1 / 23

Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation

Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation. PROJECT LOCATION. TH 47 BR 46. Meeting Outline. Purpose of the Meeting Structures Section re-organization Existing bridge deficiencies Alternatives considered Summary and recommendation-.

ronnie
Download Presentation

Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Enosburg BRO 1448(40) Bridge 48 on TH 2 Over the Tyler Branch Alternatives Presentation

  2. PROJECT LOCATION TH 47 BR 46

  3. Meeting Outline • Purpose of the Meeting • Structures Section re-organization • Existing bridge deficiencies • Alternatives considered • Summary and recommendation-

  4. Purpose of Meeting • Present the alternatives that we have considered • Explain the constraints to the project • Help you understand our approach to the project • Provide you with the chance to ask questions. • Provide you with the chance to voice concerns • Build consensus for the recommended alternative -

  5. Phases of Development • Project • Funded • Project • Defined • Contract • Award Project Definition • Project Design • Construction • Identify resources & constraints • Evaluate alternatives • Public Participation • Build Consensus • Quantify areas of impact • Environmental permits • Right-of-Way Process • Utility Coordination • Develop plans, estimate and specifications

  6. Accelerated Bridge Program • Began in January 2012 • Bridges are deteriorating faster than we can fix them • Accelerated Bridge Construction (ABC) is key • Impacts to property and resources is minimized • Standard details repeated on many projects • Shift from individual projects to programmatic approach • Accelerated Project Delivery • Goal of 2 year design phase for ABP (5 years conventional) • Goal of 25% of projects into Accelerated Bridge Program-

  7. Project Initiation & Innovation Team • Part of re-organization in January 2012 • Currently team of 5 • All projects will begin in the PIIT • Very efficient process • Look for innovative solutions whenever possible • Involved until Project Scope is defined • Hand off to PM to continue Project Design phase -

  8. Project Background • Priority 20 in the Town Highway Bridge Program • The structure is owned and maintained by the Town • TH 2 is a Class 2 Town Highway • Existing bridge is a single-span steel beam bridge with a concrete deck (replaced with temporary Mabey bridge) • Span of 47 feet and width of 18 feet • The bridge was built in 1924 • Bridge is structurally deficient and has a Federal sufficiency rating of 9.0 (out of 100) -

  9. Project Background (Cont) • Traffic Data • Design speed = 50 mph (Note: 4 way stop proposed)

  10. Description of Terms Used Beams (Superstructure) Bridge Rail Deck Abutment (Substructure)

  11. EXISTING BRIDGE DEFICIENCIES • Deficiencies • The deck, superstructure and substructure are in critical to poor condition • The bridge width does not meet the current standard. • Inspection Report Information (Based on a scale of 9) • Deck Rating 3 Critical • Superstructure Rating 4 Poor • Substructure Rating 4 Poor • Channel Rating 5 Fair

  12. Width of Bridge 18’

  13. Bridge Side View

  14. Existing Site Conditions • Bridge Width (Face-Face Rail) = 18’-0” • Design Speed Limit = 50 mph (Note: 4 way stop) • No Postings for Weight Restriction • Overhead Utilities present (cross over bridge)-

  15. Layout Showing Constraints

  16. Proposed Project • Complete bridge replacement warranted • Use 10’ lanes w/ 2’ shoulders (24’ rail-rail width) • Approximately 48’ span • Improved intersection w/ 4 way stop -

  17. Alternatives • Full replacement w/ abutments on bedrock

  18. Proposed Bridge Typical

  19. Alternative 1

  20. Alternative 1 Profile

  21. Bridge Closure Details • 4 week closure specified in contract • Timing of closure will be made w/ input from Town (to minimize community impacts) • Town responsible for detour route (location, signing, installing, maintaining) • One route adds 3 miles and is 11 miles end-end • Local share cut in half w/ closure-

  22. Alternatives Matrix

  23. Questions

More Related