1 / 15

Installation and Fabrication Progress Update

Update on progress for the fabrication and installation of piping and utilities in preparation for system upgrades and detector installations. Includes detailed tasks, orders, and completed work. Safety reviews and technician vacation schedule also provided.

rtim
Download Presentation

Installation and Fabrication Progress Update

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progress Completed Order/Fabricate SS Piping for HBD Purge gas from all detectors DAQ tests Prep. for Shutdown work (open doors, move carriages, etc. Pave access to gas pad/mixing house/1008 South Fit up “Bridge” and mark CM for drilling Measure Bridge area for utilities support Remove Bridge, drill & tap CM for Bridge Install Bridge MuRPC-remove Caen Crate, remove all wiring and plumbing, remove prototype panels Remove all TOF West Prototype wiring/piping Relocate Crates On MMS Backplate For Improved Access Prepare EC for subsystems work Remove MVD Install Measureflos in cooling circuits

  2. Progress Completed • Design Mounting For Central Region Detector Upgrades • Final Design: TOF West panels • Design Mounting/Install'n for TOF West Full Sector Coverage • Install SS pipe for HBD Gas Pad to Mixing House, Mix House to IR Sill • Install TOF West Vent Stack from mixing house • Bridge utilities support plan • Upgrade IR AC Controls and monitoring • MuTr-Install new LV cables North & South • MuTr- Glink/Clink & HV repairs • Install Gas Supply/Return/ Vent for TOF West

  3. Progress In Progress • Complete Installation of Rack Room AC’s ands Controls (ductwork) • Design Mounting/Install'n for TOF West Full Sector Coverage • Order/Fabricate Parts for TOF W • Upgrade IR AC Controls and monitoring • MuTr-FEE dead board replacements North & South • Assemble and Install TOF Gas system in Mixing House • Assemble/Install HBD Gas system and transparency monitor in AH • TEC Work

  4. Coming Up • Replace emergency fan louvres - CA • Rewire/add IR Ceiling lights on emergency power - CA • Replace WC sliding platform hoisting cables - CA • Install access platforms from EC top north and MMS eyebrow - CA • Sectors 7 and 8 Work - CA • Repower IR equipment from interlocked PS per stillpoweredup.txt list • Analyze/balance rack water distribution/measureflo for Rack Room - CA • HBD – Install Mounting and Support provisions • Install TOF West Installlation guide • Receive TOF West panels from VU/Prepare Installation • TOF West – Install Full sector 4-panel coverage • Receive HBD Detector for Installation/Prepare for installation • HBD – Install Services, Install Prototype/Preliminary Model • E carriage roll in & setup & Prepare for Run • TOF West & HBD Safety and Final Design Reviews

  5. BridgeUtilities Central Magnet Platform Utilities Plan • Water supply and return tap into East Carriage Branch supply and return hard piping below NMM. • Run hard pipe (2”) up east side of NMM without blocking access hatches or lampshade removal. • Flexible loop to supply and return manifolds underneath platform as close to east edge as possible. (2” Manifolds run full north-south length of platform with tees perpendicular to location of each crate (9 crates) solenoid, measurflo and ¼ turn manual ball valve on each supply tee. • 12 “ cable tray with divider for HV runs full length of platform just below platform on east side of CM flux return. • Piping and cable trays to be installed after CM platform is installed using manlift and access from platform by removing sections of grating. • Plumbers to install risers to flexible loop. Phenix to install manifolds

  6. BridgeUtilities Tap into Supply & Return Near Base of NMM

  7. BridgeUtilities Supply and Return are routed along NMM south of access panel Feed for Bridge electrical. Fed from a junction box below East carriage

  8. BridgeUtilities Electric Distribution panel with feed down to CM replaces old Supply and Return Manifolds mounted under platform on east side of Flux Return 12 inch cable tray Divided for HV and Signal under Bridge near front edge feed

  9. BridgeUtilities Access to Work on Cable trays and manifolds by lifting out grating and from manlift

  10. BridgeUtilities Racks to be in single row down center of platform over middle grating. North most section is open to allow access to front and back of racks

  11. Access to top of MMS for MuTr FEE replacement

  12. Next Week • Gas piping work for HBD & TOF West • Order/Fabricate TOF west & HBD installation parts • Fan Trays • MMS MuTr FEE replacement (top) • Fabricate HBD and TOF W Mockups • TEC Work • Bridge plumbing and electric • Prepare for annual safety review, TOF W and HBD safety reviews

  13. Excess Vacation Carry over • Marino,Salvatore F 5 Days • Biggs,John C 7.25 Days • Tradeski Jr,John W 12.25 Days • Jones,Kenneth B 3.25 Days • La Bounty,James J 11 Days • Desmond,Edmond J 5.5 Days • Pisani,Robert P 9.94 Days • Lenz,Michael D 7 Days • Lenz,William E 4 Days • Lynch,Donald R 4 Days

  14. Safety Nugget: Don’t Do This !!

  15. If you think your job stinks …

More Related