LTI magnet installation preparation. Situation: General services works is starting (TT40 already done) One more year to go before bulk installation (~ 400 magnets). !. Aims: Clarify responsibilities Produce detailed planning (initial granularity ~ month)
E N D
LTI magnet installation preparation Situation: General services works is starting (TT40 already done) One more year to go before bulk installation (~ 400 magnets) ! Aims: Clarify responsibilities Produce detailed planning (initial granularity ~ month) Identify open points + actions to be taken Scope: Magnets Magnet accessories (supports, bus bars, …, connections, …) Components to be fitted to magnets (vacuum chambers, BPMI, …) Handling devices (+ storage / working space)
TI 2 / TI 8 overall layout, commissioning milestones • combined length 5.6 km • over 700 room-temperature magnets (74 recup’d) http://proj-lti.web.cern.ch/proj-lti/ TI 8 late 2003 … early 2004 TI 2 04/2007 Q4/2004
http://edms.cern.ch/file/90193/4.0/LHC-PM-EM-0001-40-00.pdf New
2002 2002 2003 2003 2004 2004 2005 2005 2006 2006 Planning Framework using warm line @ IP8 Sector test “Old”: Injection test early 2004 TI 8 test late 2003 LSS4 extraction test early 2003 New: SPS stop Sector test LSS4 extraction test Q3/2003 TI 8 start HW tests late 2003, tests with beamearly 2004 Injection test early 2006
TT40 / TI 8 installation planning 2002 2003 http://edms.cern.ch/file/323089/1.0/LHC-TI8-MS-0001-10-00.pdf TI 8 beam line installation (via UJ88) TT40 beam line installation (via ECA4) TI 8 start HW tests ? Now Extraction tests
TT40 access gallery to neutrino target area (TAG41) link tunnel TAG42 access gallery TA40 ECA4 PGC8 TED chicane STOP TJ8 TT41 TT40 SPS Beam here in Q3/2003 TI 8 SD 01/02 - TT40 services installation SD 02/03 - TT40 magnet installation
Transfer line TI 8 TED Installation and start HW tests 2003 STOP D(m) Beam here early 2004 s(m)
Aims • Not dig into technical details ! • Clarify responsibilities • Produce detailed planning (initial granularity ~ month) • Identify open points + actions to be taken • Decide on way and frequency of follow-up • Identify / update (still open) link persons