GAUSS Work plan

GAUSS Work plan. Software Week 6 March 2002 F.Ranjard / CERN. Contents. Work plan set in October 2001 Gauss today Planning. Work plan as set in October 2001. GAUSS should be able to read HepMC files is done A task for GAUDI

reynold
Download Presentation

GAUSS Work plan

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. GAUSS Work plan Software Week 6 March 2002 F.Ranjard / CERN

  2. Contents • Work plan set in October 2001 • Gauss today • Planning GAUSS Work plan

  3. Work plan as set in October 2001 • GAUSS should be able to read HepMC files is done • A task for GAUDI • GAUSS should be able to write an output at various levels of the processing and to restart the processing from where it was stopped. is done • A task for GAUDI (writing) and GAUSS (reprocessing) • GAUSS should be able to simulate various setups selected with job options. • A task for GAUDI (condition data base) and GAUSSnot yet done (see Sebastien’s talk on Friday) These tasks do not need all detectors in , they could be achieved by June 2002.Will be achieved before June 2002 GAUSS Work plan

  4. Gauss today • The following packages have been installed yesterday on Lxplus. • Gen/GeneratorModules/v1r0 ATLAS origin • Gen/GeneratorObjects/v1r0 • Gen/GeneratorUtils/v1r0 • Gen/Pythia_i/v1r0 • Gen/PYTIA/v61r52 interface package • Sim/HepMC/v1r2 ATLAS package • Sim/GiGaCnv/v4r0 • Sim/Gauss/v1r0 application package GAUSS Work plan

  5. Update of the work plan http://lhcb-comp.web.cern.ch/lhcb-comp/Simulation/planning/GAUSS.html GAUSS Work plan

  6. Planning • We still expect to have a framework with full functionality by June 2002. • That would allow to add detectors when they are ready to come in. GAUSS Work plan