230 likes | 263 Views
Explore Austin Commercial's approach to forecasting change in construction projects through regression models, analyzing RFI's and new drawings impact on cost. The study delves into data collection, regression modeling techniques, and the application of forecasts.
E N D
Forecasting Models Forecasting Change in the Construction Industry By: David Walls
Austin Commercial • Large Construction Manager • Based in Texas • Operations throughout the United States • Past customers include: • Intel • Texas Instruments • Exxon • EDS • FED • SMU
Austin Commercial’s Problem • Problem: Dealing with change in construction • Large amount of changes taking place • Not taking into account the impact the changes have later in a project • Uncertainty in knowing what was causing change and what impacts change had
Problem Analysis • Discussions with Austin’s Management • Two main indicators of change in a construction project • RFI’s (Request for Information) • New drawings issued • Austin’s needs: • A way to predict potential changes at any given point in project • Impact of those changes on cost
Research and Data Collection • Designed a spreadsheet to collect data • RFI’s and new drawings broken down monthly over the life of the project • Broken down into Divisions • Architectural • Structural • Civil • Mechanical • Electrical • Cost Information • Compiled a list of Project that were wanted
Projects • Akin, Gump, Strauss, Hauer, and Field Project • Alcon Laboratories Building G Project • Austin Ventures Project • CarrAmerica Project • Clark, Thomas, and Winters Project • Crossmark Project • CTW Storage/Fitness Center Project • Ft. Worth Convention Center Phase 1 Project • Ft. Worth Convention Center Phase 2 Project • Hall Office Project • Love Field CUP Project • Mabel Peters Caruth Center Project • Terrace V Project (RFI info only) • TriQuint Semiconductor Project • University of North Texas Recreation Center Project • University of Texas Southwestern Medical Center Project
Situation Analysis • Calculated the Percentage of RFI’s and new drawings that were complete at key points in a project (10% 25% 50% 75% 100%) • By division and Total • Decided to use regression modeling • Could obtain the most accurate fit of the relationship between the inputs and outputs of the project
Regression Models • Two Regression Models • Cubic (polynomial) Regression Model • “best fit” line (cubic) for the relationship between the percentage complete in the job and the percentage of the RFI’s or new drawings issued out of the total • Multiple Regression Model • Best fit (linear) for the relationships between the costs of a project and totals for RFI’s and new drawings and initial budget
Cubic Regression Model • Used Minitab to solve a cubic regression model • For total RFI’s and by division • For total new drawings and by division • Allow forecast of total RFI’s and total new drawings by division at the end of the project
Multiple Regression Models • Two Models were solved: • The total change in cost on a project • The overall total cost of a project • Based on the historical totals for RFI’s and new drawings by division, and Austin initial forecasted budget
Two Models • Using both models together • Forecast total for RFI’s and new drawings based on initial input of percent complete of the job and current totals of RFI’s and new drawings • Use those forecast to forecast the total change in cost of the project and overall total cost of project
Model Output • Cubic Regression Models • High R-squared terms • Civil models had highest R-squared terms – also had largest confidence intervals • Architectural models had S-squared terms of 100% - had the smallest confidence intervals • Multiple Regression Models • High R-squared terms • Total RFI and Civil RFI variables seemed too have largest influence in both models • Low probability that there terms where zero • Total cost model more accurate that total change in cost model • Significantly higher F-ratio and corresponding P-value (probability) • Overall both models were strong and did good job of representing the data
Recommendations • Austin should use these models to help forecast RFI’s and new drawings issued and their cost impacts • Spreadsheet to allow Austin use these forecast models • Austin should collect monthly RFI and new drawings issued information on all of its jobs • Give current information to run forecasts with • Provide historical data to add to current models to make more accurate • Conclusion: With the help of these models and Austin Commercial’s realization and efforts to solve this change management problem, I believe Austin Commercial can set itself apart from its competitors and better serve its customers in the long run.
Assumptions and Limitations • Only uses data from last 3 years – assumes last 3 years is indicative of future • Projects that were used for data ranged from cost of about $500,000 to $50,000,000 – model may not be accurate for extremely large projects • Assumes RFI’s and new drawings issued are the best indicators for change in a project • Amount of projects used - Would have like to included more projects in the data (hopefully more data will be available in the future)