner Commitments: • October 2017 Optimal Completion • Actively seek opportunities to accelerate the schedule
FY 12 Funding and Obligations(Oct 2011 – Sept 2012) Funding: • FY12 USACE Optimal Capability = $28M • FY12 President’s Budget = $21M • House Sub-Committee Budget = $19.028M • Continuous Resolution Ending Nov 18 = $8.1M Obligations:
Staff Recommendation Staff recommends that the Board approve Resolution No. 11-30 (Attachment C) and: • Approve Amendment No. 3 (Attachment A) to the PCA authorizing the acceleration of funds to the USACE in an amount not to exceed the current estimate of the non-federal sponsors’ required cash contribution for the JFP, less any funds previously contributed, for the immediate use by the USACE and; • Delegate to the Board President the authority to execute the amendment in substantially the form attached hereto.
Questions? CVFPB: Kent Zenobia, PE, DEE kzenobia@water.ca.gov Wilbur Huang, PE, CFM whuang@water.ca.gov USACE: Elizabeth Salyers, PE Elizabeth.A.Salyers@usace.army.mil
What is the JFP? • A new auxiliary spillway adjacent to the main dam, including: • approach channel • control structure • spillway chute • stilling basin • Improves the ability to manage large flood events by lowering the spillway elevation to allow more water to be released earlier in a flood event.
Background JFP will work in conjunction with upgraded levees downstream to achieve a 200-year level of protection.
Background Schedule History • Original schedule – 2015 completion • 35% design • accepted as baseline schedule • Revised schedule – 2018 completion • More detailed design • Reviewed & recommended by consultants • Unsatisfactory to all parties • Joint task force revised schedule – 2017 completion
Commitments • October 2017 completion: Optimal Completion Date • Aggressive • Realistic • Weighs risks and rewards developed by Task Force • The USACE will continue to seek opportunities to accelerate the schedule
Schedule: Milestones & Critical Path Final Design and Deliverables: • Cut-off Wall 95% Review 13 April 2012 Upstream and Downstream Design 95% Review 5 October 2012 Record of Decision (ROD) Signed 31 Mar 2013 Control Structure: Bulkhead Gates Installed 15 July 2014 Contract Complete 3 October 2014 Cut off Wall (schedule being refined) NTP 1 April 2013 Contract Complete (NLT) 16 January 2014 Chute and Stilling Basin & Approach Channel: NTP 30 August 2013 Contract Complete 30 October 2017 • Contract Complete (Commissioning and Testing) 30 October 2017
Control Structure • Status: 14%Complete • Rockbolting & Blasting • Accelerated Schedule due 28 Dec 11 • Bulkhead Gates installed 15 July 2014
Project Partnering Agreement – Department of Water Resources Signed 11-Feb-05 Amendment 1 signed 24-Aug-09 Amendment 2 signed 28-Apr-10 Amendment 3 – Acceleration of Funds Memorandum of Agreement – Bureau of Reclamation Signed 22-Aug-06 Land Use Agreement – Bureau of Reclamation Signed 16-Sep-10 Memorandum of Agreement – Sacramento Area Flood Control Agency (Restoration) Amendment signed 24-Jul-08 Project Partnering Agreements Partner Commitments: • October 2017 Optimal Completion • Aggressive and Realistic • Weighs risks and rewards developed by Task Force • We will continue to actively seek opportunities to accelerate the schedule if/when options arise within funding limits
Current Schedule Milestones Final Design and Deliverables: Chute and Stilling Basin 65% Review 30 November 2011 (A: 30 Oct 2011 Cutoff wall/Rock Plug Decision Point 10 November 2011 (A) Cofferdam 35% Review 14 November 2011 (A: 10 Nov 2011) Approach Channel 65% Review 17 February 2012 • Administrative Draft EIS 13 March 2012 • Cut-off Wall 95% Review 13 April 2012 Upstream and Downstream Design 95% Review 5 October 2012 RTA Follow-On Phases 7 December 2012 Record of Decision (ROD) Signed 31 Mar 2013 Control Structure: Bulkhead Gates Installed 15 July 2014 Tainter Gates Installed 15 August 2014 Contract Complete 3 October 2014 Cut off Wall NTP 1 April 2013 Contract Complete (NLT) 16 January 2014 Chute and Stilling Basin & Approach Channel: NTP 30 August 2013 Contract Complete 30 October 2017
Current Schedule Critical Path Final Design and Deliverables: Record of Decision (ROD) Signed 31 Mar 2013 • Cut-off Wall: • NTP 1 April 2013 • Construction Complete (NLT)** 16 January 2014 Control Structure: Bulkhead Gates Installed 15 July 2014 Approach Channel: Start Rock Plug Excavation** 16 January 2014 Walls and Slabs 24 June 2016 Wet Excavation 21 September 2017 Chute and Stilling Basin : Chute and Stilling Basin work will run concurrently with Approach Channel work with Approach Channel driving the critical path Contract Complete (Commissioning and Testing) 30 October 2017 ** Cut-off Wall schedule currently being refined
Control Structure • Status: 14%Complete • Rockbolting and Blasting. • Accelerated Schedule due 28 Dec. Milestone Dates May 07ROD 24 Sep 10Contract award (Continuing Contract/design bid build) 6 Dec 10 NTP 16 Sep 11 Design revision 4 modification award 31 Oct 11 Design revision 1, 3 & 5 modification award 30 Nov 11 Design revision 2 and 6 modification award 28 Dec 11 Recovery Schedule due 15 Jul 14 Bulkhead Gate Completion (critical path) 15 Aug 14 Tainter Gate Completion (not critical) 2 Sep 14 Substantial Completion (not critical) 3 Oct 14 Construction Complete (not critical)
Control Structure • Status: 14%Complete • Rockbolting and Blasting • Accelerated Schedule due 28 Dec 11 Milestone Dates 6 Dec 10 NTP 28 Dec 11 Recovery Schedule due 15 Jul 14 Bulkhead Gate Completion 15 Aug 14 Tainter Gate Completion 3 Oct 14 Construction Complete