REVISED 60% PLAN APPROVAL. Presentation Outline. Board Direction 60% Plan Modifications Cost Estimates Project Timeline Recommendation. Board Direction. Approved motion from March 2009 Reconstruct 91 st Street keeping the travel lanes at their current width
E N D
Presentation Outline • Board Direction • 60% Plan Modifications • Cost Estimates • Project Timeline • Recommendation
Board Direction • Approved motion from March 2009 • Reconstruct 91st Street keeping the travel lanes at their current width • Keep power lines in the current alignment • Construct an 8’ foot wide multi-use path at the edge of the right-of-way • Move or narrow to ensure no trees are damaged • Maximize the potential for new tree plantings
Typical Cross Section 2’ CURB & GUTTER 6’ SHOULDER (2’ PAVED) VEGETATED AREA VARIES VARIES VARIES 20’ 8’ 66’-100’
New Tree Plantings Add 10-15 Live Oaks Existing underground utilities
Intersection Modifications Reduced radius and removed taper Extend curb and gutter through radius
Estimated Costs Road resurfacing Paved shoulder Multi-use path Resurface path $1,016,000 $33,000 $27,000 $1,076,000 Widen and resurface path $1,016,000 $33,000 $51,000 $1,100,000 Relocate & widen path $1,016,000 $33,000 $71,000 $1,120,000 Maximum cost difference = $44,000
Project Timeline Bid award and contract approval by BoCC 90% plan approval by BoCC
Recommendation • Approve the 60% design plans as presented and direct staff to proceed with production of 90% plans.