90 likes | 109 Views
Electron Systems Overview. David Schultz. 2 month delay in Injector Impact and plan Later talks to cover: Injector/Linac Management, E. Bong Injector/Linac Installation Status, C. Rago. Installation Schedule. 250 MeV. 4.30 GeV. 13.6 GeV. 6 MeV. 135 MeV. Linac- X L =0.6 m.
E N D
Electron Systems Overview David Schultz • 2 month delay in Injector • Impact and plan • Later talks to cover: Injector/Linac Management, E. Bong Injector/Linac Installation Status, C. Rago
Installation Schedule 250 MeV 4.30 GeV 13.6 GeV 6 MeV 135 MeV Linac-X L =0.6 m Linac-0 L =6 m rf gun L0-a,b Linac-1 L 9 m Linac-2 L 330 m Linac-3 L 550 m 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC2 L 22 m BC1 L 6 m ‘Wall region’ DL2 L =275 m 2007 down Now through Dec. SLAC linac tunnel research yard
LCLS Installation and Commissioning Time-Line Drive-Laser Commissioning LTU/und. Install LTU/und. hall “ready” Drive-Laser Installed Controls Checkout First Spont. Light A S O N D J F M A M J J A S O N D J F M A M J J 2006 2007 2008 No Ops Gun/Inj./BC1 Install (8/21 – 2/20) Gun/Inj./BC1 Commissioning Inj./Linac/BC2 Commissioning linac/BC2 Install LTU/und. Commissioning Oct. 19, 2006
2006 Installation Sector 21 Sector 20 Laser stopper BLM BC1 LX L1 Ins/SAB Wall
Linac Tunnel Installation Issues • Late: • Need to lock-up and begin Linac beam operations Jan. 2. • A few components will not make the lock-up deadline. • Vacuum chambers in insertion region. (Jan. 07) • BC1 Instrument package. (Jan. 07) • Toroids (in several locations) • BLM 11 (BLM 12 will be in) • Linac Access will be available to install these. • These are not on the Injector commissioning critical path.
Injector Vault Installation Issues • Late: • The GTL support stand. • Will be here 11/16 • Laser table install, optics transport commissioning follows. • The Gun will be ready.
Gun-to-Linac area Laser table To L0a Spectrometer GTL Gun GTL table
Injector Vault Installation Issues • GTL beamline is late, now in machining. • Completion date is 2/8, we are pushing to advance this date and to stage delivery. • Stage delivery to advance laser vitual cathode commissioning, if possible. • This leads to a 2 month delay to e- commissioning. • January – February: • Laser commissioning • Controls checkout • RF processing of L0a and L0b • The 2007 commissioning goals will still be met.
Commissioning Schedule 250 MeV 4.30 GeV 13.6 GeV 6 MeV 135 MeV Linac-0 Linac-X rf gun L0-a,b Linac-1 Linac-2 Linac-3 25-1a 30-8c 21-3b 24-6d ...existing linac 21-1 b,c,d undulator L =130 m X BC2 BC1 3/07 – 8/07 5/08 - 12/07- 4/08 SLAC linac tunnel research yard