Keck NGAO Project Replan: AO and Laser Systems

Keck NGAO Project Replan: AO and Laser Systems. Donald Gavel NGAO Team Meeting 6 April 25, 2007. AO and Laser Systems Project Replan: Outline of Presentation. Program plan overview Purpose and approach of the replan Key changes highlighted

roddy
Download Presentation

Keck NGAO Project Replan: AO and Laser Systems

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Keck NGAO Project Replan:AO and Laser Systems Donald Gavel NGAO Team Meeting 6 April 25, 2007 Don Gavel: Keck NGAO meeting April 25, 2007

  2. AO and Laser Systems Project Replan:Outline of Presentation • Program plan overview • Purpose and approach of the replan • Key changes highlighted • Feedback from the team on schedule & level of effort Don Gavel: Keck NGAO meeting April 25, 2007

  3. AO and Laser System Program Overview • AO and Laser System Design phase follows the system engineering / trade studies phase • Inputs: Architecture Definitions, Study results, FRDs v.1 (June/July time frame) • Outputs: Contributions to System Design Manual & FRDs v.2 (= Conceptual Design or Proposal level => raising funding to build) Don Gavel: Keck NGAO meeting April 25, 2007

  4. Purpose and Approach of the Replan • Problem: present plan is behind schedule. • Approach: given currrent status and lessons learned, adapt the plan to achieve key goals using the resources available • Play to people and institutional strengths • Streamline the work – fewer people at higher percentage • Level the plan and tie to people availability Don Gavel: Keck NGAO meeting April 25, 2007

  5. Overview of changes in 3.2, 3.3 • WBS 3.2 AO System. • Reshuffling of personnel on four tasks. • Two new tasks: • atmospheric profiler • d-IFU & LOWFS AO & Object Selection (broken out from WBS 3.5) • WBS 3.3 Laser Facility. Reshuffling of personnel on three tasks. Don Gavel: Keck NGAO meeting April 25, 2007

  6. Changes to 3.2, 3.3 Don Gavel: Keck NGAO meeting April 25, 2007

  7. Program Plan Changes – 3.2 Details Don Gavel: Keck NGAO meeting April 25, 2007

  8. Program Plan Changes – 3.3 Details Don Gavel: Keck NGAO meeting April 25, 2007

  9. Team Feedback • WBS definitions correct and unambiguous • Objectives feasible in the time allocated • Availability, time commitment Don Gavel: Keck NGAO meeting April 25, 2007