LTI magnet installation preparation

LTI magnet installation preparation. Situation: General services works is starting (TT40 already done) One more year to go before bulk installation (~ 400 magnets). !. Aims: Clarify responsibilities Produce detailed planning (initial granularity ~ month)

rob
Download Presentation

LTI magnet installation preparation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. LTI magnet installation preparation Situation: General services works is starting (TT40 already done) One more year to go before bulk installation (~ 400 magnets) ! Aims: Clarify responsibilities Produce detailed planning (initial granularity ~ month) Identify open points + actions to be taken Scope: Magnets Magnet accessories (supports, bus bars, …, connections, …) Components to be fitted to magnets (vacuum chambers, BPMI, …) Handling devices (+ storage / working space)

  2. TI 2 / TI 8 overall layout, commissioning milestones • combined length 5.6 km • over 700 room-temperature magnets (74 recup’d) http://proj-lti.web.cern.ch/proj-lti/ TI 8 late 2003 … early 2004 TI 2 04/2007 Q4/2004

  3. http://edms.cern.ch/file/90193/4.0/LHC-PM-EM-0001-40-00.pdf New

  4. 2002 2002 2003 2003 2004 2004 2005 2005 2006 2006 Planning Framework using warm line @ IP8 Sector test “Old”: Injection test early 2004 TI 8 test late 2003 LSS4 extraction test early 2003 New: SPS stop Sector test LSS4 extraction test Q3/2003 TI 8 start HW tests late 2003, tests with beamearly 2004 Injection test early 2006

  5. TT40 / TI 8 installation planning 2002 2003 http://edms.cern.ch/file/323089/1.0/LHC-TI8-MS-0001-10-00.pdf TI 8 beam line installation (via UJ88) TT40 beam line installation (via ECA4) TI 8 start HW tests ? Now Extraction tests

  6. TT40 access gallery to neutrino target area (TAG41) link tunnel TAG42 access gallery TA40 ECA4 PGC8 TED chicane STOP TJ8 TT41 TT40 SPS Beam here in Q3/2003 TI 8 SD 01/02 - TT40 services installation SD 02/03 - TT40 magnet installation

  7. TT40, looking towards TJ8

  8. Transfer line TI 8 TED Installation and start HW tests 2003 STOP D(m) Beam here early 2004 s(m)

  9. Aims • Not dig into technical details ! • Clarify responsibilities • Produce detailed planning (initial granularity ~ month) • Identify open points + actions to be taken • Decide on way and frequency of follow-up • Identify / update (still open) link persons