Proton source shutdown schedule

Proton source shutdown schedule. Mary Convery 4/18/11. Shutdown scheduling ( Linac ). NTF can only be off for ~2 months When RFQ is ready (unknown!!!) All RFQ and Linac tunnel work will take place while NTF off 2 mech support vacuum crews (split Ben’s crew)

roch
Download Presentation

Proton source shutdown schedule

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Proton source shutdown schedule Mary Convery 4/18/11

  2. Shutdown scheduling (Linac) • NTF can only be off for ~2 months • When RFQ is ready (unknown!!!) • All RFQ and Linac tunnel work will take place while NTF off • 2 mech support vacuum crews (split Ben’s crew) • Biggest Linac job is momentum dump sleeve • Mech support work in Booster will be limited during that time (try to keep BRF cavity refurbishment going) • Scheduled ~8 months of Linac gallery work (most while supporting NTF)

  3. Shutdown scheduling (Booster) • Then ~6 weeks for Booster girder moves for aperture (run beam between moves) • Will be chances for continuing Booster RF and some Linac work during this time • Penciled in RF cavity swaps for tuner refurbishment roughly every 25 days • Only real difficulty scheduling will be during RFQ installation • Solid state work can take place basically at its own pace • Booster absorber schedule not finalized yet

  4. Support manpower • Mechanical support vacuum: Ben, Jason, Justin + 2 players to be named later • Water group: no specific crew assigned • FESS contractors will do return pump and return piping to CUB job • Electricians: will likely be moved back and forth between MI and proton source to keep them busy • Alignment: aware of our jobs

  5. Shutdown schedule • Available from proton source homepage under schedules or • http://www-ad.fnal.gov/proton/protonsched/shutdown2012.html • shutdown worklisthttp://www-ad.fnal.gov/worklist • submit jobs with “Shutdown 2012” in the description