Nushagak Cooperatives Inc. July 30, 2007 Quarterly ReportDenali Commission Including JW cooling system upgrade Insulation of Supplemental heat piping
Quarterly work report • Continuing installation J/W system • Preliminary work performed to facilitate installation of Generators 14 and 15. • ASRC Energy personnel to arrive on July 25, 2007 to assess Tank Liner work. • Preliminary work performed to facilitate installation of new station service transformers.
Work to be Completed-Remainder of 2007 • Complete J/W cooling system Superior side • Replace Tank Farm liner by 12/30/2007 • Install 2 Ea. Pad mount station service transformers (arriving on Sept Barge). • Install 2 Ea. Caterpillar 3512C Generator sets, Units 14 and 15(arriving Sept Barge).