Donella Drive ImprovementsPublic Meeting Presented By: Kyle Gass, PE, CFM Date: October 19, 2015
Donella Drive ImprovementsProject Team Town of Hollywood Park San Antonio Water System (SAWS) CPS Energy Grady Carlson (SpawGlass Project Executive) Kyle Gass (CEC Project Manager) David Costales (CEC Project Engineer) Telephone: 210-798-9292
Replace Water and Gas Mains within project limits. • Install storm drain and improve roadside ditches to convey stormwater • Reconstruct concrete driveways from edge of pavement to right of way • Reset mailboxes. (Temporary community mailbox will be installed on Mustang Circle for mail delivery and collection during construction.) • Detour routes will be implemented to direct traffic around the construction area. Local access will be maintained for all residences. • Project updates will be posted on the Town of Hollywood Park Website: http://hollywoodpark-tx.gov/donella-street-project Donella Drive ImprovementsOther Work Items
Donella Drive ImprovementsSequence of Work Contractor will first construct new water and gas mains. Contractor will then begin constructing storm sewer, reclaiming existing roadway, and paving new surface. Contractor will then grade roadside ditches and build concrete curb, driveways, and riprap. Roadway and drainage construction will start to Lorence Creek and progress towards US 281. Then, construction will move back to Mustang Circle and move towards Lorence Creek. The final steps will be placing new signage and resetting mailboxes.
Donella Drive ImprovementsContract Duration and Value Duration 6 months (finish late April) Contract Value Town of Hollywood Park $ 1,181,000.28 SAWS (Water) $ 505,809.20 CPS (Gas) $ 524,257.80 Project Total $ 2,211,067.28
August 09, 2015 Began Advertising Project August 18, 2015 Held Pre-Bid Conference August 21,2015 Qualification Statement Deadline August 27,2015 Issued Request for Bids September 14, 2015 Opened Bids September 16, 2015 Recommended SpawGlass to be awarded the project as the Qualified Low Bidder September 22, 2015 Council approved SpawGlass Donella Drive ImprovementsSchedule of Events
Donella Drive ImprovementsSchedule of Events, cont. October 8, 2015 Held Pre-Construction Meeting October 19, 2015 Public Meeting October 21, 2015 Groundbreaking Ceremony